Hawaii Supreme Court Tackles "Other Insurance" Issues
February 25, 2014 —
Tred Eyerly – Insurance Law HawaiiResponding to four certified questions from the Ninth Circuit, the Hawaii Supreme Court addressed various issues raised by competing "other insurance" provisions in two CGL policies. Nautilus Ins. Co. v. Lexington Ins. Co., 2014 Haw. LEXIS 59 (Haw. Feb. 13, 2014).
Coverage for a development on Maui was at issue. The developer, VP & PK (ML) LLC, was insured by Lexington. The other insurance provision in Lexington's policy provided it was excess over "any other primary insurance available to you covering liability for damages arising out of the premises . . . for which you have been added as an additional insured."
Kila Kila Construction was one of VP & PK's subcontractors. Kika Kila was not an additional insured under Lexington's policy. Kila Kila had its own CGL policy with Nautilus. The Nautilus other insurance clause stated the insurance was excess over "any other primary insurance available to you covering liability arising out of the premises or operations for which you ahve been added as an additional insured." An endorsement added VP & PK as an additional insured, but only for liability arising out of Kila Kila's negligence.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
California Supreme Court Finds that When it Comes to Intentional Interference Claims, Public Works Projects are Just Different, Special Even
April 20, 2017 —
Garret Murai - California Construction Law BlogEarlier, we reported on a California Court of Appeals decision – Roy Allan Slurry Seal, Inc. v. American Asphalt South, Inc. – which held for the first time that a second-place bidder on a public works contract could sue a winning bidder who failed to pay its workers prevailing wages, under the business tort of intentional interference with prospective economic advantage.
Fast forward nearly two years, several amicus briefs, and “one doghouse”* later and the California Supreme Court has . . . reversed.
The Roy Allan Slurry Seal Case
To catch you up, or rather, refresh your recollection . . .
Between 2009 and 2012, American Asphalt South, Inc. was awarded 23 public works contracts totaling more than $14.6 million throughout Los Angeles, Orange, San Bernardino and San Diego counties. Two of the losing bidders on those projects – Roy Allan Slurry Seal, Inc. and Doug Martin Contracting, Inc. – sued American in each of these counties for intentional interference with prospective economic advantage as well as under the Unfair Practices Act (“UPA”) (Bus. & Prof. Code §§ 17000 et seq.) and the Unfair Competition Law (“UCL”) (Bus. & Prof. Code §17200).
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Increasing Use of Construction Job Cameras
January 27, 2014 —
Beverley BevenFlorez-CDJ STAFFJob site cameras are increasingly used on construction sites, for various reasons, reports Tom Sawyer of Engineering News-Record. Mark Penny, senior vice president of the Dallas Region Manhattan Construction Inc., told Sawyer that he uses the camera primarily for marketing purposes: “We have a lot of high-profile jobs that people want to see. They are a great opportunity for us and the client to showcase the construction, which makes the job of selling what we do a lot easier.”
Warren Andres, senior vice president at Andres Construction uses cameras for safety monitoring. Andres told Sawyer that “he has three monitors on his desk. One shows live feeds from all his cameras. If he sees unsafe work, he sends a photo to the superintendent and demands action. Similarly, he says he can spot slow work crews and do enough quality control to send the message that management is watching.”
Vendors commented to Sawyer that “the growing use [of cameras] include the rise of building information modeling and its increased need for accountability; as well as companies chasing work beyond usual areas of operations and needing to extend supervision while holding down travel of staffs trimmed by the recession.”
Read the court decisionRead the full story...Reprinted courtesy of
Dangerous Condition, Dangerous Precedent: California Supreme Court Expands Scope of Dangerous Condition Liability Involving Third Party Negligent/Criminal Conduct
August 19, 2015 —
R. Bryan Martin, Laura C. Williams, & Lawrence S. Zucker II – Haight Brown & Bonesteel LLPIn Cordova v. City of Los Angeles (filed 8/13/15, Case No. S208130), the California Supreme Court held a government entity is not categorically immune from liability where the plaintiff alleges a dangerous condition of public property caused the plaintiff’s injury, but did not cause the third party conduct which precipitated the accident.
