Application Of Two Construction Contract Provisions: No-Damages-For-Delay And Liquidated Damages
February 14, 2022 —
David Adelstein - Florida Construction Legal UpdatesA recent Florida opinion between a prime contractor and a Florida public body touches upon two important issues: (1) the application of a no-damage-for-delay provision; and (2) the application of a liquidated damages provision. Both provisions find there way into many construction contracts. Unfortunately, the opinion is sparse on facts. Nevertheless, the application of these provisions is worthy of consideration.
In this opinion, Sarasota County v. Southern Underground Industries, Inc., 2022 WL 162977 (Fla. 2d DCA 2022), a county hired a contractor to install sanitary and water piping underneath a waterway. During construction, a nearby homeowner complained that vibration from the drilling caused damage to his home. As a result, the county stopped the contractor’s work to address a potential safety issue, as it was contractually entitled to do. The contractor hired a structural engineer to inspect the house and the engineer issued a report determining that any alleged damage was cosmetic and that there was sufficient monitoring of the vibrations to prevent future damage. The contractor also had an insurance policy to cover any homeowner claim for damage. However, upon receipt of the engineer’s report, the county did not lift its stop work order. Rather, the stop work order remained in place for an additional 71 days.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
The Road to Hell is Paved with Good Intentions: A.B. 1701’s Requirement that General Contractors Pay Subcontractor Employee Wages Will Do More Harm Than Good
November 02, 2017 —
Steven M. Cvitanovic & Omar Parra - Haight Brown & Bonesteel LLPTales of subcontractors who close up shop before paying their employees are not all that uncommon, but they are certainly not common enough to require General Contractors to pay for that same labor twice. Last month, the California Legislature passed Assembly Bill No. 1701, which requires the General Contractor of a private construction project to pay all unpaid wages and fringe benefits owed to an employee of a subcontractor, irrespective of the tier, and even if the General Contractor made the payment. With the Governor’s recent signature, Assembly Bill No. 1701 is now the law of the land. Here is what you need to know:
- It applies to all private (but not public) construction contracts entered into on or after January 1, 2018;
- It gives a subcontractor’s employee a direct cause of action against the General Contractor for any unpaid wages and fringe benefits, even if the General Contractor has fully paid the subcontractor;
- It gives a third party owed fringe or other benefits a cause of action against the General Contractor;
- All actions by the employee or third party must be filed within one year of the earliest of the recordation of the notice of completion, the recordation of the notice of cessation of work, or the actual completion of the work;
- The General Contractor cannot contract to avoid the liability imposed by Assembly Bill No. 1701, but it can seek indemnity from the subcontractor; and
- At the General Contractor’s request, the subcontractor shall provide the General Contractor with its payroll records.
Reprinted courtesy of
Steven Cvitanovic, Haight Brown & Bonesteel LLP and
Omar Parra, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com
Mr. Parra may be contacted at oparra@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Warranties: Have You Seen Me Lately?
February 07, 2022 —
Christopher D. Cazenave - ConsensusDocsA construction contract typically contains many different types of warranties. Owners expect contractors to explicitly warrant their workmanship, contractor-provided materials and equipment, and in many instances to assume other warranty risks that may obligate the contractor years after the project is completed.
No contractor wants to be surprised years after a project is completed by the existence of warranty obligations that were not considered or negotiated at the outset of the project. To help avoid this situation, warranties should be treated similar to other critical risk-sharing provisions in the contract in concert with other bargained-for provisions, including for example price and schedule.
This article provides a brief overview of warranty obligations found in typical construction contracts followed by a few practical considerations for contractors to consider when negotiating warranty obligations.
Reprinted courtesy of
Christopher D. Cazenave, Jones Walker, LLP (ConsensusDocs)
Mr. Cazenave may be contacted at ccazenave@joneswalker.com
Read the court decisionRead the full story...Reprinted courtesy of
Wage Theft Investigations and Citations in the Construction Industry
October 11, 2017 —
Evelin Y. Bailey - California Construction Law BlogThis month we share some cautionary tales for employers in the construction industry. During the past several months the California Labor Commissioner has cited or filed suit against several construction companies. In one investigation, a general contractor was held equally responsible for wages owed by a subcontractor to its employees. The lesson learned from these stories is that now more than ever it is important to have in place proper wage and hour practices and to conduct periodic audits of those practices, including those of your lower tiered contractors, preferably by experienced legal counsel.
Read the court decisionRead the full story...Reprinted courtesy of
Evelin Y. Bailey, California Construction Law Blog
World's Longest Suspension Bridge Takes Shape in Turkey
November 29, 2021 —
Aileen Cho - Engineering News-RecordIt was a long-standing dream—not only of Ersin Arıoğlu, but of a nation. Could a suspension bridge someday cross the Dardanelles Strait in Turkey and provide another link between Europe and Asia? “To build a highway suspension bridge over the Çanakkale Strait has been on the agenda of the Turkish Ministry of Public Works for the last 20 years,” Arıoğlu, co-founder of contractor Yapi Merkezi, wrote in a technical paper. That was in 1994.
Reprinted courtesy of
Aileen Cho, Engineering News-Record
Ms. Cho may be contacted at choa@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Construction Insurance Rates Up in the United States
November 20, 2013 —
CDJ STAFFA new report says that construction firms paid from three to seven percent more on average during the first six months of 2013 than they had in the last half of 2012. Firms with poor loss histories paid even more, reaching double-digit increases.
Michael Anderson, of Marsh’s U.S. Construction Practice said that “U.S. construction firms are grappling with a firming insurance market, especially when it comes to liability insurance where underwriters continue to tighten coverage terms and seek rate increases to make up for reduced investment income.” He did note that “the good news for well-managed construction firms is they can still generally find competitive pricing and terms.”
Read the court decisionRead the full story...Reprinted courtesy of
Delay In Noticing Insurer of Loss is Not Prejudicial
April 28, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe Tenth Circuit reversed a district court's determination that untimely notice of the loss was prejudicial, eliminating the insurer's coverage obligations. B.S.C. Holding, Inc. v. Lexington Ins. Co., 2014 U.S. App. LEXIS 4492 (10th Cir. March 11, 2014).
In January 2008, the insured's employees detected an inflow of water in a salt mine and feared dissolution of the salt or structural problems. The insured tried to devise a solution. Two and a half million dollars were spent to find the cause of the water inflow and to identify a solution. In April 2010, the insured determined the inflow was caused by an improperly sealed oil well. In July 2010, the insured notified Lexington of the water inflow. The ultimate proof of loss was for $7.5 million, which included remediation measures that the insured had performed before notifying Lexington.
Lexington's all-risk policy required the insured to notify the company in writing as soon as practicable.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Los Angeles Construction Sites May Be on Fault Lines
December 30, 2013 —
CDJ STAFFCalifornia law prohibits building near or on top of earthquake fault lines, but Los Angeles County building officials may have used outdated information that misreported the location of certain faults. The Los Angeles Times reports that after their earlier articles on fault lines, the officials have started using newer maps.
According to the older maps, an apartment building under construction on Brockton Avenue in Los Angeles is 1.9 miles away from the Santa Monica fault. But a more recent map, created by the state in 2010, shows that the fault line could potentially be right under the building site.
The builders of another apartment building potentially located on the Santa Monica fault said that the city did not ask for a fault investigation. The Los Angeles Department of Building and Safety said that there was no official zone designation for the Santa Monica fault, and so did not require seismic studies.
Read the court decisionRead the full story...Reprinted courtesy of