Hunton Insurance Partner Syed Ahmad Serves as Chair of the ABA Minority Trial Lawyer Committee’s Programming Subcommittee
January 13, 2020 —
Michelle M. Spatz - Hunton Insurance Recovery BlogSyed Ahmad, a partner in Hunton Andrews Kurth’s Insurance Coverage practice, has volunteered to serve as Chair of the
ABA Minority Trial Lawyer Committee’s Programming Subcommittee. The Minority Trial Lawyer Committee (MTL) serves as a resource for minority litigators, in-house counsel and law students, aiming to foster professional development, legal scholarship, advocacy and community involvement. As Chair of the Programming Subcommittee, Syed, who was named to Benchmark Litigation’s 40 & Under Hot List earlier this year, will help advance MTL’s mission of facilitating discussions about diversity and the law and providing career network opportunities for minority trial lawyers.
Read the court decisionRead the full story...Reprinted courtesy of
Michelle M. Spatz, Hunton Andrews KurthMs. Spatz may be contacted at
mspatz@HuntonAK.com
Architecture, Robotics, and the Importance of Human Interaction – An Interview with Prof. Kathrin Dörfler
September 21, 2020 —
Aarni Heiskanen - AEC BusinessWe sat down with Professor Kathrin Dörfler of the Technical University of Munich (TUM) in advance of WDBE 2020. We discussed the importance of innovation and how her research focuses on the need for practical and productive solutions when it comes to on-site support.
Digital and technical innovation plays an essential role in optimizing the modern built environment. Now leading the Augmented Fabrication Lab (AFAB) in TUM, Professor Kathrin Dörfler quickly saw the need for practical solutions early in her career.
The Importance of ‘Need’
“I’m originally an architect,” she says. “I studied digital art and architecture and my tendency to go toward digital fabrication came from this proximity to computational design and the need to use robots for fabrication. There was no other way to build the things you created in your virtual space without using machinery.”
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Release Of “Unknown” Claim Does Not Bar Release Of “Unaccrued” Claim: Fair Or Unfair?
July 15, 2019 —
David Adelstein - Florida Construction Legal UpdatesA general release of “unknown” claims through the effective date of the release does NOT bar “unaccrued” claims. This is especially important when it comes to fraud claims where the facts giving rise to the fraud may have occurred prior to the effective date in the release, but a party did not learn of the fraud until well after the effective date in the release. A recent opinion maintained that a general release that bars unknown claims does NOT mean a fraud claim will be barred since the last element to prove a fraud had not occurred, and thus, the fraud claim had not accrued until after the effective date in the release. See Falsetto v. Liss, Fla. L. Weekly D1340D (Fla. 3d DCA 2019) (“The 2014 [Settlement] Agreement’s plain language released the parties only from “known or unknown” claims, not future or unaccrued claims. Because there is a genuine issue of material fact as to whether the fraud claim had accrued — that is, whether Falsetto [party to Settlement Agreement] knew or through the exercise of due diligence should have known about the alleged fraud at the time the 2014 Agreement was executed — the trial court erred in granting summary judgment on those fraud claims.”).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
US Supreme Court Backs Panama Canal Owner in Dispute with Builders
May 20, 2024 —
C.J. Schexnayder - Engineering News-RecordA long-running legal battle over the concrete used in construction of the Panama Canal's third lane expansion locks has reached its end in U.S. courts—with the U.S. Supreme Court on March 26 upholding a $271.8-million award to the project owner, the Panama Canal Authority, against its contractor group, Grupo Unidos por el Canal.
Reprinted courtesy of
C.J. Schexnayder, Engineering News-Record
Mr. Schexnayder may be contacted at schexnayderc@enr.com
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
History of Defects Leads to Punitive Damages for Bankrupt Developer
March 01, 2012 —
CDJ STAFFThe South Carolina Court of Appeals has ruled that evidence of construction defects at a developer’s other projects were admissible in a construction defect lawsuit. They issued their ruling on Magnolia North Property Owners’ Association v. Heritage Communities, Inc. on February 15, 2012.
Magnolia North is a condominium complex in South Carolina. The initial builder, Heritage Communities, had not completed construction when they filed for bankruptcy protection under Chapter 11. The remaining four buildings were completed by another contractor. The Property Owners’ Association subsequently sued Heritage Communities, Inc. (HCI) alleging defects. The POA also sued Heritage Magnolia North, and the general contractor, BuildStar.
The trial court ruled that all three entities were in fact one. On appeal, the defendants claimed that the trial court improperly amalgamated the defendants. The appeals court noted, however, that “all these corporations share officers, directors, office space, and a phone number with HCI.” Until Heritage Communities turned over control of the POA to the actual homeowners, all of the POA’s officers were officers of HCI. The appeals court concluded that “the trial court’s ruling that Appellants’ entities were amalgamated is supported by the law and the evidence.”
