Colorado Homebuyers Must be in Privity of Contract with Developer to Assert Breach of Implied Warranty of Suitability
May 03, 2017 —
Maggie Stewart - Colorado Construction Litigation On April 17, 2017, the Colorado Supreme Court announced its decision in Forest City v. Rogers, No. 15SC1089, 2017 CO 23 (Colo. Apr. 17, 2017). The Court held that privity of contract is necessary for a homebuyer to assert a claim for breach of implied warranty of suitability against a developer. In other words, one must be a party to a contract to pursue a claim for breach of any implied warranty of suitability therein.
Defendant Forest City was the developer of a mixed use property in Stapleton. Forest City subdivided the land and sold the vacant lot at issue to a professional builder, Infinity. Infinity then built a residence and sold it to the plaintiff, Tad Rogers. After moving into the home, Rogers came to believe that the water table beneath the house along with calcite leaching from the road material led to a buildup of calcite in the foundation drain, making the basement uninhabitable and causing the sump pump to work overtime. Rogers sued Forest City on various theories, including breach of the warranty of suitability. In particular, Rogers alleged that Forest City impliedly warranted to him that his lot was suitable for a home with a finished basement, when in fact it was not. He prevailed on this claim at the trial court level.
Read the court decisionRead the full story...Reprinted courtesy of
Maggie Stewart, Higgins, Hopkins, McLain & Roswell, LLCMs. Stewart may be contacted at
stewart@hhmrlaw.com
Seattle Expands Bridge Bioswale Projects
May 11, 2020 —
Jim Parsons - Engineering News-RecordThe success of engineered systems to capture stormwater runoff from Seattle’s Aurora Avenue Bridge has spurred construction of additional measures that proponents say will increase total filtering capacity by another two million gallons per year.
Jim Parsons, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
“Bound by the Bond”
September 02, 2024 —
Daniel Lund III - LexologyA New York trial court granted judgment in favor of a performance bond surety on a construction project, based upon the failure of the claiming party to abide by the terms of the bond.
The “AIA Document A312” bond form – described by the court (quoting surety law authority) to be “one of the clearest, most definitive, and widely used type of traditional common law ‘performance bonds’ in private construction” – contains various procedures which must be honored as a “condition precedent to an action to recover” on the bond/against the surety. One of those prerequisites is a “declaration of default” concerning the contractor principal (here, a subcontractor).
The case involved the construction of an 85-story skyscraper in midtown Manhattan, and the performance of the subcontract for the building’s superstructure. The bonded contract was at a value of approximately $25,000,000 and obligated the sub to provide a performance bond “in a form similar to the [A312 bond],” and which was otherwise satisfactory to the obligee/construction manager.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
In Colorado, Repair Vendors Can Bring First-Party Bad Faith Actions For Amounts Owed From an Insurer
December 20, 2012 —
BRADY IANDIORIO, HIGGINS, HOPKINS, MCLAIN & ROSWELLWith the aftermath of Sandy still being felt up and down the Eastern seaboard, the question of many victims turns to how they can rebuild their lives and homes. One of the first things many people do is call on their insurance carriers to help rebuild whatever damaged property they have. In a recent case here in Colorado, those rebuilding efforts got reaffirmed by a Court of Appeals case, Kyle W. Larson Enterprises, Inc., Roofing Experts, d/b/a The Roofing Experts v. Allstate Insurance Company, --- P.3d ----, 2012 WL 4459112 (Colo. App. September 27, 2012).
The facts of the case are pretty straightforward and could describe many repair vendors in numerous situations. Roofing Experts contracted with four homeowners insured by Allstate to repair their damaged roofs. The contracts provided that repair costs would be paid from insurance proceeds. The contracts also allowed Roofing Experts full authority to communicate with Allstate regarding all aspects of the insurance claims. Before work began, Roofing Experts met with adjusters from Allstate to discuss the four homes and the amount of each claim. After receiving approval for the claims, Roofing Experts began the repairs. During construction, Roofing Experts discovered additional repairs were necessary to maintain certain manufacturer’s warranties and to conform to applicable building codes.
Read the court decisionRead the full story...Reprinted courtesy of
Brady Iandorio, Higgins, Hopkins, McLain & Roswell, LLCMr. Iandorio can be contacted at
iandiorio@hhmrlaw.com
But Wait There’s More: Preserving Claims on Commonwealth Projects
February 07, 2018 —
Wally Zimolong - Supplemental Conditions BlogOn construction projects owned by the Commonwealth of Pennsylvania, a contractor may make a claim with the Board of Claims. But first, you must be aware of two limitations periods that could cause you to waive your claim if they are not met.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Caltrans to Speak before California Senate regarding Bay Bridge Expansion
August 06, 2014 —
Beverley BevenFlorez-CDJ STAFFThe San Francisco Chronicle reported that at an upcoming California Senate hearing, Caltrans is expected to defend itself against “allegations that they ‘gagged and banished’ engineers who identified construction problems on the new Bay Bridge eastern span and that the agency failed to maintain basic quality control on the project.”
