Keeping Detailed Records: The Best Defense to Constructive Eviction
October 24, 2023 —
Ben T. Welch & Ken Brown - Snell & WilmerInevitably, commercial property owners and managers will be faced with a claim by a tenant of constructive eviction. This article is intended to describe what constructive eviction is and to suggest what owners and managers can do to prepare for, and ward off, such claims.
Constructive eviction occurs where a tenant’s “right of possession and enjoyment” of the leasehold is disrupted by the landlord in a manner that renders the premises “unsuitable for the purposes intended.”i Put another way, it is interference that is so “substantial nature and so injurious as to deprive the tenant of the beneficial enjoyment of a part or the whole of the demised premises.”ii Although easy to describe in theory, constructive eviction can be devilishly difficult to determine in the real world. In litigation, determining when interference crosses over the line to constructive eviction is intensely fact-sensitive and resists sweeping generalizations.iii
For instance, Utah courts have held that tenants have been constructively evicted when they have been subjected to continual harassment or insults by the landlord or the landlord’s agent,iv prevented or impaired in their access to the leased premises during operating hours,v or when a landlord fails to provide an operable elevator (or other essential commercial amenities) necessary for a tenant’s business operations.vi By contrast, claims of “discomfort” or “inconvenience” have been rejected as a basis for constructive eviction.vii The same goes for claims that a landlord wrongfully served a three-day notice to pay or quit.viii
Generally, constructive eviction is an affirmative defense made in response to a landlord’s lawsuit for nonpayment of rent.ix It is not, as is commonly supposed, a basis for a tenant’s premature abandonment of the premises. In other words, the defense is raised after the tenant has vacated as a result of being effectively “evicted.”x Further, the defense requires the tenant to actually abandon the premises and do so within a “reasonable time” after the alleged interference.xi A tenant cannot stay in possession and simply refuse to pay rent on the basis of constructive eviction.xii
The key consideration in preparing for, and responding to, a claim of constructive eviction is keeping good records. A tenant claiming constructive evicting likely must prove that the issue was raised in a timely manner and, despite multiple entreaties, was never resolved.xiii As such, it is critical that landlords acknowledge tenant complaints as well as document in writing their efforts to ameliorate those complaints. While a landlord does not carry the burden of proof for constructive eviction, detailed documentation can thwart a tenant’s claim that a landlord has been inattentive or unwilling to address the tenant’s concerns.
Detailed records are also useful in disputes where a tenant claims substantial interference. “The whole point of constructive eviction is that the landlord basically drove the tenant out through the landlord’s action or inaction.”xiv As such, a landlord that is unable to document the steps taken in response to complaints will be grossly disadvantaged whereas the tenant, which had control and knowledge of the premises, will have a much easier time describing how the alleged interference deprived them of enjoying the premises.
Even with meticulous records, however, owners and managers may still face claims of construction eviction. In such instances, counsel should be retained to properly advise on compiling, preserving, and employing the evidence necessary to refute the tenant’s claims.
i Gray v. Oxford Worldwide Grp., Inc., 139 P.3d 267, 269 (Utah Ct. App. 2006).
ii Gray, 139 P.3d at 270 (citing Neslen, 254 P.2d at 850) (internal formatting omitted).
iii See Gray, 139 P.3d at 269–70 (citing Thirteenth & Washington Sts. Corp. v. Neslen, 254 P.2d 847, 850 (Utah 1953)); Brugger v. Fonoti, 645 P.2d 647, 648 (Utah 1982).
iv See Gray, 139 P.3d at 270–71.
v Thirteenth & Washington Sts. Corp. v. Neslen, 254 P.2d 847 (Utah 1953).
vi See Richard Barton Enterprises, Inc. v. Tsern, 928 P.2d 368, 375, 378 (Utah 1996) (citing Union City Union Suit Co. v. Miller, 162 A.D.2d 101, 556 N.Y.S.2d 864 (1990)).