The case arises out of a traffic collision by which the negligent driving of a third party motorist caused another car to careen into a tree planted in the center median owned and maintained by the City of Los Angeles (“City”). Of the four occupants in the car that collided with the tree, three died and the fourth was badly injured. The parents of two of the occupants sued the City for a dangerous condition of public property under Government Code Section 835. The plaintiffs alleged the roadway was in a dangerous condition because the trees in the median were too close to the traveling portion of the road, posing an unreasonable risk of harm to motorists who might lose control of their vehicles.
The City successfully moved for summary judgment, which plaintiffs appealed. On review, the Court of Appeal affirmed holding the tree was not a dangerous condition as a matter of law because there was no evidence that the tree had contributed to the criminally negligent driving of the third party motorist.
Reprinted courtesy of Haight Brown & Bonesteel LLP attorneys
R. Bryan Martin,
Laura C. Williams and
Lawrence S. Zucker II
Mr. Martin may be contacted at bmartin@hbblaw.com
Ms. Williams may be contacted at lwilliams@hbblaw.com
And Mr. Zucker may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Failure to Allege Property Damage Within Policy Period Defeats Insured's Claim
October 03, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe insured's inability to determine when water damage occurred meant it could not pursue claims of property damage against the insurers. Creek v. State Farm Fire & Cas. Co., 2022 U.S. Dist. LEXIS 116939 (W.D. Wash. July 1, 2022).
Gold Creek Condominium complex experienced water damage. The complex was completed in 1982. The owners sued State Farm and Travelers under all-risk policies when tenders for the damage were denied.
In 2017, Creek hired an expert to investigate deterioration due to water intrusion. The expert noted that "water intrusion had been evident in the exterior walls, soffits, terraces, handrails and elevated entry walkways for some time." Thereafter, Creek tendered claims for property damage to State Farm and to Travelers.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Coverage Denied Where Occurrence Takes Place Outside Coverage Territory
December 11, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe court held there was no coverage for construction defect claims that occurred outside the coverage territory. Foremost Signature Ins. Co. v. Silverboys, 2018 U.S. Dist. LEXIS 154524 (S.D. Fla. Sept. 11, 2018).
Solo Design, LLC, a Miami-based design company, entered into a contract with Silverboys, LLC (Owner) to provide interior design services in conjunction with the renovation of the Owner's vacation home in the Bahamas. Solo retained Whittingham, a Bahamian architect, as a subcontractor to serve as project manager.
Owner sued Solo, Whittingham and others in Florida for breach of contract, fraud, conversion and negligence when the project did not go as planned. The underlying complaint alleged intentional misconduct, lying about qualifications and the progress of the project, submitting false invoices, requesting money for services that were not performed, etc. Owner alleged that the damages included: (a) the cost to repair substandard work; (b) loss of use of the home due to delay; and (c) overcharges for furnishings, contract fees, and expenses. The underlying complaint set forth only a few instances of physical injury to the home, including mold on the ceiling in the master shower, faulty millwork on the children's playroom bookshelf, and a defective front door and resysta facade.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Design and Construction Defects Not a Breach of Contract
February 14, 2013 —
CDJ STAFFThe California Court of Appeals tossed out a breach of contract award in Altman v. John Mourier Construction. The decision, which was issued on January 10, 2013, sent the construction defect case back to a lower court to calculate damages based on the conclusions of the appeals court.
The case involved both design issues and construction issues. According to the plaintiffs’ expert, the design plans did not make the buildings sufficiently stiff to resist the wind, and that the framing was improperly constructed, further weakening the structures, and leading to the stucco cracking. Additionally, it was alleged that the roofs were improperly installed, leading to water intrusion. The contractor’s expert “agreed the roofs needed repair, but disputed what needed to be done to repair the roofs and the cost.”
