DE Confirms Robust D&O Protection Despite Company Demise
February 18, 2015 —
James Yoder, Michael Onufrak and Siobhan Cole – White and Williams LLPOn Feb. 5, 2015, the United States Bankruptcy Court for the District of Delaware, per Judge Brendan L. Shannon, entered proposed findings of fact and conclusions of law in favor of the former president and CEO of Ultimate Escapes Inc., James M. Tousignant, and its chairman, Richard Keith, after determining that Tousignant’s actions in negotiating and executing a controversial asset purchase agreement were protected by the business judgment rule, despite the demise of the company a short time later. The failure of a business strategy, in and of itself, does not create liability on the part of the former directors and officers of a bankrupt company.
Background
Ultimate Escapes was a luxury destination club that provided its members with access to high-end vacation residences around the world. Unfortunately, Ultimate Escapes’ business suffered greatly from the economic downturn that began in 2008, and on Sept. 20, 2010, Ultimate Escapes filed voluntary petitions for relief pursuant to Chapter 11 of the Bankruptcy Code.
Reprinted courtesy of White and Williams LLP attorneys
James Yoder,
Michael Onufrak and
Siobhan Cole
Mr. Yoder may be contacted at yoderj@whiteandwilliams.com
Mr. Onufrak may be contacted at onufrakm@whiteandwilliams.com
Ms. Cole may be contacted at coles@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Part I: Key Provisions of School Facility Construction & Design Contracts
May 16, 2018 —
David R. Cook Jr. - Autry, Hall & Cook, LLPWe all expect our school construction projects will go smoothly, on time and under budget. But despite our best efforts, some projects will encounter speed bumps, detours or outright roadblocks. While there are many precautions a school facility manager may take, one of the best precautions is to have solid construction and design contracts.
A good contract will account for the known risks and specify an outcome in favor of the school authority. School construction risks can be categorized into a few categories: performance risk, time risk, cost risk and political risk. Some risks are typical to all construction projects, while others are peculiar to the unique needs of school authorities.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
City Potentially Liable for Cost Overrun on Not-to-Exceed Public Works Contract
June 29, 2017 —
David R. Cook Jr. - Autry, Hanrahan, Hall & Cook, LLPOn a public works construction project, a contractor incurred additional costs and asserted a claim against the city. The city denied the claim because the contract had a not-to-exceed price, and the city council and mayor did not approve contract modifications to exceed that amount. City ordinances require approval for contract modifications and change orders exceeding ten percent of the original not-to-exceed amount.
But the contractor argued that the ordinance did not apply because the excess costs did not result from a contract modification or change order. In addition, the contractor argued that, in refusing to approve an increase in the not-to-exceed amount, the city breached the implied duty of good faith and fair dealing. The court concluded that these questions were factual issues for the jury to decide.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hanrahan, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Foreclosing Junior Lienholders and Recording A Lis Pendens
July 13, 2020 —
David Adelstein - Florida Construction Legal UpdatesWhen you foreclose on a construction lien, there are a couple of pointers to remember.
First, you want to make sure you include junior lienholders or interests you are looking to foreclose (or you want to be in a position to amend the foreclosure lawsuit to identify later). The reason being is you want to foreclose their interests to the property. “[J]unior interest holders are a narrow class of mortgagees whose interest in the underlying property is recorded after the foreclosing contractor’s claim of lien is filed. This class is routinely joined to the construction lien enforcement action under section 713.26 to allow the construction lienor to foreclose out the junior lienholder’s interest in the property encumbered by the construction lien.” See Decks N Sunch Marine, infra.
Second, you want to record a lis pendens with the lien foreclosure lawsuit. Failure to do so could be problematic because Florida Statute s. 713.22(1) provides in part, “A lien that has been continued beyond the 1-year period by the commencement of an action is not enforceable against creditors or subsequent purchasers for a valuable consideration and without notice, unless a notice of lis pendens is recorded.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
California Court of Appeal Affirms Trial Court’s Denial of anti-SLAPP Motion in Dispute Over Construction of Church Facilities
March 27, 2023 —
Garrett A. Smee & Lawrence S. Zucker II - Haight Brown & Bonesteel LLPOn February 28, 2023, the California Fourth District Court of Appeal, Division One, issued an opinion in Billauer v. Escobar-Eck (D079835), affirming the trial court’s denial of an anti-SLAPP motion stemming from a public debate over a Church construction project.