Heritage also claimed that the trial court should not have allowed the plaintiffs to produce evidence of construction defects at other Heritage properties. Heritage argued that the evidence was a violation of the South Carolina Rules of Evidence. The court cited a South Carolina Supreme Court case which made an exception for “facts showing the other acts were substantially similar to the event at issue.” The court noted that the defects introduced by the plaintiffs were “virtually identical across all developments.” This included identical use of the same products from project to project. Further, these were used to demonstrate that “HCI was aware of water issues in the other projects as early as 1998, before construction on Magnolia North had begun.”
The trial case ended with a directed verdict. Heritage charged that the jury should have determined whether the alleged defects existed. The appeals court noted that there was “overwhelming evidence” that Heritage failed “to meet the industry standard of care.” Heritage did not dispute the existence of the damages during the trial, they “merely contested the extent.”
Further, Heritage claimed in its appeal that the case should have been rejected due to the three-year statute of limitations. They note that the first meeting of the POA was on March 8, 2000, yet the suit was not filed until May 28, 2003, just over three years. The court noted that here the statute of limitation must be tolled, as Heritage controlled the POA until September 9, 2002. The owner-controlled POA filed suit “approximately eight months after assuming control.”
The court also applied equitable estoppel to the statute of limitations. During the time in which Heritage controlled the board, Heritage “assured the unit owners the construction defects would be repaired, and, as a result, the owners were justified in relying on those assurances.” Since “a reasonable owner could have believed that it would be counter-productive to file suit,” the court found that also prevented Heritage from invoking the statute of limitations. In the end, the appeals court concluded that the even apart from equitable tolling and equitable estoppel, the statute of limitations could not have started until the unit owners took control of the board in September, 2002.
Heritage also contested the jury’s awarding of damages, asserting that “the POA failed to establish its damages as to any of its claims.” Noting that damages are determined “with reasonable certainty or accuracy,” and that “proof with mathematical certainty of the amount of loss or damage is not required,” the appeals court found a “sufficiently reasonable basis of computation of damages to support the trial court’s submission of damages to the jury.” Heritage also claimed that the POA did not show that the damage existed at the time of the transfer of control. The court rejected this claim as well.
Finally, Heritage argued that punitive damages were improperly applied for two reasons: that “the award of punitive damages has no deterrent effect because Appellants went out of business prior to the commencement of the litigation” and that Heritages has “no ability to pay punitive damages.” The punitive damages were upheld, as the relevant earlier decision includes “defendant’s degree of culpability,” “defendants awareness or concealment,” “existence of similar past conduct,” and “likelihood of deterring the defendant or others from similar conduct.”
The appeals court rejected all of the claims made by Heritage, fully upholding the decision of the trial court.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Renee Zellweger Selling Connecticut Country Home
August 06, 2014 —
Emily Heffter – BloombergYou had me at seven fireplaces (and a bread oven).
Actress Renee Zellweger’s Connecticut country home, on the market for $1.6 million, is hardly roughing it.
The luxury farmhouse, built in 1770 and updated in 2004, is a stylish and luxurious country getaway. Set on 38 acres overlooking the Quinebaug River in rural Pomfret Center, the retreat at 96 Cotton Rd is 3,463 square feet with a top-of-the-line kitchen, a bread oven in the family room and a swimming pool.
Read the court decisionRead the full story...Reprinted courtesy of
Emily Heffter, Zillow
CSLB’s Military Application Assistance Program
October 20, 2016 —
Garret Murai – California Construction Law BlogWho knew? I didn’t.
Military Applicants, with Proper Forms, Move to Front of Line for Contractor License Processing
SACRAMENTO – The Contractors State License Board (CSLB) salutes U.S. military personnel for their service and offers expedited application processing by specially trained staff to veterans seeking to become licensed contractors. Unfortunately, not all veterans applying for California contractor licenses are able to take advantage of this opportunity because they do not submit the forms required for this service.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Public Contract Code Section 1104 Does Not Apply to Claims of Implied Breach of Warranty of Correctness of Plans and Specifications
October 30, 2023 —
Garret Murai - California Construction Law BlogIt’s the classic tale of two cities. One city is occupied by architects and engineers. The other, by contractors. And while the cities typically co-exist relatively peacefully together, at times, they do not, such as when a defect arises that can either be a design or construction defect.
Sometimes, project owners are pulled into these fights as well. There is a common law rule that when contracting with a contractor the owner impliedly warrants to the contractor that the plans and specifications are sufficiently accurate and correct.
And, if you work on local public works projects, you may be familiar with Public Contract Code section 1104 which provides that, with the exception of design-build projects, local public entities cannot require a bidder to assume responsibility for the completeness and accuracy of architectural or engineering plans and specifications.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com