Motions to Dismiss, Limitations of Liability, and More
January 23, 2023 —
Christopher G. Hill - Construction Law MusingsRemember BAE Sys. Ordnance Sys. V. Fluor Fed. Sols? I examined that case on two occasions previously here at Construction Law Musings. Previously the discussions were about the
mix (or lack thereof) between fraud and contract and about how
careful contract drafting is key.
In the
most recent opinion in this ongoing litigation from March of 2022, the Court examined various motions to dismiss the Complaint and Counterclaim in the matter. As a reminder, the basic facts are as follows.
The US Army Joint Munitions Command (“Army”) contracted with BAE Systems OrdnanceSystems, Inc. (“BAE”) to operate and maintain the Radford Army Ammunition Plant (“RFAAP”)under a basic ordering agreement (“BOA”). Under BOA Task Order 002, BAE contracted to replace the legacy NC facility at the RFAAP with a newer one (the “NC Project”). Initially, BAE subcontracted the NC Project to Lauren Engineers & Constructors (“Lauren”), but later terminated Lauren. Despite terminating Lauren, BAE’s timeline to complete the NC Project remained unchanged and BAE was required to use Lauren’s design for the NC Project. BAE gave interested bidders access to the Lauren design and other related documents and required the selected subcontractor to perform in accordance with the 85% complete Lauren design, that the Lauren design could be relied on for accuracy, and the selected subcontractor only had to complete the unfinished parts. Fluor Federal Solutions, LLC (“Fluor”) submitted a request for information (“RFI”) asking BAE about the standards referenced in the SOW. Fluor was unable to determine the completeness of the Lauren design but relied on BAE’s assertion that the design was 85% complete. BAE rejected Fluor’s initial bid as being too high given what BAE had already paid Lauren for its design and told Fluor to lower its bid because the design was close to complete. Fluor lowered its price and submitted another bid proposal that outlined a firm-fixed-price design/build that forecasted 32 months to complete the NC Project. BAE awarded Fluor an Undefinitized Contract Action (“UCA”) in the amount of $9 million dollars, later increased to $32 million. Under the UCA, Fluor began procuring materials and physical construction before a formal subcontract was agreed upon. On December 17, 2015, BAE and Fluor agreed to a fixed-price design and build subcontract (the “Subcontract”) in which Fluor agreed to design, construct, and partially commission the NC Project for $245,690,422.00, which included money spent already in the UCA. When this litigation began, Fluor was scheduled to complete its work by December 2020, 2.5 years beyond the originally agreed-upon completion date.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Two Lawyers From Hunton’s Insurance Recovery Group, Andrea DeField and Latosha Ellis, Selected for American Bar Association’s 2022 “On The Rise” Award
August 15, 2022 —
Kevin V. Small - Hunton Insurance Recovery BlogPartner, Andrea DeField, and counsel, Latosha Ellis, were each recently awarded “On the Rise – Top 40 Young Lawyers” honors by the American Bar Association’s Young Lawyers Division. The award honors 40 of the nation’s most promising lawyers under the age of 40 or who have been licensed for 10 years or less. Recipients demonstrate high achievement, innovation, vision, leadership, and service to the profession and their communities, including extensive knowledge in litigation or transactional work and commitment to pro bono, charitable, or professional volunteer work, all while making a lasting impact in their respective fields. More information may be found
here.
