Claim Preclusion: The Doctrine Everyone Thinks They Know But No One Really Knows What it Means in Practice
April 25, 2023 —
Garret Murai - California Construction Law BlogGenerally, I think restraint in litigation is a good thing. Don’t go crazy on your claims, don’t go nut-so in your discovery, and don’t present your case at trial in a way that causes the judge and/or jury to raise their eyebrows or shake their heads in disbelief. But, as with nearly everything, there’s always an exception. One of which is: don’t hold back on a claim because you “think” you might be able to bring it later, because you might not be able to as the next case, 5th and LA v. Western Waterproofing Company, Inc., 87 Cal.App.5th 781 (2023), demonstrates.
The 5th and LA Case
At the outset, let me first say how much I enjoyed reading this case based on the writing alone. The case, as the 2nd District Court of Appeals states, involves “a second lawsuit about an increasingly leaky roof.”
In 2012, property owner 5th and LA hired roofing contractor Western Waterproofing Company, Inc. to remove and recoat a parking lot that served also served as the roof over retail and office space below. Western completed its work in July 2012 and almost immediately 5th and LA noticed water that the coating was failing causing water leaks to the interior of the building.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Sales of Existing Homes in U.S. Fall to Lowest Since 2012
March 26, 2014 —
Shobhana Chandra – BloombergPurchases (ETSLTOTL) of previously owned homes in the U.S. declined in February to the lowest level since July 2012, a sign the industry may be slow to recover.
Contract closings on existing properties fell 0.4 percent to a 4.6 million annual rate, matching the median projection in a Bloomberg survey, figures from the National Association of Realtors showed today in Washington. Prices rose 9.1 percent from a year earlier, the group said.
The slowdown in sales since the middle of last year reflects a pickup in borrowing costs, declining affordability and, more recently, bad weather. Faster job growth that generates bigger income gains are needed to spur demand and allow housing to contribute more to the economy.
Read the court decisionRead the full story...Reprinted courtesy of
Shobhana Chandra, BloombergMs. Chandra may be contacted at
schandra1@bloomberg.net
PATH Station Designed by Architect Known for Beautiful Structures, Defects, and Cost Overruns
October 01, 2013 —
CDJ STAFFThe new PATH station at the World Trade Center site in New York is six years behind schedule and its cost has doubled to $4 billion dollars. But maybe New Yorkers shouldn’t be surprised. The New York Times reports that the Port Authority, which operates the PATH trains between New York and New Jersey, hired Santiago Calatrava, an architect whose work has frequently lead to cost overruns and claims of defects.
The problems in lower Manhattan are not all Mr. Calatrava’s fault. Auditors described the Port Authority as “a challenged and dysfunctional organization.” (A separate report in the New York Times notes that a former PATH executive may have walked away with the rights to the words “World Trade Center” for $10. The company he subsequently founded, The World Trade Center Association, charges millions for the use of the name.)
One problem with Mr. Calatrava’s design for the station is that he insisted that all the mechanical elements of the station be located in other buildings. Further, the Port Authority might want to examine those plans carefully. In the design for a museum in Valencia, Spain, Mr. Calatrava forgot to provide for handicap access or fire escapes. That project, according to the Times tripled in cost as it was built.
Read the court decisionRead the full story...Reprinted courtesy of
WSDOT Seeks Retraction of Waiver Excluding Non-Minority Woman-Owned Businesses from Participation Goals
September 28, 2017 —
Lindsay K. Taft - Ahlers & Cressman PLLCIf you are a regular reader of our blog, you will likely recognize that our firm has been actively involved and concerned with the results of Washington State Department of Transportation’s (“WSDOT”) Disparity Study, which impacts both Disadvantaged Business Enterprises (“DBE”) and general contractors who bid on federally-funded projects with DBE goals. On June 1, 2017, WSDOT implemented a “waiver”, which excluded Caucasian women-owned firms (“WBEs”) from qualifying for Condition of Award DBE Goals on federally-funded projects. This drastic action was the result of WSDOT’s highly criticized 2012 Disparity Study conducted by BBC Research & Consulting of Denver, Colorado, which concluded non-minority women-owned firms do not face “substantial disparities” in the federally-funded transportation contracting market.
BBC’s study was criticized for a number of reasons, but most concerning was BBC’s flawed and unreliable statistical methodology that did not accurately represent true marketplace conditions. See Ahlers & Cressman letter of January 9, 2014 and Associated General Contractors of Washington article. For example, BBC’s results showed both decreasing WBE availability and availability vastly out of range with other states (e.g., the availability of women-owned construction firms in Washington was just 1.5% compared to 11.96% in Oregon). Nevertheless, based on this flawed BBC study and BBC’s assertion that women-owned firms did not face disparities, WSDOT sought and on June 1, 2017 was granted a waiver precluding general contractors from counting WBE firms towards their DBE goals on federally funded public works projects.
