Alabama Supreme Court Reverses Determination of Coverage for Faulty Workmanship
August 26, 2019 —
Tred R. Eyerly - Insurance Law HawaiiAlthough the lower court held that the insured contractor was entitled to coverage and indemnification under a CGL policy despite claims based upon faulty workmanship, the Alabama Supreme Court reversed. Nationwide Mut. Fire Ins. Co. v. David Group, Inc., 2019 Ala. LEXIS 52 (Ala. May 24, 2019).
The David Group (TDG) specialized in custom-built homes. The Shahs purchased a newly built home from TDG in October 2006. After moving in, the Shahs experienced problems with their new home that TDG was unable to correct. In February 2008, the Shahs sued TDG. The complaint alleged that serious defects existed, resulting in health and safety issues, building code violations, poor workmanship, misuse of construction materials, and disregard of property installation methods. The case went to arbitration and an award of $12,725 was issued to the Shahs.
Nationwide was TDG's CGL carrier and initially defended TDG. After Nationwide withdrew its defense, TDG sued seeking a judgment declaring that Nationwide was obligated to defend and indemnify. The trial court denied Nationwide's motion for summary judgment and issued a partial summary judgment in favor of TDG on the issue of coverage. Nationwide appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Pushing the Edge: Crews Carve Dam Out of Remote Turkish Mountains
July 04, 2023 —
Pam McFarland - Engineering News-RecordRugged Construction | Part Two of an ENR Series
On a cold, gray day in late March, the mountains on the drive to the Yusufeli hydroelectric dam project site in northeastern Turkey seem ominous.
With the highest of these rising more than 3,000 meters above sea level—some of them snow-capped—the jagged rock formations look stark and imposing, the type only a trained professional should attempt to cross.
Reprinted courtesy of
Pam McFarland, Engineering News-Record
Ms. McFarland may be contacted at mcfarlandp@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Real Estate & Construction News Roundup (8/6/24) – Construction Tech Deals Surge, Senators Reintroduce Housing Bill, and Nonresidential Spending Drops
September 16, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, cybersecurity attacks target contractors, U.S. banks report weaker profits, additional commercial real estate is distressed, and more!
- Spending dropped in almost half of nonresidential subcategories in June, with the decrease stemming from higher interest rates, tighter credit conditions and a softening economy. (Sebastian Obando, Construction Dive)
- Despite the decline in investment dollars for construction technology, the number of deals surged by 18% year-over-year, indicating sustained interest and activity in the sector. (Sebastian Obando, Construction Dive)
- As cybersecurity attacks on U.S.-based businesses ramp up, general contractors are not immune. (Jen A. Miller, Construction Dive)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Rather Than Limit Decision to "That Particular Part" of Developer's Policy Necessary to Bar Coverage, 10th Circuit Renders Questionable Decision on Exclusion j(6)
September 06, 2021 —
William S. Bennett - Saxe Doernberger & Vita, P.C. The 10th Circuit Court of Appeals, applying Colorado law, recently extended Colorado’s broad application of the phrase “arising out of” in insurance interpretation, barring an insured real estate developer from receiving a defense to a suit alleging liability for construction of a defective retaining wall and associated resulting damage.1 The decision also included a questionable analysis of the commercial general liability (“CGL”) policy’s exclusion j(6), contradicting both the plain meaning of the exclusion as well as existing 10th Circuit case law.
The underlying dispute concerned a land developer, HT Services, LLC, who was sued by the homeowner’s association (“HOA”) of one of its developments. The HOA alleged that HT Services negligently designed and constructed a retaining wall in the community. HT Services had CGL policies from Western Heritage Insurance Company in place from 2010 to 2013 that insured it for liability associated with four acres of land that the community was built upon.
HT Services tendered the HOA’s lawsuit to Western Heritage, which declined to defend and indemnify HT Services. After that matter settled, HT Services sued Western Heritage, alleging breach of contract and bad faith. Western Heritage moved for summary judgment, asserting two exclusions, and the District Court granted the motion in Western Heritage’s favor. In upholding the District Court’s decision, the 10th Circuit discussed two exclusions that the District Court determined precluded coverage.
