Indiana Court Enforces Contract Provisions rather than Construction Drawing Markings
January 14, 2015 —
Beverley BevenFlorez-CDJ STAFFTimothy J. Abeska, a vice-chair of Barnes & Thornburg LLP’s Construction Law Practice Group, analyzed Goodrich Quality Theaters, Inc. v. Fostcorp Heating and Cooling, Inc., 16 N.E.3d 426 (Ind. Ct. App. 2014), which “provides an example of a court enforcing contract provisions rather than markings on construction drawings that are inconsistent with contract requirements.”
The case evolved from a dispute on a construction of an IMAX theater, when the general contractor did not understand the architect’s markings for non-standard joist girders, and ordered standard joist girders, per the contract. The error created delays and other problems, which led to payment disputes and mechanic’s liens against the project.
Abeska stated that “[t]his case shows the importance of making sure all documents which comprise a construction contract are consistent with each other, as courts will enforce contracts negotiated by the parties. The case also demonstrates that litigation is not a quick process, as the Court of Appeals Opinion was issued more than seven years after the project was completed.”
Read the court decisionRead the full story...Reprinted courtesy of
South Carolina Clarifies the Accrual Date for Its Statute of Repose
March 18, 2019 —
William L. Doerler - The Subrogation StrategistIn Lawrence v. General Panel Corp., 2019 S.C. LEXIS 1, No. 27856 (S.C. Jan. 1, 2019), the Supreme Court of South Carolina answered a certified question related to South Carolina’s statute of repose, S.C. Code § 15-3-640,[1] to wit, whether the date of “substantial completion of the improvement” is always measured from the date on which the certificate of occupancy is issued. The court held that a 2005 amendment to § 15-3-640 did not change South Carolina law with respect to the date of substantial completion. Thus, under the revised version of § 15-3-640, “the statute of repose begins to run at the latest on the date of the certificate of occupancy, even if there is ongoing work on any particular part of the project.” A brief review of prior case law may assist with understanding the court’s ruling in Lawrence.
In Ocean Winds Corp. of Johns Island v. Lane, 556 S.E.2d 377 (S.C. 2001), the Supreme Court of South Carolina addressed the question of whether § 15-3-640 ran from substantial completion of the installation of the windows at issue or on substantial completion of the building as a whole. Citing § 15-3-630(b),[2] the court found that the windows “were ‘a specified area or portion’ of the larger condominium project” and, upon their incorporation into the larger project they could be used for the purpose for which they were intended. Thus, the court held that “the statute of repose began running when installation of the windows was complete.”
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and WilliamsMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
Drawing the Line: In Tennessee, the Economic Loss Doctrine Does Not Apply to Contracts for Services
December 11, 2023 —
Gus Sara - The Subrogation StrategistIn Commercial Painting Co. v. Weitz Co. LLC, No. W2019-02089-SC-R11-CV, 2023 Tenn. LEXIS 39 (Weitz), the Supreme Court of Tennessee (Supreme Court) considered whether the economic loss doctrine barred the plaintiff’s claims for fraud, negligent misrepresentation and punitive damages arising out of a contract with the defendant for construction services. The court held that the economic loss doctrine only applies to product liability cases and does not apply to claims arising from contracts for services. This case establishes that, in Tennessee, the economic loss doctrine does not bar tort claims in disputes arising from service contracts.
In Weitz, defendant, Weitz Co. LLC (Weitz), was the general contractor for a construction project and hired plaintiff Commercial Painting Co. (Commercial) as a drywall subcontractor. Weitz refused to pay Commercial for several of its payment applications, claiming that the applications were submitted untimely and contained improper change order requests. Commercial filed a lawsuit against Weitz seeking over $1.9 million in damages, alleging breach of contract, unjust enrichment, enforcement of a mechanic’s lien, and interest and attorney’s fees under the Prompt Pay Act of 1991. Weitz filed a counterclaim for $500,000 for costs allegedly incurred due to Commercial’s delay and defective workmanship. In response, Commercial amended its complaint to add claims for fraud, intentional and negligent misrepresentation, rescission of the contract and $10 million in punitive damages. Commercial alleged that Weitz received an extension of the construction schedule but fraudulently withheld this information from Commercial and continued to impose unrealistic deadlines.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
The Anatomy of a Construction Dispute Stage 2- Increase the Heat
January 21, 2015 —
Christopher G. Hill – Construction Law MusingsLast week we discussed the groundwork and circumstances of a construction claim. This week’s post will discuss the next steps, hopefully short of full blown arbitration or litigation that you, as a construction company, can pursue presuming your claim has been properly preserved.
