Terminating Notice of Commencement Without Contractor’s Final Payment Affidavit
October 23, 2018 —
David Adelstein - Florida Construction Legal UpdatesPrior to construction work being performed on your property, a Notice of Commencement should be recorded. Among other things, construction liens will relate back in time to an effective Notice of Commencement (meaning it has not expired). For this reason, lenders or others will want the Notice of Commencement to be terminated when the job is complete by recording in the official records a Notice of Termination of the Notice of Commencement. There is a statutory procedure to terminate a Notice of Commencement pursuant to Florida Statute 713.132.
Frequently, a clerk will want the Notice of Termination of the Notice of Commencement to be accompanied with a Contractor’s Final Payment Affidavit because 713.132 says, in material part:
(2) An owner has the right to rely on a contractor’s affidavit given under s. 713.06(3)(d), except with respect to lienors who have already given notice, in connection with the execution, swearing to, and recording of a notice of termination. However, the notice of termination must be accompanied by the contractor’s affidavit.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Saudi Arabia Awards Contracts for Megacity Neom’s Worker Housing
September 16, 2019 —
Vivian Nereim - BloombergSaudi Arabia has awarded to two Saudi firms contracts to build worker housing for its futuristic mega-city called Neom, as plans for the $500 billion project move forward despite skepticism from investors.
Tamimi Group and Saudi Arabian Trading & Construction Co. won contracts to finance, build and operate three residential areas with capacity to house 30,000 people, Neom said in a statement on Sunday. The areas will be part of a so-called “Construction Village,” which Neom later plans to expand to accommodate more than 100,000 residents, it said. Neom did not say how much the contracts were worth.
Read the court decisionRead the full story...Reprinted courtesy of
Vivian Nereim, Bloomberg
New Law Raises Standard for Defense Experts as to Medical Causation
September 05, 2023 —
Haight Brown & Bonesteel LLPOn July 17, 2023, California Governor Gavin Newsom signed Senate Bill (SB) No. 652, adding Section 801.1 to the California Evidence Code. This section provides additional requirements for expert opinions relating to medical causation. In particular, it allows a party not bearing the burden of proof to offer a contrary expert in response to an expert proffered by a party bearing the burden of proof as to medical causation who is required to opine that causation exists to a reasonable medical probability. The contrary expert may only be proffered, however, if he or she is able to opine that an alternative medical causation is one that exists to a reasonable medical probability. Section 801.1, however, does not preclude an expert witness from testifying that a specific matter cannot meet a reasonable degree of probability in the applicable field.
With respect to medical causation, a “reasonable degree of probability” means that the expert is testifying that a particular event or source was more likely than not the cause of a person’s injuries.
Read the court decisionRead the full story...Reprinted courtesy of
Haight Brown & Bonesteel LLP
Finding Insurer's Declaratory Relief Action Raises Unsettled Questions of State Law, Case is Dismissed
November 05, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court for the District of Hawaii dismissed the insurer's action for declaratory relief because it raised issues that were unsettled by Hawaii courts. Association of Apartment Owners of Lahaina Residential Condominium, et al., No. 1-24-cv-00075-JAO-BMK, Order Granting AOAO's Motion to Dismiss (D. Haw. Aug. 29, 2024).
The case addressed whether a property damage exclusion barred coverage over an owner's claim that a condominium association and its property manager failed to obtain adequate insurance before the condominium's property was damaged by the Maui wildfire in August 2023. Great American filed suit seeking a declaration that it had no duty to defend or indemnify the Association and the property manage, Quam Properties Hawaiiana, Inc., in connection with a demand for mediation submitted to the Association and Quam on behalf of one of the owners.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Effective Allocation of Damages for Federal Contract Claims
October 25, 2021 —
Dirk D. Haire, Joseph L. Cohen & Jane Han - ConsensusDocsFederal construction contracts law generally recognizes four basic methods for pricing damages: (1) Actual Cost Method (ACM); (2) Total Cost Method (TCM); (3) Modified Total Cost Method (MTCM); and (4) Jury Verdict Recovery Method (JVRM). In practice, it is difficult to obtain significant recoveries on TCM and JVRM claims, and only marginally easier on MTCM claims. That is because the courts and boards that hear federal government contracts cases have developed a clear preference for the ACM. Despite this preference, many contractors do not have systems in place to maximize their opportunity to recover damages under the ACM. This article introduces various strategies for tracking and allocating damages during project performance in a manner that will support an ACM analysis if a federal construction claim is litigated.
