Even Where Fraud and Contract Mix, Be Careful With Timing
April 12, 2021 —
Christopher G. Hill - Construction Law MusingsI have often discussed the limited circumstances under which a construction contract claim and a fraud claim can coexist. A recent case from the Western District of Virginia federal court demonstrates that care is necessary even in those limited circumstances.
In Fluor Fed. Sols., LLC v. Bae Sys. Ordinance Sys., the Court examined the question of a fraud statute of limitations under Virginia law. The basic facts found in the Complaint are these:
In 2011, the United States Army awarded BAE Systems Ordinance Systems Inc. a basic ordering agreement under which BAE was responsible for modernization projects at the Radford Army Ammunition Plant. This action stems from a subcontract between Fluor Federal Solutions LLC and BAE, under which Fluor agreed to design and construct a new natural gas boiler at the plant. Fluor has completed work on the project, and BAE has accepted that work. Nonetheless, Fluor claims that BAE has refused or failed to pay for the balance of the project costs. Fluor alleges that BAE received several changes to its prime contract from the Army but did not pass those changes along to Fluor until after BAE solicited a bid from Fluor and entered a contract with Fluor to build a temporary facility. Instead, BAE continued to misrepresent the scope of the project. Fluor alleges that the change in plans increased costs substantially, but that BAE withheld information about those changes so that it could solicit lower bids. Fluor alleges that it requested a copy of BAE’s prime contract on numerous occasions, but BAE failed to provide a copy of it. Instead, Fluor submitted a request under the Freedom of Information Act. It received a copy of BAE’s prime contract on Oct. 3, 2018.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Home Construction Thriving in Lubbock
December 30, 2013 —
CDJ STAFFThe 2013 numbers for home construction aren’t ready yet, but the January through November numbers for Lubbock, Texas show a 42% increase over the number of construction permits issued for single-family homes in the first 11 months of 2012. The number look even better compared to 2011’s totals, according to KFYO.
Read the court decisionRead the full story...Reprinted courtesy of
The Evolution of Construction Defect Trends at West Coast Casualty Seminar
May 24, 2018 —
Don MacGregor – Bert L. Howe & Associates, Inc.Twenty-five years ago. 1993. On January 23rd, Bill Clinton was sworn in as the 42nd President of the United States. The average cost of a gallon of gasoline was $1.16, a movie ticket cost $4.00, and the average cost of a new home was $113,200.00.
1993 also marked the first of what would be a quarter century of annual seminars hosted by West Coast Casualty Service, and provided to the combined professionals within the Construction Defect Community. As the seminar has grown both in attendance and prominence within this community under the watchful stewardship of David and Coral Stern, much has changed both with regard to the content of the seminar and the climate within which it was presented. A quick look at the topics addressed over the past 25 years of the Construction Defect Seminar provides one with a veritable history of construction defect litigation and insurance coverage trends across the United States and beyond.
While the first seminar was hosted in 1993, my first attendance didn’t occur until 1999, and the first time I was honored to be a panelist would have to wait until 2007. In the subsequent years, I’ve had the opportunity to sit on panels an additional three times, and each one I gained rare and valuable insights into the Construction Defect Community, its willingness to challenge itself, and the amazing professionals we all have the distinct pleasure of working with every day (and whom we sometimes take too much for granted).
In the mid to late 90’s, topics at the seminar included such subjects as the Montrose Chemical Corp v. Superior Court decision (Montrose) regarding a carrier’s duty to defend and the subsequent Stonewall Insurance case that examined the duty to indemnify in the context of construction defect claims. The California Calderon Act of 1997, laying out the roadmap for HOA’s filing construction defect lawsuits was also a topic of discussion and debate within the West Coast “arena.”
The new millennium saw the landmark Aas v. William Lyon decision, which disallowed negligence claims for construction defects in the absence of actual resultant damage. This was followed by Presley Homes v. American States Insurance wherein the court ruled that a duty to defend applies where there is mere potential for coverage and the duty to defend applies to the entire action. Each of these bellwether decisions was addressed contemporaneously by panels at the West Coast seminar, contemporaneously bringing additional dialog to the CD community, from within the community.
