Utah Digs Deep and Finds “Design Defect” Includes Pre-Construction Geotechnical Reports
November 19, 2021 —
Kyle Rice - The Subrogation SpecialistThe Supreme Court of Utah recently found that an incorrect pre-construction geotechnical engineering report is a “defective design.” Thus, actions arising from an incorrect geotechnical report are appropriately governed by Utah’s Economic Loss Statute (Statute), Utah Code Ann. § 78B-4-513(1).
Hayes v. Intermountain GeoEnvironmental Servs. No. 20190764, 2021 UT 62, 2021 Utah Lexis 144, arose out of a suit filed by homeowners Kim and Nancy Hayes (the Hayeses). The Hayeses’ home was part of the Quail Hollow subdivision in Layton, Utah, which was developed by K.C. Halls Construction, Inc. (K.C. Halls). Prior to construction, K.C. Halls contracted with Intermountain GeoEnvironmental Services, Inc. (IGES) for a geotechnical report of the planned development to comply with the requirements of Layton City. The report found that “the subject site is suitable for the proposed construction” and made recommendations to ensure foundational integrity for future construction. The Hayeses ultimately purchased a lot from an agent for K.C. Halls and hired Bob Stevenson (Stevenson) to construct the home. About 14 months after the completion of construction, the Hayeses noticed cracking in their foundation walls.
Read the court decisionRead the full story...Reprinted courtesy of
Kyle Rice, White and WilliamsMr. Rice may be contacted at
ricek@whiteandwilliams.com
Best Practices: Commercial Lockouts in Arizona
April 15, 2024 —
Patrick Tighe - Snell & Wilmer Real Estate Litigation BlogIf a tenant defaults under a commercial lease, Arizona law permits the landlord to re-take possession of the premises by locking out the defaulting tenant. However, if the landlord’s lockout is wrongful, the landlord may be liable for the damages the tenant sustains because of the wrongful lockout. To minimize such liability, here are some general best practices to follow when locking out a defaulting tenant:
- Do Not Breach the Peace. It is vital when performing a lockout to not breach the peace. What constitutes a “breach of the peace” depends on the particular circumstances at hand. For example, if a tenant arrives during the lockout and becomes angry or threatens violence, the landlord should stop performing the lockout and return at a later time. As a general rule of thumb, it is best to perform lockouts in the early morning hours or in the late evening hours when the landlord is less likely to encounter the tenant.
- Provide A Notice of Default. Many commercial leases require the landlord to provide a notice of default before the landlord can lock out a defaulting tenant. Check, double check, and triple check that the landlord followed the lease’s notice of default provisions correctly, including that the landlord sent the notices to all required parties in accordance with the time requirements set forth in the lease.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick Tighe, Snell & WilmerMr. Tighe may be contacted at
ptighe@swlaw.com
California Enacts New Claims Resolution Process for Public Works Projects
January 19, 2017 —
Garret Murai – California Construction Law BlogIf you’re a public entity or contractor involved in public works construction you should be aware of a new law,
AB 626, which took effect on the first of this year and establishes a new mandatory claims resolution process for disputes on public works projects. Here’s what you need to know:
What is the new law and where is it codified at?
AB 626 added new Public Contract Code Section 9204 that according to the bill’s author, Assemblymember David Chiu of San Francisco, establishes “a claim resolution process applicable to any claim by a contractor in connection with a public works project.”
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Preparing Your Business For Internal Transition
October 14, 2019 —
Stephen P. Katz, Esq. - ConsensusDocsWhen is it right to start thinking about succession planning and preparing a construction company for transition? Many would agree – in concept, at least – that serious thought regarding succession and transition planning should begin at a company’s inception and be revisited throughout its lifecycle, but as a practical matter, it is frequently not part of the mindset when growing a business. This article explores issues that construction company owners should consider in order to achieve smooth transition of ownership and control. We will address three critical questions:
- What happens to the business when an owner retires;
- In the event an owner(s) become disabled; and,
- Unplanned exit/owner pre-deceases her/his exit from the company
Owners who do not plan carefully for transition are often faced with the less than appealing option of liquidating their business for much less than its value, or by closing the business with no return upon that event. However, those who plan carefully can realize the value of their life’s work, pass the business to the next generation and see their legacy continue.