Background: Four Basic Methods for Pricing Damages
The four methods for pricing damages are described, below:
1. Actual Cost Method
The actual cost method claims damages based on records of “actual costs” that were documented during the performance of the contract. All additional costs must be separately recorded from the costs incurred in the normal course of contract performance. Because contractors provide the court or board with documented underlying expenses under the actual cost method, courts and boards prefer this method. However, the actual cost method may not always be feasible where a contractor is confronted with drastic changes early and often in a project.
Reprinted courtesy of
Dirk D. Haire, Fox Rothschild LLP,
Joseph L. Cohen, Fox Rothschild LLP and
Jane Han, Fox Rothschild LLP
Mr. Haire may be contacted at dhaire@foxrothschild.com
Mr. Cohen may be contacted at jlcohen@foxrothschild.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Law Firm Welin, O'Shaughnessy + Scheaf Merging with McDonald Hopkins LLC
February 05, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to a press release on PR Newswire, Columbus, Ohio law firm McDonalds Hopkins LLC is merging with firm Welin, O’Shaughnessy + Scheaf. McDonalds Hopkins LLC is “a business advisory and advocacy law firm with a more than 80-year history.” They are looking to expand their “Columbus presence” by the merger with “the boutique firm” that specializes in construction law, complex business litigation and oil and gas litigation.
Read the court decisionRead the full story...Reprinted courtesy of
Sometimes You Get Away with Unwritten Contracts. . .
January 20, 2020 —
Christopher G. Hill - Construction Law MusingsI have spoken often regarding the need for a well written construction contract that sets out the “terms of engagement” for your construction project. A written construction contract sets expectations and allows the parties to the contract to determine the “law” of their project. An unwritten “gentleman’s agreement” can lead to confusion, faulty memories, and more money paid to construction counsel than you would like as we lawyers play around in the grey areas.
One other area where the written versus unwritten distinction makes a difference is in the calculation of the statute of limitations. In Virginia, a 5 year statute of limitations applies to written contracts while a 3 year statute of limitations applies to unwritten contracts. This distinction came into stark relief in the case of M&C Hauling & Constr. Inc. v. Wilbur Hale in the Fairfax, Virginia Circuit Court. In M&C Hauling, M&C provided hauling services to the defendant through a subcontract with Hauling Unlimited in 2014, the last of which was in July. M&C provided over 2000 hours of hauling and provided time tickets (that were passed to Mr. Hale on Hauling Unlimited letterhead and signed by Mr. Hale or his agent) and an invoice stating the price term of $75.00 per hour. No separate written contract between M&C and Hauling Unlimited or Mr. Hale existed.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Fourth Circuit Rejects Application of Wrap-Up Exclusion to Additional Insured
December 11, 2018 —
K. Alexandra Byrd & Samantha M. Oliveira - Saxe Doernberger & Vita, P.C.Utilizing an owner-controlled or contractor-controlled insurance program (collectively known as “wrap-ups”) can reduce claims, save costs, and give owners and general contractors comfort in knowing their project is adequately insured. However, problems often arise when a subcontractor doesn’t enroll in the wrap-up and, instead, agrees to provide additional insured coverage to the owner and general contractor on the subcontractor’s own general liability policy. One of those problems is the prevalence of wrap-up exclusions on subcontractors’ general liability policies. If the wrap-up exclusion is too broadly drafted, the exclusion can eliminate coverage for the general contractor and owner even when the subcontractor is not enrolled in the wrap-up.
Reprinted courtesy of
K. Alexandra Byrd, Saxe Doernberger & Vita, P.C. and
Samantha M. Oliveira, Saxe Doernberger & Vita, P.C.