If your contract requires certain steps such as informal resolution attempts or other items, these are the first things that must be done while still preserving your rights to pursue all remedies available. Instituting such contractually required resolution steps can and should be the first “notch” on the dial of increased pressure on the Owner, General Contractor or possibly Subcontractor against whom you have a claim.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Even Toilets Aren’t Safe as Hackers Target Home Devices
June 11, 2014 —
Amy Thomson – BloombergCome home to a hot iron and smoldering clothes this afternoon? Soon, it may not be a sign of forgetfulness, but rather evidence that you’ve been hacked.
In coming years, your smartphone will be able to lock your house, turn on the air conditioning, check whether the milk is out of date, or even heat up your iron. Great news, except that all that convenience could also let criminals open your doors, spy on your family or drive your connected car to their lair.
“As these technologies become more sophisticated, it opens up a broader spectrum of threats,” said Gunter Ollmann, chief technology officer of IOActive, a tech security firm in Seattle. A world of connected devices makes it possible “for the bad guys to have permanent entry into your household.”
Read the court decisionRead the full story...Reprinted courtesy of
Amy Thomson, BloombergMs. Thomson may be contacted at
athomson6@bloomberg.net
Is Safety Compliance Putting Your Project in Jeopardy? Examining the Essentials of DOE’s Worker Safety and Health Program
July 02, 2024 —
Lucas T. Daniels & Benjamin J. Hochberg - ConsensusDocsMost contractors are familiar with the myriad of labor and safety regulations intended to safeguard the health and safety of workers. Many contractors will be equally familiar with the maze of forms and reports, the maintenance of safety personnel, safety walks and talks, and the many other measures intended to prevent and prepare for accidents. Less known among contractors and construction industry leaders is the regulatory framework establishing safety requirements and the ramifications of ignoring safety-related rules. Knowing and understanding the jurisdiction and authority of the agencies monitoring safety compliance on your project is critical to avoiding administrative ordeals and audits that could add days or weeks to your schedule and frustrate your staff.
The Department of Energy’s Worker Safety and Health Program
Under the Occupational Safety and Health Act of 1970, as amended (OSH), the Department of Labor’s Occupational Safety and Health Administration (OSHA) issues and enforces occupational health and safety regulations. OSHA, or a state with approval from OSHA, regulates the occupational health and safety of private sector employees unless another federal agency has and exercises its statutory authority to regulate. Several federal agencies have developed their own safety programs and conduct their own enforcement of those regulations independent of OSHA. For example, projects receiving funding from the Department of Energy (DOE) are subject to additional oversight of their safety programs by this agency. DOE directly manages its own Worker Safety and Health Program (WSHP), codified at 10 C.F.R. § 851, et seq., and will enforce compliance with its WSHP at all DOE sites. A “DOE site” is defined as a DOE-owned or -leased area or location or other area or location that DOE controls, where a contractor performs activities and operations in furtherance of a DOE mission. This broad definition encompasses a wide range of facilities and operations, including those not directly managed by the DOE but still under its control. The contractor at such a site must be aware of the specific requirements and procedures of the DOE under the WSHP and the ramifications of violating these regulations.
Reprinted courtesy of
Lucas T. Daniels, Peckar & Abramson, P.C and
Benjamin J. Hochberg, Peckar & Abramson, P.C
Mr. Daniels may be contacted at ldaniels@pecklaw.com
Mr. Hochberg may be contacted at bhochberg@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Can We Compel Insurers To Cover Construction Defect in General Liability Policies?
December 09, 2011 —
Douglas Reiser, Builders Council BlogRecently, I read an article on Engineering News-Record that outlines a remarkable movement by as many as four states, to mandate coverage of construction defects in contractor general liability insurance policies. Say what? Is this a reality? What will become of affordable insurance?
Commercial General Liability insurance, or CGL, is your basic liability insurance. Every contractor doing business in the State of Washington, and most likely those abroad, has this insurance. Contractors buy this insurance to protect them from unforeseen liabilities arising from their negligence - and right now it’s reasonably affordable.
Why is it so affordable in such a risk-heavy industry? Because CGL policies significantly limit the scope of their coverage. Coverage is generally afforded for damages resulting from negligence (The roofer put a hammer through the drywall contractor’s wall) or which resulted from your defective construction (the roof leaked and flooded the rest of the house). But, that coverage does not include replacement of your faulty construction (the contents of the home might be protected by your leaky roof - the leaky roof itself is not).
The debate over coverage typically stems from the definition of “occurrence,” a term used to describe the event from which coverage arises, “resulting loss,” a term used to describe the type of loss covered.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
Will a Notice of Non-Responsibility Prevent Enforcement of a California Mechanics Lien?