Read the court decisionRead the full story...Reprinted courtesy of
Stephen P. Katz, Esq., Peckar & Abramson, P.C.Mr. Katz may be contacted at
skatz@pecklaw.com
Why You May Not Want a Mandatory Mediation Clause in Your Construction Contract
October 26, 2017 —
Christopher G. Hill - Construction Law MusingsI know, you are likely surprised by the title of this post. You’ve read Construction Law Musings for a while now and know that as a Virginia Supreme Court certified mediator, I have advocated mediation as a great way to resolve your construction disputes short of the expensive and time consuming litigation process. Knowing all of this, you as a reader of this blog (thanks by the way) probably wonder why I think that a mandatory mediation clause may not be the best thing for your construction contracts. I can understand your possible confusion (particularly
in light of this post from @sethsmiley).
Please don’t take the headline as my suddenly taking a new view of mediation. Short of simply resolving the dispute between the parties to the construction contract, mediation still remains number one on my list of construction dispute resolution mechanisms. I still believe that it is useful even when a resolution is not met after a good faith attempt by both sides to come to a business agreement. However, I also believe that mediation works best when entered into voluntarily by the parties.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Changes in the Law on Lien Waivers
November 16, 2020 —
Alan Paulk - Autry, Hall & Cook, LLPAmong many things to look forward to in 2021, we can add a new lien law to the list. Effective January 1, 2021, Georgia’s Lien Statute will be modified so that lien waivers and releases are limited to “waivers and releases of lien and labor or material bond rights and shall not be deemed to affect any other rights or remedies of the claimant.” O.C.G.A. 44-14-366(a). This would mean that lien waivers only waive lien or bond rights and do not waive contractual rights to collect payment.
The new law is in reaction to a decision from the Georgia Court of Appeals in ALA Constr. Servs., LLC v. Controlled Access, Inc., 351 Ga. App. 841 (2019). In that case, a contractor signed an interim lien waiver at the time it submitted an invoice. The contractor did not receive payment, and it failed to timely record an affidavit of non-payment or a claim of lien. Subsequently, the contractor filed suit for breach of contract. The Georgia Court of Appeals held that the statutory form lien waiver was binding against the parties “for all purposes” and not just the purpose of preserving the right to file a lien. By such sweeping logic, the contractor’s breach of contract claim was denied.
Read the court decisionRead the full story...Reprinted courtesy of
Alan Paulk, Autry, Hall & Cook, LLPMr. Paulk may be contacted at
paulk@ahclaw.com
New Jersey’s Governor Puts Construction Firms on Formal Notice of His Focus on Misclassification of Workers as Independent Contractors
May 24, 2018 —
Kevin J. O'Connor & Joseph M. Vento - Peckar & Abramson, P.C.We have written quite a bit about the mounting threat to employers, both nationally and locally, of claims of misclassification of workers as independent contractors rather than employees. New Jersey’s new Gov. Phil Murphy signed an executive order last week that establishes a task force on employee misclassification to punish contractors who commit fraud by classifying their employees as independent contractors.
In the words of Governor Murphy: “I am signing this order to crack down on unscrupulous contractors who commit 1099 fraud to exploit workers and rob them of family and medical leave and safe workplace protections that the law provides,” Murphy said. “The employer gives themselves an unfair business advantage and this practice is illegal. This is a question of enforcing what is already on the books.” He has vowed that any employer caught misclassifying workers will either be brought into compliance or put out of business. The task force will foster compliance with the law and conduct a comprehensive review of existing practices.
Reprinted courtesy of
Kevin J. O'Connor, Peckar & Abramson, P.C. and
Joseph M. Vento, Peckar & Abramson, P.C.
Mr. O'Connor may be contacted at koconnor@pecklaw.com
Mr. Vento may be contacted at jvento@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Inability to Confirm Coverage Supports Setting Aside Insured’s Default Judgment on Grounds of Extrinsic Mistake
January 21, 2019 —
Christopher Kendrick & Valerie A. Moore - Haight Brown & Bonesteel LLPIn Mechling v. Asbestos Defendants (No. A150132, filed 12/11/18), a California appeals court affirmed the trial court’s grant of an insurer’s motion to set aside default judgments entered against its defunct insured pursuant to the trial court’s inherent, equitable power to set aside defaults on the ground of extrinsic mistake, thereby allowing the insurer to intervene and defend its own interests in the case.
In Mechling, Fireman’s Fund insured Associated Insulation of California, which was named as a defendant in asbestos litigation filed in 2009. Associated had ceased operating in 1974, but was somehow successfully served with the complaint and defaulted, leading to default judgments of several million dollars. Notice of the judgments was served on Associated but not Fireman’s Fund.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of