Kiewit-Turner Stops Work on VA Project—Now What?
December 31, 2014 —
Craig Martin – Construction Contractor AdvisorThe Kiewit-Turner joint venture created to build the VA’s hospital near Denver stopped work on December 10 after the Civilian Board of Contract Appeals ruled that the VA breached the contract. Kiewit-Turner claims that the VA owes it over $100 million on the project. And, given the appeals board’s recent ruling entirely against the VA, the claim may get some traction.
This project has been plagued with problems from the beginning. One strange aspect of the project is the VA’s apparent unwillingness to incorporate value engineering or require the architects to redesign the project to fit within the budget. The latest budget was $582M, while the latest projections show that the project will cost more than $1 billion to complete.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
New York Appellate Court Affirms 1966 Insurance Policy Continues to Cover WTC Asbestos Claims
January 02, 2019 —
Michael S. Levine & Joshua S. Paster - Hunton Andrews KurthIn a prior post, we discussed a New York trial-court decision that found an insurance policy issued in 1966, to insure the construction of the World Trade Center, continues to cover modern-day asbestos claims, with each claim constituting an individual occurrence. Last week, in American Home Assurance Co. v. The Port Authority of N.Y. and N.J., 7628-7628A (1st Dep’t Nov. 15, 2018), an intermediate appellate court affirmed that decision, agreeing that coverage is triggered for claims tied to alleged asbestos exposure at the WTC site in the 1960s and ’70s.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Joshua S. Paster, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Paster may be contacted at jpaster@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Yet ANOTHER Reminder to Always Respond
July 11, 2021 —
Christopher G. Hill - Construction Law MusingsYou would think I wouldn’t have to discuss the absolute need to respond to any served pleadings, particularly after some of the prior examples of what can happen if you fail to respond. Of course, I wouldn’t be starting a post like this if those that were sued contacted an experienced attorney in a timely fashion and followed this advice.
Yet another example of the disastrous results that can occur simply from failing to file responsive pleadings occurred last year in the Eastern District of Virginia federal court in Alexandria, VA. In Pro-Telligent, LLC v. Amex Int’l, Inc. the Court considered a claim for breach of contract (among other causes of action) by Pro-Telligent against Amex. The operative facts are that Pro-Telligent was a subcontractor to Amex that claimed it was unpaid in the amount of $279,660.27, its Complaint was served on January 7, 2021, and Amex did not respond within the required 21-day window. The Court then held a hearing on February 28, 2020, regarding the validity of the Clerk of Court’s entry of default per the rules of court.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
The Creation of San Fransokyo
June 17, 2015 —
Garret Murai – California Construction Law BlogSome of the most awe inspiring buildings and urban environments started off on paper and, these days, on computer screens. Think Babylon or even Pierre Charles L’Enfant’s Washington, D.C..
Most of those structures and cityscapes were designed for human habitation, but not all. Some were designed purely for our imaginations, like Minecraft, which those of you with young ones might be familiar with.
Another more recent example though is Big Hero 6, about a science-whiz named Hiro (pronounced “hero,” get it) who journeys from boyhood to manhood and saves the world along the way with his robot pal Baymax. The movie is set in foreign-yet-familiar “San Fransokyo.”
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Wake County Justice Center- a LEED Silver Project done right!
October 01, 2014 —
Melissa Dewey Brumback – Construction Law in North CarolinaYesterday evening, I had the privilege of attending the Triangle USGBC’s “Talk & Walk” at the Wake County Justice Center. The 576,996 square foot Justice Center was completed 6 months early and over 30 million under budget. (The final cost, including soft costs, came in at ~$141,000,000). Now that’s what I call a LEED project done right!
Interestingly, the County did not endeavor for a LEED Silver rating– the plan was to aim for a Certification. However, as the process unfolded, the Team kept meeting the goals and points for a Silver certification without any appreciable additional costs.
