Washington’s Court of Appeals Protects Contracting Parties’ Rights to Define the Terms of their Indemnity Agreements
March 19, 2024 —
Margarita Kutsin - Ahlers Cressman & Sleight PLLCIt has long been the law in Washington that contracting parties are free to draft contractual indemnity agreements to allocate risk arising from performance of the work, and Courts will generally enforce those agreements as written. This well-settled principle was recently reaffirmed in King County v. CPM Development Corp., dba ICON Materials[1] a decision from Division I of the Washington Court of Appeals, wherein one party to an indemnity agreement attempted to evade its contractual obligations by arguing that certain common law indemnity principles supersede the written terms. This appeal followed a multi-week jury trial from which the client and Ahlers Cressman and Sleight legal team, including Lindsay Watkins, Klien Hilliard, and Christina Granquist, obtained a seven-figure judgment in the client’s favor, including an award of all attorneys’ fees and costs.
ICON was the general contractor on a Vashon Island Highway Pavement project for King County. Part of the work on the project involved hauling away and disposing of ground milled asphalt (the “millings”) at King County-approved sites. ICON and D&R Excavating Inc., (“D&R”) executed a subcontract for D&R to perform that work. The subcontract incorporated the contract between ICON and King County, including the obligation to stockpile millings only at approved sites. D&R, however, did not obtain the requisite approvals from King County, and placed the millings at various sites on the Island, including locations that King County explicitly rejected.
Read the court decisionRead the full story...Reprinted courtesy of
Margarita Kutsin, Ahlers Cressman & Sleight PLLCMs. Kutsin may be contacted at
margarita.kutsin@acslawyers.com
Reminder: Your MLA Notice Must Have Your License Number
November 26, 2014 —
Christopher G. Hill – Construction Law MusingsRemember a couple of years ago when the Virginia mechanic’s lien rules changed to require inclusion of a claimant’s contractor’s license number (where a license is required)? If not, then this is a reminder of that particular wrinkle in the strictly interpreted mechanic’s lien statute. This requirement applies to all mechanic’s lien memoranda and, like all parts of this crazy statute, will invalidate a lien if not met. Well, another change to the statute happened with a bit less fanfare.
The change back in 2013 that came along with the license number requirement for a lien memorandum is a change in the mechanic’s lien agent notice requirement that applies to residential construction. The basic requirement, namely that those performing residential construction must notify any mechanic’s lien agent (“MLA”) listed on a building permit within 30 days of starting work that they are on the job and could file a lien, has not changed. What the amendments to the lien statutes in 2013 added was a requirement that the notice, like a lien memorandum, must include the contractor’s or subcontractor’s license number.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Michael Baker Intl. Settles Federal Pay Bias Allegations
February 26, 2024 —
James Leggate - Engineering News-RecordMichael Baker International Inc. agreed to pay $122,299 in back wages as part of an agreement with the U.S. Dept. of Labor to resolve allegations that the engineer-consultant paid women in four job titles less than their male counterparts.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Hunton Insurance Head Interviewed Concerning the Benefits and Hidden Dangers of Cyber Insurance
December 04, 2018 —
Michael S. Levine - Hunton Insurance Recovery BlogThe head of Hunton Andrews Kurth’s insurance practice, Walter Andrews, was interviewed earlier this week by ABC 7 (WJLA) concerning the need for cyber insurance and the benefits that it can provide to government contractors and other businesses that are impacted by a cyber event. Andrews explains the diverse spectrum of benefits that are available through cyber insurance products, but cautions that a serious lack of uniformity exists among today’s cyber insurance products, making it crucial that policyholders carefully analyze their cyber insurance to ensure it provides the scope and amount of insurance they desire.
Read the court decisionRead the full story...Reprinted courtesy of
Michael S. Levine, Hunton Andrews KurthMr. Levine may be contacted at
mlevine@HuntonAK.com
Newmeyer Dillion Announces New Partners
January 06, 2020 —
Michael Krueger & Jason Morris - Newmeyer DillionProminent business and real estate law firm Newmeyer Dillion is pleased to announce that Walnut Creek attorney, Michael Krueger, and Newport Beach attorney, Jason Morris, have been elected to partnership. Their promotion is effective immediately.
"We are proud to have Jason and Mike join the firm's partnership," said Managing Partner Paul Tetzloff. "They both embody the firm's core cultural pillars – like, trust, respect and loyalty – and they've both demonstrated a commitment to outstanding client service and excellent legal work. They will continue to propel the firm's success for decades to come."
Michael Krueger is based in the firm's Walnut Creek office, representing companies at every stage of the business life cycle to create business solutions that minimize risk and accomplish strategic objectives. Recognized as a 2019 California Trailblazer by The Recorder, Krueger is a trusted advisor for complex business negotiations, real estate ventures including Opportunity Zone projects, mergers and acquisitions, bank finance and private equity transactions. A former in-house counsel and business owner, he serves as general counsel for clients focused on expanding their operations, products, and services. Krueger earned his B.A from Marian University and his J.D. from Valparaiso School of Law.