The Appellant (Billauer) ran several social media sites as a “neighborhood activist.” The Respondent (Escobar-Eck) ran a land use and strategic planning firm in San Diego. The “All People’s Church” had hired Escobar-Eck’s company in 2019 to obtain City approval for a Church campus. During a Zoom presentation by Escobar-Eck to a Church planning group on November 11, 2020, Billauer, as a participant in the meeting sent a chat to Escobar-Eck stating: “I’m going to make sure you get sent back to where you came from.” Over the span of the next six months, from November 11, 2020 to April 8, 2021, Billauer continued the onslaught through a series of five posts on Instagram and Facebook, attacking Escobar-Eck. On December 10, 2020, Escobar-Eck fired back with a Twitter post to Billauer’s employer, Wells Fargo, labeling Billauer as a cyberbullying racist.
Reprinted courtesy of
Garrett A. Smee, Haight Brown & Bonesteel LLP and
Lawrence S. Zucker II, Haight Brown & Bonesteel LLP
Mr. Smee may be contacted at gsmee@hbblaw.com
Mr. Zucker may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Where Breach of Contract and Tortious Interference Collide
July 18, 2022 —
Christopher G. Hill - Construction Law MusingsClaims for breach of contract are numerous in the construction law world. Without these claims we construction attorneys would have a hard time keeping the doors open. A 2021 case examined a different sort of claim that could arise (though, “spoiler alert” did not in this case) during the course of a construction project. That type of claim is one for tortious interference with business expectancy.
In Clark Nexsen, Inc. et. al v. Rebkee, the U. S. District Court for the Eastern District of Virginia gave a great explanation of the law of this type of claim in analyzing the following basic facts:
In 2018, Clark Nexsen, Inc. (“Clark”) and MEB General Contractors, Inc. (“MEB”) responded to Henrico County’s (“Henrico”) Request for Proposals (“RFP”) for the design and construction of a sport and convocation center (the “Project”). Henrico initially shortlisted Clark and MEB as a “design-build” team for the Project, but later restarted the search, issuing a second RFP. Clark and MEB submitted a second “design-build” proposal, but Henrico selected Rebkee Co. (“Rebkee”) for certain development aspects of the Project. MEB also submitted proposals to Rebkee, and Rebkee selected MEB as the design-builder for the Project. MEB, at Rebkee’s request, solicited proposals from three design firms and ultimately selected Clark as its design partner. From December 2019 to May 2020, Clark and MEB served as the design-build team to assist Rebkee in developing the Project. In connection therewith, Clark developed proprietary designs, technical drawings, and, with MEB, several cost estimates. In February 2020, MEB submitted a $294,334.50 Pay Application to Rebkee for engineering, design, and Project development work. Rebkee never paid MEB. Henrico paid MEB $50,000.00 as partial payment for MEB’s and Clark’s work. MEB then learned that Rebkee was using Clark’s drawings to solicit design and construction proposals from other companies. On July 23, 2020, Rebkee told MEB that Henrico directed it to cancel the design-build arrangement with MEB and Clark and pursue a different planning method. MEB and Clark sued and Rebkee for, among other claims, tortious interference with a business expectancy. Rebkee moved to dismiss the tortious interference claim.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
I.M. Pei, Architect Who Designed Louvre Pyramid, Dies at 102
July 01, 2019 —
James S. Russell - BloombergI.M. Pei, a dominant figure in American architecture for more than three decades who designed the Louvre’s crystal pyramid and the angular East Building of Washington’s National Gallery of Art, has died. He was 102.
His son Li Chung Pei said on Thursday that his father had died overnight, the New York Times reported.
Pei gave “this century some of its most beautiful interior spaces and exterior forms,” said the jury of the Pritzker Architecture Prize, which Pei won in 1983.
Though reserved and supremely diplomatic, Pei’s face, always crowned by round thick-rimmed glasses, could break unexpectedly into a wide, dazzling smile. He approached clients with charm and a quick wit, and they usually succumbed happily.