2002 brought what has become the defining legislation in California regarding construction defect litigation and a builder’s right to repair. Senate Bill 800 (SB800), and its subsequent codification as Title 7, Part 2 of Division 2 of the California Civil Code, Sections 895 through 945.5 would become the defining framework for similar legislation across the United States. During the course of its drafting, movement through the legislature, and final adoption in January of 1993, many of the questions raised and debated in committees in Sacramento, had already been and were continuing to be addressed by panelists at the West Coast Seminar. How does SB800 work with Calderon? How does it affect the prior Aas decision? What now constitutes a defect, and what are timeframes established within the complex pre-litigation process? Open the pages of the 2002 – 2004 Seminar invitations and you’ll see panels comprised of the finest members of the insurance law and coverage communities addressing those very questions (and more)!
As the first decade of the new century drew to a close, a brief review of the WCC invitations from that period suggests a trend towards programmatic analyses of key themes selected for the seminar. In 2008, my second opportunity as a guest speaker, topics included a review of the state of construction defect litigation in a post-SB 800 environment. Panelists offered retrospective insight into the state of right to repair statutes in multiple states, while others offered a glimpse at where the industry might be headed, as similar legislation was enacted across the country. As always, pertinent court decisions bearing on construction defect, both in California, and elsewhere were given unique perspective and additional clarity by multiple panels of gifted speakers. In 2009, claims and coverage were examined from multiple unique perspectives, including that of plaintiff, the policyholder, and the insurer. Wrap policies and the gaps in due to self-insured retention obligations were examined.
As we rapidly approach the end of the second decade of the 21st Century, West Coast Casualty’s Construction Defect Seminar continues to lead the Construction Defect Community as the premier source for information and peer dialog on all matters relating to construction law, coverage, and emerging trends. In 2017, the Seminar tackled such broad subjects as the role of women in the construction industry, claims management, and risk management, challenges raised by wrap versus non-wrap litigation, and the emergent trend of apartment to condo conversions (and the attendant coverage challenges).
On May 16th at the Disneyland Resort, in Anaheim California, America’s largest Construction Defect event kicked off its 25th Anniversary celebration. As has been every year since 1993, the Seminar provided insurance, legal, and industry professionals an exciting and informative array of salient and timely panel topics, as well as a stellar faculty of gifted panelists. This year’s West Coast Casualty’s Construction Defect Seminar, like the past 25 years, was not only informative and educational, but also a promise for another 25 years of peerless service to the Construction Defect Community.
Read the court decisionRead the full story...Reprinted courtesy of
Florida's New Pre-Suit Notification Requirement: Retroactive or Prospective Application?
February 05, 2024 —
Holly A. Rice - Saxe Doernberger & Vita, P.C.Florida’s newly formed Sixth District Court of Appeal (“Sixth DCA”) recently certified conflict with Florida’s Fourth District Court of Appeal on the issue of retroactive application of the pre-suit notice requirement contained in Florida Statute §627.70152.1 Earlier this year, the Fourth District Court of Appeal (“Fourth DCA”) held that the pre-suit notice provision applies retroactively, meaning, it applies to all suits filed after July 1, 2021, regardless when the insurance policy was issued.2 The Sixth DCA, in
Hughes v. Universal Property & Casualty Insurance Company,3 directly rejected the Fourth DCA’s interpretation and instead found a retroactive application of the pre-suit notice to be unconstitutional under Florida law. Prior to the Fourth DCA’s ruling, most trial courts had found no retroactive application for the pre-suit notice provision.4
In August 2021, shortly after Florida Statutes Section 627.70152 went into effect on July 1, 2021, Rebecca Hughes (“Hughes”) sued Universal Property & Casualty Insurance Company (“Universal Property”) for breach of contract after Universal Property denied her insurance claim. Hughes did not file a pre-suit notice under Section 627.70152. Universal Property moved to dismiss based on Hughes’ failure to file the pre-suit notice, arguing that the pre-suit notice requirement applies to all lawsuits filed after July 1, 2021, even if the claimant’s insurance policy was issued before the statute’s effective date. The trial court agreed with Universal Property and dismissed the lawsuit.