Read the court decisionRead the full story...Reprinted courtesy of
William S. Bennett, Saxe Doernberger & Vita, P.C.Mr. Bennett may be contacted at
wsb@sdvlaw.com
Proving Impacts to Critical Path to Defeat Liquidated Damages Assessment
December 16, 2019 —
David Adelstein - Florida Construction Legal UpdatesWhen a contractor is staring down the barrel of an owner’s assessment of liquidated damages, the burden will fall on the contractor to establish that the delay was attributable to the owner and the owner’s agents. The contractor will want to do this not only to defeat the assessment of liquidated damages, but because it will want to establish that the delay caused it to incur extended field overhead (general conditions) for which the owner is responsible. A contractor supports its burden by proving the impacts to its critical path. “In general, proving an allegation of government-caused delays without a means of showing the critical path is a steep prospect.” James Talcott Construction v. U.S., 2019 WL 1040383, *8 (Fed. Cl. 2019) (unreported opinion) (finding that because contractor did NOT present a critical path analysis it could not support its claim for delay caused by the government).
Avoiding the assessment of liquidated damages means the contractor needs to support that it encountered excusable delay and it is/was entitled to an extension of time to complete the project.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
First Circuit Limits Insurers’ Right to Recoup Defense Costs or Settlement Payments
April 02, 2024 —
Eric Hermanson, Austin Moody & Victoria Ranieri - White and Williams LLPWeighing in on an issue that has divided courts nationwide, the U.S. Court of Appeals for the First Circuit has ruled that an insurer under Massachusetts law has no right to recoup defense costs, or amounts the insurer pays in settlement – even if the insurer reserves rights prior to payment and obtains a ruling, after the fact, that no defense or indemnity was owed. Berkley Natl. Ins. Co. v. Atlantic-Newport Realty LLC, No. 22-1959, 2024 U.S. App. LEXIS 4115 (1st Cir. Feb 22, 2024) (“Granite Telecomm"). However, the First Circuit rested its ruling on narrow procedural grounds, which may prolong the controversy rather than resolve it.
The insureds in Granite Telecomm owned a company cafeteria. They were sued by a food service worker who suffered a foot infection after being exposed to bacteria during a sewage backup. They sought coverage from their insurer, Berkley. Berkley argued that coverage was barred by a fungus and bacteria exclusion in the policy. The insureds disagreed. They threatened suit under M.G.L. ch. 93A, and demanded that Berkley defend the case.
Reprinted courtesy of
Eric Hermanson, White and Williams LLP,
Austin Moody, White and Williams LLP and
Victoria Ranieri, White and Williams LLP
Mr. Hermanson may be contacted at hermansone@whiteandwilliams.com
Mr. Moody may be contacted at moodya@whiteandwilliams.com
Ms. Ranieri may be contacted atranieriv@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Indemnity Provision Prevails Over "Other Insurance" Clause
December 06, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe Second Circuit predicted that the New York appellate courts would find the contractual indemnity provision prevailed over the application of an "other insurance" provisions. Cent. Sur. Co. v. Metro. Transit Auth., 2021 U.S. App. LEXIS 29860 (2nd Cir. Oct. 5,2021).
Long Island Railroad (LIRR) contracted with general contractor Rukh Enterprises, Inc. to complete a railroad bridge lead paint removal and repainting project on Metropolitan Transit Authority property. Rukh hired subcontractor, East Coast Painting & Maintenance to complete certain lead-related work on the project.
An employee of East Coast suffered an injury while working on the project. The employee sued LIRR and Rukh. A settlement in the underlying case was reached, implicating three of four policies - Admiral (primary for LIRR), Arch (CGL for Rukh), and Harleysville (primary for East Coast). Century Surety (excess liability for Rukh) did not contribute to the settlement and disclaimed all coverage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
City Potentially Liable for Cost Overrun on Not-to-Exceed Public Works Contract
June 29, 2017 —
David R. Cook Jr. - Autry, Hanrahan, Hall & Cook, LLPOn a public works construction project, a contractor incurred additional costs and asserted a claim against the city. The city denied the claim because the contract had a not-to-exceed price, and the city council and mayor did not approve contract modifications to exceed that amount. City ordinances require approval for contract modifications and change orders exceeding ten percent of the original not-to-exceed amount.
But the contractor argued that the ordinance did not apply because the excess costs did not result from a contract modification or change order. In addition, the contractor argued that, in refusing to approve an increase in the not-to-exceed amount, the city breached the implied duty of good faith and fair dealing. The court concluded that these questions were factual issues for the jury to decide.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hanrahan, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com