Read the court decisionRead the full story...Reprinted courtesy of
James S. Russell, Bloomberg
Why You Make A Better Wall Than A Window: Why Policyholders Can Rest Assured That Insurers Should Pay Legal Bills for Claims with Potential Coverage
March 14, 2018 —
Alan Packer and Graham Mills - Newmeyer & Dillion, LLPUnfortunately, policyholders, such as manufacturers and contractors, routinely face the unnecessary challenge of how to access all of the insurance coverage which they have purchased. Frequently, the most pressing need is to get the insurance company to pay the legal bills when the policyholders have been sued. The recent Iowa federal district court opinion in
Pella Corporation v. Liberty Mutual Insurance Company should help a policyholder in a dispute to require its insurance company to pay those legal bills sooner rather than later by highlighting that the duty to defend arises from the potential for coverage, and the insurer may not force the policyholder to prove the damage to obtain a defense.
In
Pella, a window manufacturer purchased several years of insurance coverage from Liberty Mutual. Similar to many companies, Pella had many “layers” of insurance coverage in any given year. These layers collectively function like a tower. The general idea is that each layer provides a certain amount of coverage after the insurance policy below it had paid its money. The Liberty Mutual insurance policies provided excess coverage.
After the
Pella window manufacturer made and sold its windows, it was sued in numerous lawsuits alleging that its windows were defective and that those defective windows caused a wide variety of damage to the structures in which they were installed. The window manufacturer tendered those lawsuits to its insurance companies in its tower of coverage, asking that the insurance companies pay its legal bills incurred in its defense. As to Liberty Mutual, the window manufacturer argued that the Liberty Mutual insurance policies were triggered, and so obligated to reimburse it, if a window was installed during the years that those policies provided coverage or if there was a mere allegation that a window was installed during the years that those policies provided coverage. Liberty Mutual opposed, arguing that the date of installation of the windows was insufficient to trigger the policies, and that the manufacturer was required to demonstrate the date that damage actually occurred to trigger a defense.
The key issue before the
Pella Court in this decision was a simple one: which insurance policies, if any, issued by Liberty Mutual had an obligation to pay the window manufacturer’s legal bills? The answer to that question is critical and financially significant. Getting an insurance company to honor its obligations and start paying the legal bills as soon as possible is very important for a policyholder because of the cost of defending oneself in a lawsuit; often the key reason why an insurance policy is even purchased is to provide the policyholder with the right to call upon the insurance company’s financial resources to defend it should it be sued.
In a ruling that will be welcomed by policyholders, the
Pella Court held that Liberty Mutual’s multiple insurance policies were triggered, and so obligated to pay for the window manufacturer’s defense, if one of two events occurred during the years in which those insurance policies provided coverage: (1) a window was actually installed during a year when the insurance policy provided coverage or (2) the window was alleged to be installed in the year that the insurance policy provided coverage. The Court agreed with the policyholder that once the windows were installed, property damage was alleged and “may
potentially have occurred” from that point on, thus the policies on the risk from that point forward. The practical effect of this ruling meant that Liberty Mutual had to reimburse the window manufacturer for the defense fees and costs that it had paid.
While
Pella was decided under Iowa law, the principles upon which it relied are similar to those applied under California law. Importantly, both California and Iowa law hold that an insurance company must provide a defense in response to a claim that is, or could be, covered by the insurance policy. The mere potential that the claim might be covered is enough for the insurance company to be obligated to pay for policyholder’s legal fees and costs.
Establishing that an insurance company must pay legal fees and costs as soon as possible allows a policyholder to save its own money. Why should a policyholder pay legal bills when it purchased an insurance policy as protection to ensure that it did not have to pay those bills? The answer is that a policyholder should not and, under
Pella, the policyholder does not have to. Rather, the insurance company must start paying for that defense from a very early date. Pella confirms for policyholders the position that their insurance companies should pay legal bills earlier rather than later.
Alan Packer is a partner in the Walnut Creek office for Newmeyer & Dillion, LLP, representing homebuilders, property owners, and business clients on a broad range of legal matters, including risk management, insurance matters, wrap consultation and documentation, efforts to counter solicitation of homeowners, subcontract documentation, as well as complex litigation matters. Alan can be reached at alan.packer@ndlf.com.
Graham Mills is a partner in the Walnut Creek offce of Newmeyer & Dillion, LLP, representing clients in the area of complex insurance law with an emphasis on insurance recovery, construction litigation, real estate litigation, and business litigation. He regularly examines and analyzes a wide variety of insurance policies. Graham can be reached at graham.mills@ndlf.com.
ABOUT NEWMEYER & DILLION LLP
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client’s needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review’s AV Preeminent® highest rating.
For additional information, call 949.854.7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of