Jason Morris is based in the firm's Newport Beach office, representing companies in all aspects of labor & employment law and business litigation. Whether offering practical advice on a wide range of day-to-day employment law issues, or navigating the complexity of all aspects of civil litigation defense, his focus is helping clients avoid potential legal landmines and keep their business assets protected. Morris brings significant leadership and trial experience to his practice, serving for nearly eight years on active duty in the United States Marine Corps as a Judge Advocate both in the Pentagon advising senior military and civilian leaders, and as a trial attorney successfully representing more than 300 cases, including over 10 trials to verdict. Morris earned his B.A. from Marian University, cum laude, and his J.D. from Indiana University Maurer School of Law.
About Newmeyer Dillion
For 35 years, Newmeyer Dillion has delivered creative and outstanding legal solutions and trial results that achieve client objectives in diverse industries. With over 70 attorneys working as a cohesive team to represent clients in all aspects of business, employment, real estate, privacy & data security and insurance law, Newmeyer Dillion delivers holistic and integrated legal services tailored to propel each client's success and bottom line. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California and Nevada, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949.854.7000 or visit www.newmeyerdillion.com.
Read the court decisionRead the full story...Reprinted courtesy of
New WA Law Caps Retainage on Private Projects at 5%
May 29, 2023 —
Brett M. Hill & Ryanne S. Mathisen - Ahlers Cressman & Sleight PLLCThis month, Governor Jay Inslee signed into law a new statute that caps retainage on private construction projects to five percent (5%), provides a mechanism for subcontractors to get paid their retainage prior to project completion, and allows for contractors and subcontractors to post a retainage bond and get paid their retainage early. For those interested in reading the full text of this new law, the statute can be found
here.
The new statute goes into effect on July 23, 2023. Under the statute, when a contractor or subcontractor considers their work under a contract subject to retainage complete, they may notify the party they contracted to perform the work for. Within 15 days of receiving the notice of completion of work, the party receiving the notice must respond with either (1) notice of acceptance of work or (2) notice of uncompleted items to the contractor or subcontractor.
If the party receiving notice does not provide notice of uncompleted items within 15 days or fails to respond to the notice of completion entirely, the unpaid retainage will begin to accrue interest at a rate of one percent (1%) per month, 30 days after the initial 15-day period. However, this interest will not accrue against a contractor who has not been paid the retainage by an upper-tier contractor or owner until payment has been received, so long as that contractor has submitted its subcontractor’s notice of completion to the upper-tier contractor or owner within 30 days of receipt.
Reprinted courtesy of
Brett M. Hill, Ahlers Cressman & Sleight PLLC and
Ryanne S. Mathisen, Ahlers Cressman & Sleight PLLC
Mr. Hill may be contacted at brett.hill@acslawyers.com
Ms. Mathisen may be contacted at ryanne.mathisen@acslawyers.com
Read the court decisionRead the full story...Reprinted courtesy of
Eleventh Circuit’s Noteworthy Discussion on Bad Faith Insurance Claims
November 01, 2021 —
David Adelstein - Florida Construction Legal UpdatesThe Eleventh Circuit Court of Appeal’s opinion in Pelaez v. Government Employees Insurance Company, 2021 WL 4258821 (11th Cir. 2021) is a non-construction case that discusses the standard for pursuing a bad faith claim against an insurer. This case dealt with an automobile accident. While the facts of the case are interesting and will be discussed, the takeaway is the Eleventh Circuit’s noteworthy discussion on the standard for bad faith claims and how they should be evaluated. This discussion is included below–with citations–because while the term “bad faith” is oftentimes thrown around when it comes to insurance carriers, there is indeed an evaluative standard that is applied to determine whether an insurance carrier acted in bad faith.
In Pelaez, a high school student driving a car crashed with a motorcycle. The motorcycle driver was seriously injured and airlifted to the hospital. The accident was reported to the automobile liability insurer of the driver of the car. The insurer through its investigation initially believed the motorcycle driver was contributory negligent. Eleven days after the crash, after learning additional information, the insurer tendered its bodily injury policy limits of $50,00 to the motorcycle driver even though it never received a settlement demand. The insurer sent a tender package to the motorcycle driver’s lawyer that included a $50,000 check for the bodily injury claim and a proposed release. The accompanying letter told the attorney to contact the insurer with any questions about the release and to edit the proposed release with suggested changes. The insurer also wanted to inspect the motorcycle in furtherance of adjusting the property damage claim which also had a policy limit of $50,000. A location of where the motorcycle could be inspected was never provided.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
July 1, 2015 Statutory Changes Affecting Virginia Contractors and Subcontractors
June 10, 2015 —
Christopher G. Hill – Construction Law MusingsAs always seems to be the case, this year, as in others, the Virginia General Assembly has seen fit to “tweak” a few construction related statutes. All of these changes will go into effect on July 1, 2015.
The big one, and one that I posted about a while back is the change to the Virginia mechanic’s lien statute to prohibit contractual waiver of lien, payment bond or claims for additional costs prior to the furnishing of labor or materials. This one is big because it relieves a bit of the angst in the pre-contract negotiations between subcontractors and general contractors.
Another significant change, this one to the wording of Virginia Code 2.2-4309, found in House Bill 1628, clarifies the fact that this Virginia statute does not limit the amount a government contractor may claim or recover against a public body under a contract dispute. This is a big one considering the ruling in the Carnell Construction Corp. v. Danville Redevelopment Housing Authority LLC limiting such claims.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com