Timely and Properly Assert Affirmative Defenses and Understand Statutory Conditions Precedent
August 05, 2024 —
David Adelstein - Florida Construction Legal UpdatesA recent case serves as a reminder to TIMELY and PROPERLY assert affirmative defenses and to understand statutory conditions precedent to construction lien claims. Failing to do one or the other could be severely detrimental to the position you want to take in a dispute, whether it is a lien foreclosure dispute, or any other dispute.
In Scherf v. Tom Krips Construction, Inc., 2024 WL 3297592 (Fla. 4th DCA 2024), the president of a construction company and his wife were building a residence. They orally accepted the proposal from the concrete shell contractor and asked for invoices to be submitted to the president’s construction company. No written contract was memorialized. The president and his wife did not pay the concrete shell contractor and the contractor recorded a lien and sued to foreclose on the lien. Years later (the case had been stayed because the president and his wife filed for bankruptcy and the shell contractor had to get leave of the automatic bankruptcy stay to pursue the lien foreclosure), the shell contractor moved for summary judgment. The president and his wife moved for leave to file an amended answer and affirmative defenses. They claimed the oral contract was with the construction company and the shell contractor was required to serve a Notice to Owner under
Florida Statute s. 713.06. Alternatively, they argued that if the oral contract was with the president and his wife, the shell contractor was required to serve a Final Contractor’s Payment Affidavit at least 5 days before filing its lien foreclosure claim, and did not, as required by s. 713.06.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
High Court Could Alter Point-Source Discharge Definition in Taking Clean-Water Case
March 18, 2019 —
Mary B. Powers - Engineering News-RecordThe U.S. Supreme Court's decision to review lower court rulings on whether a permit is required under the federal Clean Water Act when pollutants originate from a point source but are carried to navigable waters by a non-point source such as groundwater could set some new parameters for compliance, observers say.
Read the court decisionRead the full story...Reprinted courtesy of
Mary B. Powers, ENRENR may be contacted at
ENR.com@bnpmedia.com
Federal Court Finds Occurrence for Faulty Workmanship Under Virginia Law
July 31, 2013 —
Tred Eyerly, Insurance Law HawaiiThe Federal District Court in Virginia found that allegations of faulty workmanship could arise from an occurrence. Nautilus Ins. Co. v. Strongwell Corp., 2013 U.S. Dist. LEXIS 79163 (W. D. Va. June 4, 2013).
Strongwell supplied certain fiberglass reinforced plastic materials to a subcontractor of Black & Veatch for a construction project at power plant. Black & Veatch subsequently sued Strongwell, claiming that numerous defects in Strongwell's materials and work were discovered after the project was completed. The complaint further alleged that as a result of the defects, there was widespread property damage to portions of the power plant.
Nautilus defended under a reservation of rights. Nautilus also filed suit for a declaratory judgment that to establish it had no duty to defend or indemnify Strongwell. Strongwell moved to dismiss the complaint insofar as it requested a declaration that there was no duty to defend. Strongwell also filed a motion to stay the coverage action until the underlying case was completed.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
NEHRP Recommendations Likely To Improve Seismic Design
November 09, 2020 —
Nadine M. Post - Engineering News-RecordCode-based earthquake engineering is on the verge of getting simpler, thanks to the National Earthquake Hazards Reduction Program’s recommendation to replace the traditional seismic hazard maps with an improved seismic hazards database. The recommendation is one of the most significant changes put forth in the 2020 update of the NEHRP seismic design provisions, which are the foundation for the prescriptive seismic design code for buildings and other structures.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Providing Notice of Claims Under Your Construction Contract
April 02, 2014 —
Beverley BevenFlorez-CDJ STAFFCraig Martin on his blog Construction Contractor Advisor explained the importance of knowing when to provide notice under your construction contract: “Time and time again, courts rule that contractors must follow notice requirements in order to submit a claim for additional time or compensation.”
Martin cited the case JEM Contracting v. Morrison-Maierle, where the contractor provided verbal notice of a claim to the engineer, but failed to submit in writing until eighteen days later, which was past the notice requirement as stated in the contract. The judge denied the contractor’s claim and sided with the engineer and county.
Read the court decisionRead the full story...Reprinted courtesy of
Chattanooga Bridge Collapse Likely Resulted From Impact
April 17, 2019 —
Jim Parsons - Engineering News-RecordTennessee highway officials believe an impact from a vehicle’s oversized load is likely to blame for the April 1 partial collapse of a ramp structure at the I-75/I-24 interchange in Chattanooga. The impact caused the outer box beam and railing of the 148-ft-long bridge’s nearly 51-ft main span to fall onto an access ramp, injuring a motorist whose vehicle collided with the debris.
Read the court decisionRead the full story...Reprinted courtesy of
Jim Parsons, ENRENR may be contacted at
ENR.com@bnpmedia.com
Paul Tetzloff Elected As Newmeyer & Dillion Managing Partner
June 03, 2019 —
Newmeyer & Dillion LLPNewmeyer & Dillion LLP, a prominent business and real estate law firm, selected Paul Tetzloff as the firm's Managing Partner. His term began on January 1, 2019. A business litigator, Tetzloff will now oversee the firm's strategic plan and manage the firm's day-to-day business affairs.
"The Firm is incredibly fortunate to have Paul stepping into the role as Managing Partner. His energy, intelligence, leadership, and drive make him uniquely qualified to lead this Firm for years to come," said former Managing Partner Jeff Dennis. "I am excited to watch where the Firm is headed – we have such an amazing opportunity to continue to develop to even greater heights, and Paul will be a huge part of making that happen."
Active in his community, Tetzloff sits on the board for HomeAid Orange County and the Marine Raider Association.
Tetzloff is succeeding Dennis, who served in the role from 2012 to 2018. "Jeff was our managing partner for seven years and he did an outstanding job. We owe Jeff a debt of gratitude for his service," said Tetzloff of his predecessor. "I'm looking forward to continuing to build on the groundwork laid to help the firm reach new levels in the years to come."
Dennis' leadership allowed the firm to grow substantially under his tenure, including opening a Las Vegas, Nevada office and establishing thriving practice areas throughout various industries. Dennis will focus his energy on overseeing the firm's growing Privacy and Data Security practice.
Paul Tetzloff
paul.tetzloff@ndlf.com
Practice Areas
Business Litigation
Construction Litigation
Real Estate Litigation
About Newmeyer & Dillion
For almost 35 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, privacy & data security and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client's needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949.854.7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Gen Xers Choose to Rent rather than Buy
February 05, 2014 —
Beverley BevenFlorez-CDJ STAFFDavid Crowe reported in Big Builder that the rate of home purchases by Gen Xers is low due to “challenges” they face caused by the recent recession. According to the article, “The headship rate rises from 16 percent to 48 percent in this age group—known as Generation X—as they finish college and become financially independent. There are 42.5 million people in this age range, and they are followed by 43.9 million in the 15 to 24 age cohort.” However, the recession forced many Gen Xers to postpone “independent living, marriage, and children. Birth rates hit all-time lows in 2012 (half the level of the baby boom), and marriage rates are the lowest they’ve been in a century.”
Unemployment seems to be the major factor in why many Gen Xers are choosing to live with parents or rent instead of buying a home. Crowe stated, “Young adults continue to express the goal of owning their own homes, but many are faced with challenges such as job availability, tight credit standards, inadequate savings for a down payment, student debt, and careers that are likely to require moves.” However, the “employment picture is expected to improve.”
Read the court decisionRead the full story...Reprinted courtesy of