March 05, 2015 —
William L. Porter – Porter Law Group, Inc.The “Notice of Non-Responsibility” is one of the most misunderstood and ineffectively used of all the legal tools available to property owners in California construction law. As a result, in most cases the answer to the above question is “No”, the posting and recording of a Notice of Completion will not prevent enforcement of a California Mechanics Lien.
The mechanics lien is a tool used by a claimant who has not been paid for performing work or supplying materials to a construction project. It provides the claimant the right to encumber the property where the work was performed and thereafter sell the property in order to obtain payment for the work or materials, even though the claimant had no contract directly with the property owner. When properly used, a Notice of Non-Responsibility will render a mechanics lien unenforceable against the property where the construction work was performed. By derailing the mechanics lien the owner protects his property from a mechanics lien foreclosure sale. Unfortunately, owners often misunderstand when they can and cannot effectively use a Notice of Non-Responsibility. As a result, the Notice of Non-Responsibility is usually ineffective in protecting the owner and his property.
The rules for the use of the Notice of Non-Responsibility are found in California Civil Code section 8444. Deceptively simple, the rules essentially state that an owner “that did not contract for the work of improvement”, within 10 days after the owner first “has knowledge of the work of improvement”, may fill out the necessary legal form for a Notice of Non-Responsibility and post that form at the worksite and record it with the local County Recorder in order to prevent enforcement of a later mechanics lien on the property.
What commonly occurs however is that early in the process the owner authorizes or even requires its tenant to perform beneficial tenant improvements on the property. This authorization is often set forth in a tenant lease or other written document. The dispositive factor for determining whether the Notice of Non-Responsibility will be enforceable though is that the owner knows that these improvements will be made to the property and intends that they be made, usually long before the work begins. Indeed, the owner has usually negotiated these very terms into the lease contract. The owner then mistakenly believes that once work on the property commences it has 10 days to post and record a Notice of Non-Responsibility and thereby protect itself from a mechanics lien.
The usual error is two-fold. First, the statute states that the Notice is available when the owner “did not contract for the work of improvement”. The fact though is that the owner did contract for the work of improvement. It did so through the lease contract. This is true even though the owner’s contract was not with the contractor or supplier directly. Secondly, the 10 day period to post and record the Notice begins when the owner first “has knowledge” of the work of improvement. This knowledge was of course gained when the lease was negotiated and signed, providing knowledge typically many days before the work has begun. Thus, the 10 day period can also seldom be met. The Notice of Non-Responsibility will therefore fail both rules because the owner has in fact contracted for the improvement and because he does not act within 10 days of gaining this knowledge.
The next event in the typical scenario occurs when the tenant does not pay its contractor. The contractor then has nothing to pay its subcontractors. Material suppliers also go unpaid. Mechanics liens are then recorded by the unpaid claimants, followed by foreclosure actions within ninety days thereafter. Owners will typically point to the Notice of Non-Responsibility they posted and recorded, claiming its protection. Claimants then in turn point to the lease or other evidence that the owner knew of the pending improvements and contracted in some way that the improvements be performed, often also more than 10 days before they posted the Notice. Judges generally agree with the unpaid mechanics lien claimants and the Notice of Non-Responsibility is deemed ineffective.
The fact that the Court does not enforce the Notice of Non-Responsibility under these circumstances is not an unfair result. Since the owner authorized the work to be performed and it received a substantial benefit in the form of those improvements, it is not unfair that the owner should pay for those benefits. It would be inequitable for the owner to obtain the benefit of the improvements which it authorized but for which it did not pay, while allowing those who provided the benefit to go unpaid. Moreover, without such a system in place the door would be open to owners setting up sham “tenants” who would enter into contracts to have work performed, only to disappear when the work is completed, leaving the contractor without a source of payment. The system in place as described above prevents such duplicity. Owners would do well to arm themselves with proper knowledge of when the Notice of Non-Responsibility will and will not protect them and then responsibly use the Notice of Non-Responsibility.
For the legal eagles among you, the following cases illustrate the view of the courts, consistent with the above: Baker v. Hubbard (1980) 101 Cal.App.3d 226; Ott Hardware v. Yost (1945) 69 Cal. App.2d 593 (lease terms); Los Banos Gravel Co. v. Freeman (1976) 58 Cal.App.3d 785 (common interest); Howard S. Wright Construction Co. v. Superior Court (2003); 106 Cal.App.4th 314 (participating owner).
William L. Porter of
Porter Law Group, Inc. located in Sacramento, California may be contacted at (916) 381-7868 or bporter@porterlaw.com
Read the court decisionRead the full story...Reprinted courtesy of