Reprinted courtesy of
Kevin V. Small, Hunton Andrews Kurth
Mr. Small may be contacted at ksmall@HuntonAK.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
California Trial Court Clarifies Application of SB800 Roofing Standards and Expert’s Opinions
February 18, 2020 —
Scott Calkins & Anthony Gaeta - Collinsworth, Specht, Calkins & Giampaoli; Mark Chapman - Bert L. Howe & Associates, Inc.Collinsworth, Specht, Calkins & Giampaoli partners Scott Calkins and Anthony Gaeta obtained a trial victory when the jury returned a 12-0 defense verdict against one plaintiff homeowner, and awarded the other homeowner less than $2,000, an amount well below the defendant’s pre-trial CCP 998 Offers to Compromise. One of the main issues in the case was the application of SB800 roofing standards. Plaintiffs’ roofing expert testified in deposition no water entered the structure or passed through a moisture barrier [Civ. Code §896(a)(4)], and no materials had fallen off the roof [§896(g)(11)]. In an attempt to circumvent the applicable performance standards, Plaintiffs argued Civ. Code §869(g)(3)(A), also known as the ‘useful life’ exception, applied because the various components of the roof (nailing pattern, tiles, vents, etc.) were installed in such a manner so as to reduce the useful life of the roof. Following pre-trial motions and objections made during Plaintiffs’ direct examination, the Court ruled Section 896(g)(3)(A) did not apply to a conventional roof, as it is not a “manufactured product” as defined in §896(g)(3)(C). Plaintiffs’ roofing claims were summarily dismissed and Plaintiffs’ expert was prevented from testifying.
In contrast, the defense expert, Mark Chapman, was allowed to testify regarding his expert opinions as to the appropriate SB800 standard relative to each alleged defect and whether the standards were violated. The SB800 performance standards were included on the jury verdict form, and the jury found Mr. Chapman’s testimony compelling, which was a substantial factor in awarding only minor damages to one Plaintiff.
For more information, contact
Scott Calkins (scalkins@cslawoffices.com),
Anthony Gaeta (ageta@cslawoffices.com) or
Mark Chapman (mchapman@berthowe.com).
Read the court decisionRead the full story...Reprinted courtesy of
Deleted Emails Cost Company $3M in Sanctions
January 13, 2017 —
Grace V. Hebbel - Saxe Doernberger & Vita, P.C. BlogRecently, the Federal District Court for the District of Delaware imposed $3 million in punitive sanctions in order to redress harms caused by a company’s bad faith deletion of tens of thousands of emails during the course of litigation. The sanctions were ordered pursuant to Federal Rule of Civil Procedure 37, which was amended effective December 1, 2015 to permit sanctions for the failure to preserve electronically stored information (“ESI”).
In GN Netcom, Inc. v. Plantronics, Inc.,1 the plaintiff, GN Netcom, brought an antitrust suit alleging that the defendant company, Plantronics, interfered with distributors to stop GN Netcom from marketing its product. Upon receipt of GN Netcom’s demand letter, Plantronics issued a litigation hold and began providing training sessions to its employees to ensure compliance. Upon filing of GN Netcom’s suit, Plantronics issued an updated litigation hold and continued training sessions.
Read the court decisionRead the full story...Reprinted courtesy of
Grace V. Hebbel, Saxe Doernberger & Vita, P.C.Ms. Hebbel may be contacted at
gvh@sdvlaw.com
The Secret to an OSHA Inspection
December 02, 2015 —
Craig Martin – Construction Contractor AdvisorWouldn’t it be nice to know ahead of time what an OSHA inspector will be looking for when he comes to your work site? Well, I know the secret. And, it’s not really a secret. Just look at OSHA’s top ten citation standards and it becomes quite clear.
In 2015, OSHA’s top ten most frequently cited violations are:
1. Fall protection (C)
2. Hazard communication
3. Scaffolding (C)
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Badly Constructed Masonry Walls Not an Occurrence in Arkansas Law
May 10, 2012 —
CDJ STAFFThe US District Court for Maryland has granted a summary judgment in the case Konover Construction Corp. v. ATC Associates to Massachusetts Bay Insurance Company and denied a request for dismissal from ACT. Konover (KBE) was contracted by Wal-Mart to build a Wal-Mart store and a Sam’s Club in Port Covington, Maryland. Superus, Inc. was hired by KBE to build the masonry walls. Superus purchased a policy from Massachusetts Bay Insurance which named KBE as an additional insured. Wal-Mart hired ATC Associates to independently test and inspect the concrete structural steel, and masonry.