Members of the “Senate Transportation and Housing Committee will question Caltrans Director Malcolm Dougherty, other state officials and the head of the bridge's lead contractor, American Bridge/Fluor, about two reports last week from an investigator and a panel of six engineers who were critical of how the $6.4 billion project was managed.”
Read the court decisionRead the full story...Reprinted courtesy of
Badly Constructed Masonry Walls Not an Occurrence in Arkansas Law
May 10, 2012 —
CDJ STAFFThe US District Court for Maryland has granted a summary judgment in the case Konover Construction Corp. v. ATC Associates to Massachusetts Bay Insurance Company and denied a request for dismissal from ACT. Konover (KBE) was contracted by Wal-Mart to build a Wal-Mart store and a Sam’s Club in Port Covington, Maryland. Superus, Inc. was hired by KBE to build the masonry walls. Superus purchased a policy from Massachusetts Bay Insurance which named KBE as an additional insured. Wal-Mart hired ATC Associates to independently test and inspect the concrete structural steel, and masonry.
After the building was in use, a large crack appeared which was attributed a latent construction defect. Other cracks were discovered. Upon investigation, it was discovered that there were “voids or foam in the concrete block surrounding the reinforcing steel that should have been filled with grout,” and in some cases, “reinforcing steel was missing or not installed in accordance with the specifications.” KBE paid for the repair and remediation and Wal-Mart assigned all rights and interests against ATC to KBE.
KBE filed suit against ATC. ATC called for dismissal on the grounds that Wal-Mart had no claims as the problems had been remediated. Wal-Mart then provided KBE with additional agreements to give them enforceable rights against ATC and Superus. KBE filed a fourteen claims against ATC, Superus, and Massachusetts Bay. In the current case, Massachusetts Bay sought summary judgment and ATC sought dismissal of all claims against it.
Massachusetts Bay claims that they need not indemnify Superus, as “there is no evidence adequate to establish that Superus’ defective work caused any collateral and/or resulting damage that was not subject to an Impaired Property exclusion, and that, in any event, no damage occurred during the policy period.”
As Wal-Mart is headquarted in Arkansas, certain contracts were under Arkansas law. Under the Arkansas courts, “defective workmanship, standing alone and resulting in damages only to the work product itself, is not an ‘occurrence.’” The court determined that collateral or resultant damage would be covered. The court found that “it is clear under Arkansas law, and the parties appear to agree, that Massachusetts Bay is not obligated to indemnify KBE for any repairs to the masonry walls themselves, including any cracks or gaps in the walls.” The court also found that “there is no evidence adequate to prove that any allegedly resultant property damage was caused by Superus’ faulty construction of the walls.” The court also noted that “if the building code violation and structural integrity problem were ‘property damage,’ insurance coverage would be barred by the Impaired Property Exclusion.” Based on these findings, the court concluded that Massachusetts Bay is entitled to summary judgment.
While the court dismissed the case against Massachusetts Bay, the court declined ATC’s motion to dismiss. The court noted that ACT’s alleged negligence in conducting inspections “created only a risk of economic loss for KBE.” Although hired by Wal-Mart, ATC “transmitted its daily testing and inspection reports of the Wal-Mart and Sam’s Club projects directly to KBE.” The court found that “KBE has made a plausible claim.”
ATC also claimed that KBE contributed to the negligence due to the negligence of its subcontractor. The court concluded that it was plausible that “ATC will not be able to carry its burden of proving KBE was contributorily negligent.” The court was less sanguine about KBE’s fraud claim, but though it “may not now appear likely to have merit, it is above the ‘plausibility’ line.”
In conclusion, KBE may not continue its case against Massachusetts Bay. However, the judge allowed the other proceedings to continue.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Court Finds That SIR Requirements are Not Incorporated into High Level Excess Policies and That Excess Insurers’ Payment of Defense Costs is Not Conditioned on Actual Liability
April 22, 2019 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Deere & Co. v. Allstate Ins. Co. (No. A145170, filed 2/25/19), a California appeals court held that the insured was not required to pay additional self-insured retentions (SIRs) in order to trigger higher level excess coverage because the retained limits applicable to the first layer of coverage did not also apply to the higher-layer excess policies.
In Deere, the insured was sued for injuries from alleged exposure to asbestos-containing assemblies used in Deere machines. In a declaratory relief action against its umbrella and excess insurers, the case was tried on: (1) whether the higher-layer excess policies were triggered once the first-layer excess policy limits, which were subject to an SIR paid by Deere, had been exhausted; and (2) whether the insurers’ indemnity obligation extended to Deere’s defense costs incurred in asbestos claims that had been dismissed. The trial court found in favor of the insurers, concluding that the retained limits in the first layer of coverage also applied to the higher-layer excess, which was not triggered until Deere paid additional SIRs. The court also concluded that the insurers were not obligated to pay defense costs when underlying cases were dismissed without payment to a claimant either by judgment or settlement.
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP Read the court decisionRead the full story...Reprinted courtesy of