Court Narrowly Interprets “Faulty Workmanship” Provision
March 28, 2018 —
Jeffrey J. Vita and Thersa A. Guertin – SDV BlogIn a recent victory in their home state of Connecticut, Saxe Doernberger & Vita partners,
Jeffrey Vita and
Theresa Guertin, representing owner-developer 777 Main Street, LLC, overcame a summary judgment motion filed by Liberty Mutual Fire Insurance Company. The Connecticut Superior court refused to adopt the insurer’s broad interpretation of the “faulty workmanship” exclusion in an all-risk builders’ risk insurance policy.
In 2014, 777 Main Street, LLC began renovations on the 27-story former Hartford National Bank building in downtown Hartford, converting the property from an office building to a mixed residential and commercial space. During the renovation, a subcontractor hired to perform the cleaning the concrete façade of the building accidentally over-sprayed the cleaning material onto the property’s windows. The subcontractor’s attempts to clean the overspray further damaged the structural integrity and cosmetic look of the windows. As a result, the owner was forced to replace over 1,800 windows, costing millions.
Mr. Vita may be contacted at jjv@sdvlaw.com
Ms. Guertin may be contacted at tag@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Wake County Justice Center- a LEED Silver Project done right!
October 01, 2014 —
Melissa Dewey Brumback – Construction Law in North CarolinaYesterday evening, I had the privilege of attending the Triangle USGBC’s “Talk & Walk” at the Wake County Justice Center. The 576,996 square foot Justice Center was completed 6 months early and over 30 million under budget. (The final cost, including soft costs, came in at ~$141,000,000). Now that’s what I call a LEED project done right!
Interestingly, the County did not endeavor for a LEED Silver rating– the plan was to aim for a Certification. However, as the process unfolded, the Team kept meeting the goals and points for a Silver certification without any appreciable additional costs.
The end result? An “iconic but energy efficient building,” according to Tim Ashby, current Wake County Facilities Project Manager. Tim was initially involved in the Project while working at O’Brien Atkins, which served as the architecture firm for the Project under the direction of Architect Andrew Zwiacher.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback may be contacted at
mbrumback@rl-law.com
How the Cumulative Impact Theory has been Defined
November 30, 2020 —
David Adelstein - Florida Construction Legal UpdatesLargely in the federal contract arena, there is a theory referred to as “cumulative impacts” used by a contractor to recover unforeseeable costs associated with a multitude of changes that have an overwhelming ripple effect on its efficiency, particularly efficiency dealing with its original, base contract work. In other words, by dealing with extensive changes, there is an unforeseeable impact imposed on the contractor relative to its unchanged or base contract work. Under this theory, the contractor oftentimes prices its cumulative impact under a total cost approach with an examination on its cost overrun. However, this is not an easy theory to prevail on because there needs to be a focus on the sheer number of changes, causation supporting the impact, and whether there were concurrent impacts or delays that played a role in the ripple effect. See, e.g., Appeals of J.A. Jones Const. Co., ENGBCA No. 6348, 00-2 BCA P 31000 (July 7, 2000) (“However, in the vast majority of cases such claims are routinely denied because there were an insufficient number of changes, contractor-caused concurrent delays, disruptions and inefficiencies and/or a general absence of evidence of causation and impact.”).
To best articulate how the cumulative impact theory has been defined, I want to include language directly from courts and board of contract appeals that have dealt with this theory. This way the contractor knows how to best work with their experts with this definition in mind–and, yes, experts will be needed–to persuasively package and establish causation and damages stemming from the multitude of changes. While many of these definitions are worded differently, you will see they have the same focus dealing with the unforeseeable ripple effect of the extensive changes.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
To Bee or Not to Bee - CA Court Finds Denial of Coverage Based on Exclusion was Premature Where Facts had not been Judicially Determined
November 28, 2018 —
Philip B. Wilusz - Saxe Doernberger & Vita, P.C.While I typically discuss cases concerning pollution, today I will change a few letters around and discuss pollination. The case, Unigard Insurance Co. et al. v. George Perry and Sons Inc. et al., asks whether there is coverage for a lawsuit brought against a commercial farm that is alleged to have killed off bee colonies used for pollination. The farm, owned by George Perry & Sons Inc. (“Perry”), allegedly used a pesticide that killed off the bee colonies that Perry had hired from Gary Mattes (“Mattes”) pursuant to an oral agreement. The bees, operating well outside of their weight class, were hired to pollinate Perry’s crops of watermelons and pumpkins. Interestingly, the bees would be brought to the farm in either large hives or “nukes,” which are smaller versions of hives.
Read the court decisionRead the full story...Reprinted courtesy of
Philip B. Wilusz, Saxe Doernberger & Vita, P.C.Mr. Wilusz may be contacted at
pbw@sdvlaw.com
Construction Litigation Roundup: “A Close Call?”
August 05, 2024 —
Daniel Lund III - LexologyNot really, said a Florida state appellate court when a public construction project owner sued a defaulted general contractor after recovering from the general contractor’s surety.
The general contractor, Close Construction, entered into a contract for a lift station rehabilitation construction project with the City of Riviera Beach in Florida. During the course of the work the public owner terminated the contract, whereupon the GC and the owner brought claims against each other in court. A jury ultimately held against the general contractor and in favor of the public owner in the amount of approximately $1.9 million. The general contractor appealed.