Read the court decisionRead the full story...Reprinted courtesy of
Lindsay Taft, Ahlers & Cressman PLLCMs. Taft may be contacted at
ltaft@ac-lawyers.com
'Major' Mass. Gas Leak Follows Feds Call For Regulation Changes One Year After Deadly Gas Explosions
October 21, 2019 —
Johanna Knapschaefer - Engineering News-RecordA natural gas leak in explosive range forced Lawrence, Mass. residents to evacuate their homes early on Sept. 27, according to electric utility National Grid, which cut power to more than 1,300 customers to avoid another disaster like last year's natural gas explosions and fires in Lawrence and two other towns north of Boston. The leak came just days after federal officials called for changes to national pipeline regulations as they released a final report on the causes of the Sept. 13, 2018, disaster.
Read the court decisionRead the full story...Reprinted courtesy of
Johanna Knapschaefer, ENRENR may be contacted at
ENR.com@bnpmedia.com
Fifth Circuit Rules that Settlements in Underlying Action Constitute "Other Insurance"
April 17, 2019 —
Tiffany Casanova - Saxe Doernberger & Vita, P.C.The Fifth Circuit ruled that settlements between an insured and its subcontractors qualified as “other insurance” to the extent those settlements were used to pay for damages covered by an excess insurance policy. Policyholders should note the outcome of this case as it demonstrates the significant impact that settlements can have on coverage.
Satterfield & Pontikes Construction, Inc. v. Amerisure Mutual Ins. Co.1 was the result of a construction project gone wrong. Zapata County, Texas hired Satterfield & Pontikes (“S&P”) as a general contractor for the construction of a courthouse building. When the project did not go as planned, Zapata County terminated S&P, hired new subcontractors to complete the project, and sued S&P.
S&P, in turn, sought indemnification from its subcontractors, who were contractually obligated to indemnify S&P and procure insurance for any damage the subcontractors caused at the project. S&P also sought coverage from its own primary insurers, American Guarantee and Liability Insurance Company (“AGLIC”) and Amerisure Mutual Insurance Company (“Amerisure”), and its excess insurer, U.S. Fire Insurance Company (“U.S. Fire”) who provided liability coverage for S&P’s potential liabilities at the project. The policies contained exclusions for losses arising from mold and did not provide coverage for attorney’s fees or similar legal costs.
Read the court decisionRead the full story...Reprinted courtesy of
Tiffany Casanova, Saxe Doernberger & Vita, P.C.Ms. Casanova may be contacted at
tlc@sdvlaw.com
The 2017 ASCDC and CDCMA Construction Defect Seminar and Holiday Reception
November 21, 2017 —
Beverley BevenFlorez-CDJ STAFFThe annual Construction Defect Seminar and Holiday Reception presented jointly by the Association of Southern California Defense Counsel (ASCDC) and the Construction Defect Claims Managers Association (CDCMA) takes place this November 30th at the Hilton Costa Mesa. This one-day seminar includes two sessions: Session 1, Recent developments in Insurance Coverage and Related Impacts on Case Resolution; Session 2, Impact of Design Claims in Construction Defect Actions. A holiday reception will immediately follow the seminar.
The keynote speaker this year is Hon. Charles Margines, Presiding Judge of the Orange Superior Court. Other speakers include David Napper, Esq., of Chapman Glucksman Dean Roeb & Barger, Adrienne Cohen, Esq., Law Offices of Adrienne D. Cohen, Blenda Eyvazzadeh, Chub North American Claims, and many others. This activity has been approved for Minimum Continuing Legal Education Credit by the State Bar of California in the amount of 3.0 hours.
November 30th, 2017
Hilton Costa Mesa
3050 Bristol Street
Costa Mesa, California 92626
United States
PDF Registration...
Online Registration...
Read the court decisionRead the full story...Reprinted courtesy of
Court Says KBR Construction Costs in Iraq were Unreasonable
August 27, 2014 —
Beverley BevenFlorez-CDJ STAFFMike Bosse of Bernstein Shur, analyzed a case involving Kellogg Brown and Root Services Inc. (KBR) and the U.S. Army for services that KBR provided during Operation Iraqi Freedom, according to JDSupra Business Advisor: “The court case involved KBR’s construction of dining facility services near Mosul, Iraq under a cost-plus fee arrangement. Under this contractual arrangement, all allowable costs were reimbursed by the government plus the contractor was paid an additional fee.”
KBR first started on a prefabricated metal dining hall that would serve 2,500 people, but part way into building they were told to stop construction and to instead start on a new reinforced concrete building that would serve almost three times as many people.
“After construction was finished, a defense contract auditing agency suspended some of the payments to KBR and instead of the $12.5 million it expected to receive, KBR was paid only $6.7 million,” reported JDSupra Business Advisor. “After trial, the court concluded KBR did not meet its burden to show the costs it incurred were reasonable under the circumstances.”
Read the court decisionRead the full story...Reprinted courtesy of