Lending Plunges to 17-Year Low as Rates Curtail Borrowing
April 15, 2014 —
Kathleen M. Howley, Zachary Tracer and Heather Perlberg – BloombergWells Fargo (WFC) & Co. and JPMorgan Chase & Co., the two largest U.S. mortgage lenders, reported a first-quarter plunge in loan volumes that’s part of an industry-wide drop off. Lenders made $226 billion of mortgages in the period, the smallest quarterly amount since 1997 and less than one-third of the 2006 average, according to the Mortgage Bankers Association in Washington.
Lending has been tumbling since mid-2013 when mortgage rates jumped about a percentage point after the Federal Reserve said it might taper stimulus spending. A surge in all-cash purchases to more than 40 percent has kept housing prices rising, squeezing more Americans out of the market. That will help push lending down further this year, according to the association.
Ms. Howley may be contacted at kmhowley@bloomberg.net; Mr. Tracer may be contacted at ztracer1@bloomberg.net; Ms. Perlberg may be contacted at hperlberg@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Kathleen M. Howley, Zachary Tracer and Heather Perlberg, Bloomberg
San Diego: Compromise Reached in Fee Increases for Affordable Housing
October 01, 2014 —
Beverley BevenFlorez-CDJ STAFFA San Diego City Council committee has forwarded a revised plan to increase affordable housing in the city, which reduces the linkage fees increases, reported the U-T San Diego. The first proposal would have increased linkage fees by five times, while this new plan doubles current fees.
The Times of San Diego reported that “[t]he fee had been halved in 1996 as an economic stimulus and was supposed to be reviewed annually, but wasn't.” However, Andrea Tevlin, the city of San Diego’s Independent Budget Analyst, estimated that “costs on developers would have jumped 400 percent to more than 700 percent, depending on the type of project.”
The new proposal also contains exemptions for “developers of manufacturing facilities, warehouses and nonprofit hospitals from paying any fees at all,” according to U-T San Diego. “Developers of research and science-related projects would still have to pay fees, but they would be exempt from the proposed increase.”
However, not everyone is satisfied by the compromise. “While the November 2013 proposal went too far, this new proposal doesn’t go far enough,” Tevlin told U-T San Diego. The vote had been deadlocked, 2-2, but will be forwarded to the main council because Republican Lori Zapf, committee chair, could break the tie.
The new plan “created jointly by the San Diego Housing Commission and a group of business leaders called the Jobs Coalition, would increase the linkage fees’ annual yield from $2.2 million to an estimated $3.7 million and allow construction of 37 affordable housing units per year instead of 22,” U-T San Diego reported.
Read the full story, U-T San Diego...
Read the full story, Times of San Diego... Read the court decisionRead the full story...Reprinted courtesy of
Exceptions to Privette Doctrine Do Not Apply Where There is No Evidence a General Contractor Affirmatively Contributed to the Injuries of an Independent Contractor's Employee
November 17, 2016 —
Renata L. Hoddinott & Lawrence S. Zucker II – Haight Brown & Bonesteel LLPThe Court of Appeal of the State of California – Second Appellate District in Khosh v. Staples Construction Company, Inc. (10/26/16 – Case No. B268937) affirmed the trial court’s granting of summary judgment in favor of the defendant under the Privette doctrine where plaintiff presented no evidence that the defendant affirmatively contributed to his injuries.
Plaintiff Al Khosh (“Khosh”) was injured while performing electrical work on a project. He was employed by Myers Power Products, Inc. (“Myers”) a subcontractor for the project. Khosh sued the general contractor, Staples Construction Company, Inc. (“Staples”) to recover damages for his injuries.
Reprinted courtesy of
Renata L. Hoddinott, Haight Brown & Bonesteel LLP and
Lawrence S. Zucker II, Haight Brown & Bonesteel LLP
Ms. Hoddinott may be contacted at rhoddinott@hbblaw.com
Mr. Zucker may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
FIFA May Reduce World Cup Stadiums in Russia on Economic Concern
July 16, 2014 —
Tariq Panja – BloombergFIFA may reduce the number of stadiums used to host the 2018 World Cup in Russia on concern that their economic viability after the monthlong event ends.
FIFA President Sepp Blatter said a day after Germany’s 1-0 win over Argentina in the final that a delegation from soccer’s governing body will meet Russian tournament organizers in September to discuss plans for the next edition.
Blatter gave a mark of 9.25 out of 10 to an “exceptional” Brazil World Cup, which cost $11 billion to stage. The tournament is a difficult challenge for organizers, Blatter said, illustrated by construction delays at almost all of the 12 arenas used for the 64 games in Brazil.
“The World Cup has taken such a dimension that the organization is hard work for the organizing country and also for FIFA,” Blatter told reporters at Rio de Janeiro’s Maracana stadium, where Germany claimed a fourth title and became the first European country to win the tournament in South America.