On appeal, the general contractor noted that the public works surety which it was required by the contract to obtain for the project had hired another company to complete the work when the general contractor was terminated and had otherwise “settled with the District under its bond for $1,000,000.” Based on that settlement, the general contractor had moved, unsuccessfully, in the trial court for a post-trial setoff because the “settlement covered the same damages that the jury assessed” against the GC, and because the surety was “jointly and severally liable” with the GC – pursuant to the terms of the bond – for those damages. In essence, the general contractor sought to avoid having the public owner “obtain a double recovery.”
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Singer Ordered to Deposition in Construction Defect Case
December 30, 2013 —
CDJ STAFFThe pop singer Rihanna has sued the former owners of her Los Angeles home and the firm that inspected it before her purchase alleging water intrusion problems that were supposed to be fixed before close of escrow. The lawsuit was filed under the singer’s legal name, Robyn Fenty. According to Gregory Pyfrom, the attorney for LaRocca Inspection Associates, he has tried to depose her over the last two years, without success. He is seeking $7,500 in compensation to his clients for the singer’s failure to schedule a deposition.
Rihanna’s attorney, Miles Cooley, described this as “a smear campaign,” and claims that the parties had agreed not to depose her “until after the matter was mediated.” Mr. Cooley says that mediation has been delayed by Mr. Pyfrom’s vacation plans.
LaRocca Inspection Associates has countersued Rihanna, claiming that if she had alerted them earlier to problems they would have performed an additional inspection. The judge in the case has now ordered that the parties agree to a date on which to depose Ms. Fenty.
Read the court decisionRead the full story...Reprinted courtesy of
3 Common Cash Flow Issues That Plague The Construction Industry
August 20, 2019 —
Patrick Hogan, HandleThe construction industry has its fair share of serious cash flow problems. The nature of the industry with long periods between billing and collection, the unpredictability of some business factors, and even the day-to-day decisions of stakeholders have a huge effect on cash reserves.
So how can you protect your business from these cash flow problems? Having a greater awareness of the most common cash flow problems is the key to maintaining your financial stability. Here are some of the top cash flow issues that construction companies need to watch out for.
1. Uncontrolled business growth
The growth of a business as a cash flow problem sounds unintuitive. It is supposed to be a positive thing. So how could it hurt your construction business? When it goes out of control.
During the growth phase, the company will need to expand its operations to meet the increasing demand. This means renting a larger office space, hiring more staff, and buying more inventory, all of which can burn through the company’s cash quickly. The more substantial the level of your growth is, the more your cash flow is affected.
Growth is a good thing, but it is important to be aware of the pitfalls that you could encounter that can lead to cash flow problems. If you are dealing with a volatile growth instead of a stable one, you have to think twice before expanding your operations. A quarter with a large number of construction project deals does not guarantee the same happening in a subsequent quarter.
2. Change of scope or scope creep
The scope, or the statement of work, is the foundation that guides a construction project from start to finish. It specifies all the deliverables needed by the project as agreed by all stakeholders. When the existing requirements are altered, new features are added, or project goals are changed uncontrollably, what happens is scope creep and it can hurt a company’s cash flow.
Construction projects can take a long time before they are finished. A lot of factors can result in changes in the scope. There may be changes in the market strategy, market demand, and other unpredictable variables that make changes in the project requirements a necessity. These changes build up and the project may shift away from what was intended, causing delays, loss of quality, and the rise of planned costs.
One way to prevent scope creep from affecting cash flow significantly is charging a fee for variations of the scope of work. However, having a solid and clear scope baseline is still the best way to combat scope creep. Reminding clients of what you signed up for by referring to the baseline is a good strategy to deal with pushy clients.
3. Payment delays and nonpayment
As previously mentioned, the construction industry tends to have a lengthy period between sending an invoice and collecting payments. And if you are too passive in your collection, clients are more likely to extend pay periods and delay paying you.
Unexpected delays in payment and other payment issues can have a devastating effect on companies that have little to no cash reserves. Without a cash cushion to fall back on, payment issues can threaten the existence of the business itself. If you are unable to manage your receivables, you will not have enough cash to pay the bills, pay employees, and fund your growth.
Payment delays and nonpayment can happen for several reasons. They can be simple like mistakes in the invoicing or the person needed to approve the invoice is unavailable. More serious reasons like a client unsatisfied with your service or, worse, trying to scam you are also possibilities. For these reasons, it is crucial to communicate with clients properly and see if you can agree with a payment structure or pursue legal action.
The construction industry operates slightly differently from other industries. Different projects produce different cash flow issues and require different strategies. By being aware of the top cash flow problems that can hurt your construction business, you will be better equipped in dealing with them in case they happen.
About the Author:
Patrick Hogan is the CEO of Handle, where they build software that helps contractors, subcontractors, and material suppliers secure their lien rights and get paid faster by automating the collection process for unpaid construction invoices. Read the court decisionRead the full story...Reprinted courtesy of
Patrick Hogan, CEO, Handle
Liquidating Agreements—Bridging the Privity Gap for Subcontractors
September 03, 2015 —
Craig Martin – Construction Contractor AdvisorWhat is a subcontractor to do when the owner has demanded additional work, but has refused to pay for it? Typically, a subcontractor cannot sue the owner because the subcontractor doesn’t have a contract with the owner. Perhaps the subcontractor and general contractor should enter into a liquidating agreement through which the general contractor can pursue the claim on behalf of the subcontractor.
Liquidating agreements bridge the privity gap between owners and subcontractors who sustain damages because of the others actions. Liquidating agreements or pass-through agreements grant the general contractor a release of its liability to the subcontractor after the general contractor prosecutes the subcontractor’s pass-through claim against the owner and gives the subcontractor any recovery.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at