Read the court decisionRead the full story...Reprinted courtesy of
Holly A. Rice, Saxe Doernberger & Vita, P.C.Ms. Rice may be contacted at
HRice@sdvlaw.com
Rainwater Collecting on Rooftop is not Subject to Policy's Flood Sublimits
October 15, 2024 —
Tred R. Eyerly - Insurance Law HawaiiResponding to a certified question from the First Circuit, the Supreme Judicial Court of Massachusetts determined that rainwater collecting on the insureds' rooftop and causing interior damage was not "flood" as defined in the policy and subject to sublimits. Zurich Am. Ins. Co. v. Medical Properties Trust, Inc., 2024 Mass. LEXIS ___ (Mass. July 23, 2024).
A severe thunderstorm caused heavy rain and strong winds which damaged a hospital. The hospital was owned by Medical Properties Trust, Inc. (MPT) and leased to Steward Health Care System LLC (Steward). Ground water accumulated and flooded the basement. Rainwater also accumulated on the hospital's parapet roofs and on the second-story courtyard, and eventually seeped through the parapet roofs and courtyard to the hospital's upper floors, causing damage to the building and property within.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Constructive Suspension (Suspension Outside of an Express Order)
December 13, 2022 —
David Adelstein - Florida Construction Legal UpdatesIn the federal procurement arena, there is a concept known as “constructive suspension.” Constructive suspension, while known in the federal arena, should reasonably apply to all projects when work is stopped outside of an express order to stop the work based on the law below. An unreasonable suspension is an unreasonable suspension and an express order to stop the work does not negate the effects of what really amounts to a suspension.
“Constructive suspension occurs when work is stopped absent an express order by the contracting officer and the government is found to be responsible for the work stoppage.” P.R. Burke Corp. v. U.S., 277 F.3d 1346, 1359 (Fed. Cir. 2002). The government delay must be unreasonable to support a constructive acceleration claim. Id.
“To demonstrate such a constructive suspension of work, the contractor must show that the delay (1) was for an ‘unreasonable length of time,’ (2) was proximately caused by the government’s actions, and (3) resulted in some injury to the contractor.” Fireman’s Fund Ins. Co. v. U.S., 2001 WL 36415627, *6 (Fed.Cl. 2001) (citation omitted). “Relative to proving that the delay was directly caused by the government, the contractor must concomitantly show that it was not delayed by any concurrent cause that would have independently generated the delay during the same time period even if it does not predominate over the government’s action as the cause of the delay.” Beauchamp Const. Co. v. U.S., 14 Cl.Ct. 430, 437 (Cl.Ct. 1988).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
New Jersey Courts Sign "Death Knell" for 1979 Weedo Decision
October 21, 2015 —
Jesse Howard Witt – Acerbic WittA new
blog post from Kilpatrick Townsend & Stockton discusses two recent decisions limiting the holding of Weedo v. Stone-E-Brick, Inc., 405 A.2d 788 (N.J. 1979), a New Jersey case that has generated decades of commentary and debate, in
my own writing as well as that of many others (at least 1880 citations, according to the blog).
Read the court decisionRead the full story...Reprinted courtesy of
Jesse Howard Witt, Acerbic WittMr. Witt welcomes comments at www.wittlawfirm.net
Miorelli Doctrine’s Sovereign Immunity in Public Construction Contracts — Not the Be-All and End-All
March 21, 2022 —
David Adelstein - Florida Construction Legal UpdatesIn the Florida commercial contract public arena, there is a sovereign immunity doctrine known as the Miorelli doctrine after 1997 Florida Supreme Court decision, County of Brevard v. Miorelli Eng’g, Inc., 703 So.2d 1049 (Fla. 1997). This doctrine would apply to construction contracts between a contractor and a public body.
Through the years, the Miorelli doctrine stands for the proposition in commercial transactions with a Florida public body “that the doctrine of sovereign immunity precludes recovery of the cost of extra work where claims for that extra work are ‘totally outside’ the terms of the contract.” Monroe County v. Ashbritt, Inc., 47 Fla.L.Weekly D594a (Fla. 3d DCA 2022). See also Asbritt, n.2 quoting Posen Construction v. Lee County, 921 F.Supp.2d 1350, 1356 (M.D.Fla. 2013) (“A claim for damages predicated on work ‘totally outside the terms of the contract‘ is barred by the doctrine of sovereign immunity, whereas damages caused by extra work done at the state’s behest and in furtherance of the contractual covenants (express or implied) are potentially recoverable.”)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com