July 20, 2020 —
Amy R. Patton & Rana Ayazi - Payne & FearsOn June 5, 2020, President Trump signed into legislation the bipartisan bill titled the Paycheck Protection Program Flexibility Act of 2020 (PPPFA). The PPPFA modifies the Paycheck Protection Program, which was first introduced under the Coronavirus Aid, Relief, and Economic Security Act (CARES Act). The modifications provide borrowers more control over the use of funds and make it easier to obtain forgiveness. The following is a summary of the key changes.
1. Extended Maturity Date From 2 Years to 5 Years
Under the CARES Act, the minimum maturity date for loan amounts after the forgiveness period was not defined. The Small Business Administration (SBA) then released an Interim Final Rule clarifying that the minimum maturity date was two years. The PPPFA has extended the term to five years: “The covered loan shall have a minimum maturity of 5 years and a maximum maturity of 10 years from the date on which the borrower applies for loan forgiveness under that section.”
2. Extension of Covered Period From Eight Weeks to a Maximum of 24 Weeks
Under the CARES Act, the covered period of the loan (i.e., the time period in which you may spend the loan funds) was February 15, 2020 to June 30, 2020, an eight-week period. The PPPFA extended the covered period to 24 weeks from the origination date of the loan, or December 31, 2020, whichever is earlier.
Reprinted courtesy of
Amy R. Patton, Payne & Fears and
Rana Ayazi, Payne & Fears
Ms. Patton may be contacted at arp@paynefears.com
Ms. Ayazi may be contacted at ra@paynefears.com
Read the court decisionRead the full story...Reprinted courtesy of
Expansion of Statutes of Limitations and Repose in K-12 and Municipal Construction Contracts
March 27, 2019 —
Henry Bangert - Colorado Construction LitigationThe purpose of this whitepaper is to bring attention to a trend in K-12 and municipal construction contracts, which expands the time periods for law suits against construction professionals.
Introduction and Background
Under Colorado statute, the period of time within which a legal action for construction defects may be brought against a construction professional in Colorado is two years from when the claimant (or its predecessor in interest) discovers or in the exercise of reasonable diligence should have discovered the physical manifestations of a defect (the “Statute of Limitations”), but in no case may an action be brought more than six years after substantial completion of the improvement, unless the claim arises in the fifth or sixth year after substantial completion, in which event the action may be brought within two years of such date, i.e., up to eight years after substantial completion (the “Statute of Repose”). See C.R.S. § 13-80-104. While the triggering events differ for the Statute of Limitations and Statue of Repose, the periods are intended to run concurrently to limit the period of time an action may be brought against construction professionals for construction defects to, at most, eight years after substantial completion. Importantly, these limitations periods may be expanded by agreement.
Prior to 1986, Colorado law provided for a 10-year Statute of Repose. However, in 1986, Colorado’s legislature shortened the Statute of Repose time limit to the current six (or up to eight) year period. In 1986, Colorado also redefined the date the claim arises from the date the defect was discovered or should have been discovered to the date the physical manifestation of a defect was discovered or should have been discovered. Therefore, after 1986, the two-year limitations period could begin to run when a claimant should have discovered the manifestation of a defect, even if the claimant did not recognize that a defect existed.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Home Prices Rose in Fewer U.S. Markets in Fourth Quarter
February 12, 2014 —
Prashant Gopal – BloombergPrices for single-family homes rose in 73 percent of U.S. cities in the fourth quarter, fewer than in the previous three months, as surging values in the past two years started to reduce affordability.
The median transaction price for an existing home climbed from a year earlier in 119 of 164 metropolitan areas measured, the National Association of Realtors said in a report today. In the third quarter, 88 percent of markets had increases.
While tight inventories and improving employment are bolstering the housing recovery, home-price gains are poised to decelerate as an increase in mortgage rates from record lows cuts into affordability. Values have been rising faster than incomes, particularly in the West, the Realtors group said.
Read the court decisionRead the full story...Reprinted courtesy of
Prashant Gopal, BloombergMr. Gopal may be contacted at
pgopal2@bloomberg.net
The Riskiest Housing Markets in the U.S.
June 26, 2014 —
Ben Steverman – BloombergThe real estate rollercoaster ride for U.S. homeowners isn't new. Some markets had even rockier rides in the early 1980s or '90s.
When so much wealth is tied up in one asset, the risk -- or stability -- of a local market can mean a lot to a homeowner. (See “The Hidden Risks in Your Housing Market” for more on this.)
Bloomberg.com asked real estate website Zillow.com to help us figure out which U.S. markets have been the riskiest over the last 35 years.
Our measure of risk: Assuming buyers held on to their homes for five years before selling, what was their chance of suffering a loss? As a secondary criterion, we compared the worst annual losses homeowners in these markets have experienced since 1979.