vii See Myrah v. Campbell, 163 P.3d 679, 682–84 (Utah Ct. App. 2007).
viii Barton v. MTB Enterprises, 889 P.2d 476, 477 (Utah Ct. App. 1995); see also Brugger, 645 P.2d at 648 (stating that the tenant’s complaints revolved around standard problems commonly associated with building maintenance and did not rise to the level of substantial interference); viv Reid v. Mutual of Omaha Ins. Co., 776 P.2d 896, 898–900 (Utah 1989) (upholding trial court’s findings of fact concerning insufficiency of disruption so as to justify claim for constructive eviction).
ix See Kenyon v. Regan, 826 P.2d 140, 142 (Utah Ct. App. 1992).
x See Kenyon, 826 P.2d at 142.
xi See Kenyon, 826 P.2d at 142; see also Barton v. MTB Enterprises, Inc., 889 P.2d 476, 477 (Utah Ct. App. 1995); Brugger, 645 P.2d at 648.
xii See Kenyon, 826 P.2d at 142 (citing Fernandez v. Purdue, 518 P.2d 684, 686 (Utah 1974)).
xiii See Brugger, 645 P.2d at 648 (noting that while the tenant had raised legitimate issues concerning state of the premises, the landorld had taken steps to remedy the problems within a reasonable time) (citing 49 Am.Jur.2d, Landlord and Tenant, § 617).
xiv Barton, 889 P.2d at 477.
Reprinted courtesy of
Ben T. Welch, Snell & Wilmer and
Ken Brown, Snell & Wilmer
Mr. Welch may be contacted at bwelch@swlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Conflict of Interest Accusations may Spark Lawsuit Against City and City Manager
February 07, 2014 —
Beverley BevenFlorez-CDJ STAFFCasper, Wyoming Councilman Craig Hedquist—who is also owner of Hedquist Construction—has been “accused of violating state and local conflict-of-interest laws,” according to the Star-Tribune. In response, Hedquist “is threatening a lawsuit against City Manager John Patterson, the city of Casper and ‘possibly others,’ according to a letter obtained by the Star-Tribune.”
The letter, which was sent to City Attorney William Luben by Hedquist attorney John Robinson, “demands the city preserve, from Aug. 1, 2012, on, all records of communication and consultation with attorneys and investigators, along with minutes, notes, recordings, executive sessions and digital data regarding Hedquist and Hedquist Construction.”
City Manager John Patterson told the Star-Tribune that “he was unaware of the letter and didn't know what the lawsuit might be about.”
Hedquist maintains that there was never a conflict of interest: “The general and expected practice for the Casper City Council members is to not vote on matters in which a council member may have a personal interest and record this recusal in the public record,” Hedquist said, as reported by the Star-Tribune. “I have done this on all contract matters regarding Hedquist Construction.”
Read the court decisionRead the full story...Reprinted courtesy of
It’s Not What You Were Thinking!
December 10, 2024 —
Daniel Lund III - LexologyAt least it is not what the lower court was thinking… but the same result for a general contractor seeking to have its comprehensive general liability insurer pay the GC’s defense related to claims for physical damage on a construction project.
In reviewing the Massachusetts federal district court’s ruling in favor of the insurer, the United States First Circuit Court of Appeals posited: “The principal question is whether a general contractor’s CGL insurance policy covers damage to a non-defective part of the contractor’s project resulting from a subcontractor’s defective work on a different part of that project.”
The district court had held under Massachusetts law that the insurer had no duty to defend because the lawsuit “did not allege ‘property damage’ caused by an ‘ occurrence,’ as required for coverage” under the policy (a defense that was urged by the insurer). The Court of Appeals affirmed, “albeit for different reasons.”
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Traub Lieberman Attorneys Recognized in the 2022 Edition of The Best Lawyers in America®
September 13, 2021 —
Traub LiebermanTraub Lieberman is pleased to announce that three Partners have been selected by their peers for inclusion in the 2022 edition of The Best Lawyers in America®. In addition, five attorneys have been included in the 2022 Best Lawyers®: Ones to Watch list. These recognitions include attorneys from the firm’s Chicago, IL; Palm Beach Gardens, FL; and St. Petersburg, FL offices.