After the building was in use, a large crack appeared which was attributed a latent construction defect. Other cracks were discovered. Upon investigation, it was discovered that there were “voids or foam in the concrete block surrounding the reinforcing steel that should have been filled with grout,” and in some cases, “reinforcing steel was missing or not installed in accordance with the specifications.” KBE paid for the repair and remediation and Wal-Mart assigned all rights and interests against ATC to KBE.
KBE filed suit against ATC. ATC called for dismissal on the grounds that Wal-Mart had no claims as the problems had been remediated. Wal-Mart then provided KBE with additional agreements to give them enforceable rights against ATC and Superus. KBE filed a fourteen claims against ATC, Superus, and Massachusetts Bay. In the current case, Massachusetts Bay sought summary judgment and ATC sought dismissal of all claims against it.
Massachusetts Bay claims that they need not indemnify Superus, as “there is no evidence adequate to establish that Superus’ defective work caused any collateral and/or resulting damage that was not subject to an Impaired Property exclusion, and that, in any event, no damage occurred during the policy period.”
As Wal-Mart is headquarted in Arkansas, certain contracts were under Arkansas law. Under the Arkansas courts, “defective workmanship, standing alone and resulting in damages only to the work product itself, is not an ‘occurrence.’” The court determined that collateral or resultant damage would be covered. The court found that “it is clear under Arkansas law, and the parties appear to agree, that Massachusetts Bay is not obligated to indemnify KBE for any repairs to the masonry walls themselves, including any cracks or gaps in the walls.” The court also found that “there is no evidence adequate to prove that any allegedly resultant property damage was caused by Superus’ faulty construction of the walls.” The court also noted that “if the building code violation and structural integrity problem were ‘property damage,’ insurance coverage would be barred by the Impaired Property Exclusion.” Based on these findings, the court concluded that Massachusetts Bay is entitled to summary judgment.
While the court dismissed the case against Massachusetts Bay, the court declined ATC’s motion to dismiss. The court noted that ACT’s alleged negligence in conducting inspections “created only a risk of economic loss for KBE.” Although hired by Wal-Mart, ATC “transmitted its daily testing and inspection reports of the Wal-Mart and Sam’s Club projects directly to KBE.” The court found that “KBE has made a plausible claim.”
ATC also claimed that KBE contributed to the negligence due to the negligence of its subcontractor. The court concluded that it was plausible that “ATC will not be able to carry its burden of proving KBE was contributorily negligent.” The court was less sanguine about KBE’s fraud claim, but though it “may not now appear likely to have merit, it is above the ‘plausibility’ line.”
In conclusion, KBE may not continue its case against Massachusetts Bay. However, the judge allowed the other proceedings to continue.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Designers George Yabu and Glenn Pushelberg Discuss One57’s Ultra-Luxury Park Hyatt
July 30, 2014 —
Jennifer Parker – BloombergOne57 might just be the hottest -- or at least the most expensive -- address in New York City.
The $375 million skyscraper currently piercing its blue-glass presence into Manhattan's midtown skyline is home not only to 94 private condos (two of which have already sold for $90 million); it also hosts a brand new Park Hyatt hotel, which opens this August.
Eight years in the making, this Hyatt is the first ultra-luxury hotel New York has seen since the Mandarin Oriental opened in 2003. It's intended to be a New York icon. So, naturally, Hyatt hired two Canadian guys to design it.
Meet George Yabu and Glenn Pushelberg, the dynamic couple who met as college students in Toronto in 1972, and decided to launch design firm YabuPushelberg. Now, they're earning millions per project to design luxury hotels, restaurants, and residences all over the world.
Read the court decisionRead the full story...Reprinted courtesy of
Jennifer Parker, Bloomberg
Keller Group Fires Two Executives in Suspected Australia Profits Reporting Fraud
February 20, 2023 —
James Leggate - Engineering News-RecordLondon-based geotechnical contracting giant Keller Group's profits from its Australia business unit may have been fraudulently inflated by the U.S. equivalent of as much as $20 million in today’s dollars since 2019, the company has revealed.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of