Read the court decisionRead the full story...Reprinted courtesy of
Ben Steverman, BloombergMr. Steverman may be contacted at
bsteverman@bloomberg.net
The Rubber Hits the Ramp: A Maryland Personal Injury Case
September 17, 2014 —
Beverley BevenFlorez-CDJ STAFFAn elderly woman filed suit against the Town of Ocean City, Maryland, “after allegedly falling from her wheelchair because of a defective rubber warning mat on a resort street corner,” according to The Dispatch.
The accident occurred when the woman’s wheelchair “struck one of the hard rubber warning mats on the handicap-accessible street corners.”
The plaintiff is seeking “$750,000 in damages on three counts including negligence, strict liability and a violation of the Americans with Disabilities Act (ADA).” However, The Dispatch reported that it is not clear who is liable, since the sidewalk is owned and maintained by the town, but the State Highway Administration installed the rubber warning mats.
Read the court decisionRead the full story...Reprinted courtesy of
ASCE Statement on House Failure to Pass the Infrastructure Investment and Jobs Act
October 04, 2021 —
Tom Smith - American Society of Civil EngineersThe following is a statement by Tom Smith, Executive Director, American Society of Civil Engineers (ASCE):
WASHINGTON, DC. – Today, American families and businesses are paying the price while the House plays politics and fails to pass the bipartisan Infrastructure Investment and Jobs Act (IIJA), a historic piece of legislation that would have monumental impacts on the economy, public safety, global competitiveness, and each American's well-being. After decades of kicking the can down the road on meaningful infrastructure legislation, Congress is missing an extraordinary chance to reverse this unsustainable trend with passage of the IIJA, instead choosing to allow critical projects to be delayed.
This legislation was passed in a strong vote by the Senate on August 10th, and almost two months later, it sits on the sidelines as the federal program for transit, roads, and bridges expired on September 30th and projects come grinding to a halt. While other countries are making investments in their future, we are letting politics steal this opportunity to move forward.
It does not have to be this way. This comprehensive bill would bring relief to communities facing strained power grids, aging bridges, leaking water pipes, and spotty broadband. American families do not want to have to wonder if their power will stay on in the next storm, if the bridge connecting their community will close for emergency repairs, or if a week of virtual school means their child will miss out.
We urge the House to pass this bipartisan, commonsense legislation today to create jobs, make goods and services move more quickly and reliably, and make American communities more climate-resilient. Our infrastructure bill has come due, and now is the time to act.
ABOUT THE AMERICAN SOCIETY OF CIVIL ENGINEERS
Founded in 1852, the American Society of Civil Engineers represents more than 150,000 civil engineers worldwide and is America's oldest national engineering society. ASCE works to raise awareness of the need to maintain and modernize the nation's infrastructure using sustainable and resilient practices, advocates for increasing and optimizing investment in infrastructure, and improve engineering knowledge and competency. For more information, visit www.asce.org or www.infrastructurereportcard.org and follow us on Twitter, @ASCETweets and @ASCEGovRel.
Read the court decisionRead the full story...Reprinted courtesy of
Review the Terms and Conditions of Purchase Orders- They Could be Important!
February 15, 2018 —
Christopher G. Hill – Construction Law MusingsThere are many moving parts on a commercial construction project. These range from site surveys to weather events to ordering materials. On most large construction projects, the prime contract and subcontracts are generally
drafted ahead of time and hopefully reviewed by both in house personnel and an
experienced construction attorney. However, there are situations, particularly where the contract may be one for service or provision of materials where individual purchase orders are issued as opposed to what would likely be looked at as a long form subcontract.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. Hill, PC
Insurance Policy’s “No Voluntary Payment” Clauses Lose Some Bite in Colorado
October 22, 2013 —
Brady Iandiorio — Higgins, Hopkins, McLain & Roswell, LLC.The Colorado Court of Appeals recently handed down an opinion dulling the teeth of the “no voluntary payment” clauses found in many contractors’ insurance policies. In the case of Stresscon Corporation v. Travelers Property Casualty Company of America, 2013 WL 4874352 (Colo. App. 2013), the Court of Appeals found that an insured’s breach of the “no voluntary payment” clause does not always bar the insured from receiving benefits from its insurance company.
In July 2007, at a construction project run by Mortenson (the “GC”), a partially erected building collapsed, killing one worker and gravely injuring another. The collapse was caused by a crane hook pulling a concrete component off of its supports. The GC contracted with Stresscon Corporation (“Stresscon”) to build pre-cast concrete components for the project, and in turn Stresscon hired two sub-subcontractors, RMS and Hardrock (the “Crane Team”) to work together to erect those concrete components. Stresscon and the Crane Team had liability insurance, and Stresscon was insured by Travelers Property Casualty Company of America (“Travelers”).
The accident led to three separate lawsuits: 1) one brought by the deceased worker; 2) one brought by the injured worker; and 3) one brought by the GC against Stresscon claiming it was entitled to contract damages incurred because the project was delayed.
Read the court decisionRead the full story...Reprinted courtesy of
Brady IandiorioBrady Iandiorio can be contacted at