2022 Best Lawyers®
Chicago, IL
- Brian C. Bassett – Insurance Law
Palm Beach Gardens, FL
- Rina Clemens – Personal Injury Litigation – Defendants
St. Petersburg, FL
- Scot E. Samis – Appellate Practice
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman
Wendel Rosen Construction Attorneys Recognized by Super Lawyers and Best Lawyers
August 30, 2017 —
Wendel Rosen Black & Dean LLP - California Construction Law BlogTwo members of Wendel Rosen’s
Construction Practice Group were recognized recently.
Garret Murai was selected for inclusion in the 2017 list of Northern California Super Lawyers and
Matthew Graham was selected for inclusion in
The Best Lawyers in America© 2018 edition. Garret Is co-chair of the firm’s Construction Practice Group and Matt is a 30+ year veteran of construction law.
Read the court decisionRead the full story...Reprinted courtesy of
Safety Guidance for the Prevention of the Coronavirus on Construction Sites
May 25, 2020 —
Heather Whitehead - Newmeyer DillionAlthough construction projects are generally allowed to proceed under most COVID-19 stay at home orders, owners and contractors need to know how to proceed safely on their construction sites. Not only do workers and others on site need to be protected, but implementation of these protocols is also critical to avoid potential liabilities. Last week, the California Department of Industrial Relations – Division of Occupational Safety & Health (CAL/OSHA) released guidance regarding safety and health procedures to prevent the spread of COVID-19 at construction sites. A link to the CAL/OSHA Safety and Health Guidance is provided here.
While the guidance states that it is not imposing any new legal obligations, it is imperative for businesses to not only be aware of these safety practices, but to incorporate these practices as appropriate on each construction site to protect its employees as well as subcontractors, suppliers and others who may be present on site. Otherwise, owners and contractors face potential exposure to regulatory action, including potential penalties and other liabilities, if they fail to properly incorporate these guidelines into the Injury and Illness Prevention Program (IIPP) at each construction site. Now is the time to update your current Injury and Illness Prevention Program (IIPP) to include recommended protocols for preventing the spread of the Coronavirus.
Read the court decisionRead the full story...Reprinted courtesy of
Heather Whitehead, Newmeyer DillionMs. Whitehead may be contacted at
heather.whitehead@ndlf.com
Seattle’s Tallest Tower Said Readying to Go On the Market
March 12, 2015 —
Hui-yong Yu – Bloomberg(Bloomberg) -- Seattle’s Columbia Center, the curved black office tower that’s the city’s tallest building, is poised to go on the market as its owners seek to tap into robust demand for U.S. real estate.
Beacon Capital Partners, a Boston-based private-equity real estate company, is working with Eastdil Secured LLC on the sale of the 76-story Columbia Center, the second-tallest U.S. building west of Chicago, according to a person with knowledge of the matter. Formal marketing is likely to begin in coming months, said the person, who asked not to be identified because the process is private.
Read the court decisionRead the full story...Reprinted courtesy of
Hui-yong Yu, BloombergMs. Yu may be contacted at
hyu@bloomberg.net
Windstorm Exclusion Found Ambiguous
September 10, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe Second Circuit reversed the District Court's issuance of summary judgment to the insurer because a windstorm exclusion was deemed ambiguous. 7001 East 71st Street, LLC v. Continental Cas. Co., 2018 U.S. App. LEXIS 17334 (2nd Cir. June 26, 2018).
A windstorm during Hurricane Sandy caused the roof of 7001 East 71st Street LLC (7001) to tear, allowing rainwater to seep in and damage 7001's "Covered Equipment" as defined by the policy. Continental denied coverage based upon the windstorm exclusion and the district court granted summary judgment to Continental.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com