Read the court decisionRead the full story...Reprinted courtesy of
Tariq Panja, BloombergMr. Panja may be contacted at
tpanja@bloomberg.net
Construction Defect Lawsuit Came too Late in Minnesota
June 28, 2013 —
CDJ STAFFThe Minnesota Court of Appeals has upheld a summary judgment in a construction defect case, Lee v. Gorham. Minnesota law requires that contractors warranty that the home will be free of major construction defects during the first ten years, but claims must “be brought within two years of the discovery of the breach.” The Lees received a home inspection report in 2009 that identified a variety of defects, including “several possible structural defects.” The court noted that the report stated, “Contact your builder in writing of the findings, and discuss your options with an attorney.”
The Lees contacted the contractor, Gorham Builders. After initial silence, Gorham told the Lees that problems would “have to be ‘turned over to [the] insurance company.’” Rodney noted in his testimony that he had two choices, to either sue Gorham or hire an outside contractor. Mr. Lee had concluded that the legal costs were likely to be equal to the cost of the contractor.
In June, 2011, the Lees changed their mind about bringing a suit. Gorham sought and received a summary judgment dismissing the case on the grounds that too much time had passed since the Lees learned of the construction defect. The Lees appealed.
The appeals court upheld the summary judgment. The Lees claimed that the 2009 home inspection did not alert them of a “major construction defect,” but the court concluded that the language of the report fit within the Minnesota statutory definition of a “major construction defect.”
Nor was the appeals court convinced that at any time did Gorham provide “assurances that it would cure the defects to the home.” Within the same month as the May 2009 inspection, Gorham had made it clear that any problems were an issue for the insurance company. Thus, the appeals court concluded that the Lee’s equitable-estoppel argument was without merit.
The Lees also brought to appeal the new argument that they did not realize they were dealing with “major construction defects” until they received a subsequent home inspection in 2011. The court noted that the second report does not detail “new defects or structural issues not identified in the 2009 inspection report.” In addition to being “without merit,” the court noted that this claim was not made in the district court and so the appeals court “need not consider this issue on appeal.”
Read the court decisionRead the full story...Reprinted courtesy of
From Singapore to Rio Green Buildings Keep Tropical Tenants Cool
June 07, 2021 —
Andrew Janes & Shawna Kwan - BloombergOn a typically hot and humid afternoon in Singapore, a fresh breeze blows beneath the canopy of the South Beach development, keeping temperatures several degrees cooler than on the surrounding streets.
The rippling 280-meter (919 feet) wave of steel-and-aluminum runs the length of the Norman Foster-designed complex, funneling prevailing winds over outdoor patrons of restaurants and bars and saving on air conditioning for the mixed-use complex. The canopy is covered with solar panels and catches rainwater to irrigate the gardens.
Offices and apartment blocks designed to be green are springing up all over the world as architects reverse almost a century of trying to insulate workers from nature and instead try to adapt structures to their natural surroundings. The change is being driven by stricter building codes, a desire to cut energy costs and, in particular, demands from corporations and startups that need to show shareholders and customers they are meeting environmental standards.
Reprinted courtesy of
Andrew Janes, Bloomberg and
Shawna Kwan, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
End of an Era: Los Angeles County Superior Court Closes the Personal Injury Hub
October 24, 2022 —
Elizabeth A. Evans & Angela S. Haskins - Haight Brown & Bonesteel LLPOn September 21, 2022, the Los Angeles County Superior Court announced that it would start a gradual shutdown of the Personal Injury Hub, currently located at the Spring Street Courthouse. This closure will see the return of personal injury cases being venued in the district where they occurred.
The Personal Injury Hub was established in 2012 as a means of consolidating personal injury cases after several civil courtrooms around the County were closed due to significant budget cuts. It first began as two courtrooms in Stanley Mosk Superior Court, then moved to the Spring Street Courthouse and ballooned to six courtrooms, each handling a case load of reportedly over 9,000 cases at times. Case Management Conferences were abolished and the parties were largely left to their own devices to move cases along. At times, slow chaos ensued. With a new and increased budget, Los Angeles Superior Court has now decided that enough is enough.
Effective October 10, 2022, new personal injury cases will be filed and handled from start to finish in independent calendar courtrooms in the districts where the events giving rise to the claims occurred. Any cases properly filed in the Central District will continue to be heard in the Personal Injury Hub for now. A new Civil Case Cover Sheet Addendum that reflects this change will be available on the Los Angeles County Superior Court website for use as of October 10th.
Reprinted courtesy of
Elizabeth A. Evans, Haight Brown & Bonesteel LLP and
Angela S. Haskins, Haight Brown & Bonesteel LLP
Ms. Evans may be contacted at eevans@hbblaw.com
Ms. Haskins may be contacted at ahaskins@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Berger: FIGG Is Slow To Hand Over All Bridge Collapse Data
November 12, 2019 —
Richard Korman - Engineering News-RecordThe Florida International University Tragedy
About half an hour before the almost-completed pedestrian bridge collapsed onto a busy Miami-area road last year, killing six people, Denney Pate, the bridge’s engineer-of-record, sent a text to Linda Figg, the chief executive of FIGG Bridge Engineers.
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of