The jury rejected the plaintiffs’ claims of product liability and breach of warranty, but found in their favor on the claims of breach of contract and negligence. The plaintiffs were awarded differing amounts based on the jury’s conclusions about their particular properties.
Both sides sought new trials. JMC, the contractor, claimed that the jury’s verdicts were “inconsistent in that the relieved JMC of liability for strict products liability and breach of warranty, but found JMC liable for breach of contract and negligence.” The plaintiffs “opposed the setoff motion on the ground that the jury heard evidence only of damages not covered by the settlements.” Both motions were denied. After this, the plaintiffs sought and received investigative costs as damages. JMC appealed this amended judgment.
The appeals court rejected JMC’s claims that evidence was improperly excluded. JMC sought to introduce evidence concerning errors made by the stucco subcontractor. Earlier in the trial, JMC had insisted that the plaintiffs not be allowed to present evidence concerning the stucco, as that had been separately settled. When they wished to introduce it themselves, they noted that the settlement only precluded the plaintiffs from introducing stucco evidence, but the trial court did not find this persuasive, and the appeals court upheld the actions of the trial court. Nor did the appeals court find grounds for reversal based on claims that the jury saw excluded evidence, as JMC did not establish that the evidence went into the jury room. Further, this did not reach, according to the court, a “miscarriage of justice.”
The court rejected two more of JMC’s arguments, concluding that the negligence award did not violate the economic loss rule. The court also noted that JMC failed to prove its contention that the plaintiffs were awarded damages for items that were covered in settlements with the subcontractors.
The appeals court did accept JMC’s argument that the award for breach of contract was not supported by evidence. As the ruling notes, “plaintiffs did not submit the contracts into evidence or justify their absence; nor did plaintiffs provide any evidence regarding contract terms allegedly breached.”
The court also did not allow the plaintiffs to claim the full amount of the investigative costs. Noting that the trial court had rational grounds for its decision, the appeals court noted that “the jury rejected most of the damages claimed by plaintiffs, and the trial court found that more than $86,000 of the costs itemized in plaintiffs’ invoices ‘appear questionable’ as ‘investigation’ costs/damages and appeared to the trial court to be litigation costs nonrecoverable under section 1033.5.”
Read the court decisionRead the full story...Reprinted courtesy of
Dispute Over Exhaustion of Primary Policy
May 20, 2015 —
Tred R. Eyerly – Insurance Law HawaiiIn a dispute between the excess and primary carriers, the Fifth Circuit determined the primary policy was exhausted, triggering coverage under the excess policy. Amerisure Mut. Ins. Co. v. Arch Spec. Ins. Co., 2015 U.S. App. LEXIS 6627 (5th Cir. April 21, 2015).
Amerisure issued a CGL policy to Admiral Glass & Mirror Co. The policy provided excess over any coverage under a controlled insurance program policy. Arch issued an Owner Controlled Insurance Program (OCIP) policy to Endeavor Highrise, LP and to its contrators and subcontractors for bodily injury and property damage arising out of the construction of the Endeavor Highrise. Admiral was a subcontractor insured under the OCIP.
The OCIP had combined bodily injury and property damage limits of $2,000,000 per occurrence, a general aggregate limit of $2,000,000 and a products-completed operations aggregate limit of $2,000,000. The OCIP contained a Supplementary Payments provision which provided that Arch would pay "[a]ll expenses we incur" in connection with any covered claim, and that "[t]hese payments will not reduce the limits of insurance." Endorsement 16, however, expressly deleted and replaced this statement with: "[supplementary payments] will reduce the limits of insurance." The OCIP also provided that Arch's duty to defend ended "when we have used up the applicable limit of insurance in the payment of judgments or settlements."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com