The end result? An “iconic but energy efficient building,” according to Tim Ashby, current Wake County Facilities Project Manager. Tim was initially involved in the Project while working at O’Brien Atkins, which served as the architecture firm for the Project under the direction of Architect Andrew Zwiacher.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback may be contacted at
mbrumback@rl-law.com
Discovery Requests in Bad Faith Litigation Considered by Court
June 10, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe federal district court considered a variety of discovery requests by the insured in a bad faith case against State Farm. Stephens v. State Farm Fire and Cas. Co., 2015 WL 1638516 (M.D. Pa. April 13, 2015).
The insured plaintiff was a quadriplegic. His complaint alleged that he notified State Farm, through its agent, that he would have to leave his residence for medical treatment and intended to rent the home while he received care for his disabling condition. The complaint further alleged that the insured was told by State Farm's agent that his insurance would remain unaffected by his departure while he sought medical care. Nevertheless, when the insured reported loss due to vandalism and water damage at his home, State Farm relied upon his departure from the residence to cancel his insurance.
In discovery, the insured requested three categories of documents from State Farm. First, he requested State Farm's claims manuals, guidelines and instructions materials relating to insurance claims like those made by this insured. Second, the plaintiff requested performance reviews and performance incentive programs for all of State Farm's employees who played a role in decisions in this case from 2009 to the present. Finally, the plaintiff demanded that State Farm compile information relating to other insurance lawsuits brought against State Farm involving theft, vandalism and water damage claims, as well as all lawsuits or complaints regarding the conduct of this particular claims adjuster. When the materials were not produced, plaintiff filed a motion to compel.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Construction Contract Provisions that Should Pique Your Interest
September 30, 2019 —
Christopher G. Hill - Construction Law MusingsConstruction contracts are a big part of my legal practice and the drumbeat here at Construction Law Musings. Why? Because not only does your construction contract set the expectations and “rules of the game” for a construction project, it will be read strictly and literally by the Virginia courts should there be a dispute. For these reasons, construction professionals need to be alert for the language in certain key clauses in a construction contract to assure that these clauses are as balanced as possible and also well understood. Here are my “Top Five”:
- “Pay if Paid”- These clauses are almost always in the subcontracts between a general contractor and a subcontractor and are enforceable in Virginia if drafted correctly and under the proper circumstances.
- Change Orders- Whether work is subject to a change order and the required payment for any changed work are often a key source of contention (read legal fees). A properly drafted and followed change order provision can help avoid much of this contention.
- Indemnity- Much has been made in recent years about indemnity provisions and their enforceability. All parties in the construction payment chain can and should be aware of how to best draft their indemnity provisions to make them enforceable. Failure to do so can be catastrophic.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Recent Bribery and Anti-Corruption Enforcement Trends in Global Construction Industry
August 26, 2019 —
Ralph A. Finizio & Anthony Finizio - ConsensusDocsBribery and corruption have long plagued the construction industry, particularly in the developing world and emerging markets. Large contracts often trickle down through layers of subcontractors, presenting opportunities for corruption at each level. The risk is enhanced in certain foreign jurisdictions, where large corporations may be wholly or partially state-owned enterprises and public officials may expect payment in exchange for state-issued licenses or government contracts.
Recent enforcement trends indicate that both the U.S. Department of Justice (DOJ) and the Securities and Exchange Commission (SEC) are increasingly targeting the construction industry for anti-bribery and corruption actions under the Foreign Corrupt Practices Act (FCPA). Several former DOJ officials also recently commented that the construction industry has become a focus of anti-corruption enforcement efforts.
The FCPA is a formidable tool for regulators, making it unlawful to influence a foreign government official with any type of payment or personal reward. While certain safe harbors apply — including de minimis payments made to expedite routine governmental action or the payment being lawful in the foreign jurisdiction — these exceptions are construed narrowly and can be difficult to apply in practice.
Reprinted courtesy of
Ralph A. Finizio, Pepper Hamilton LLP and
Anthony Finizio, Pepper Hamilton LLP
Mr. Finizio may be contacted at finizior@pepperlaw.com
Mr. Finizio may be contacted at finizioa@pepperlaw.com
Read the court decisionRead the full story...Reprinted courtesy of