Practical Pointers for Change Orders on Commercial Construction Contracts
December 31, 2014 —
John E. Bowerbank - Newmeyer & DillionConstruction projects pose unique challenges, including keeping costs within budget, meeting project deadlines, and coordinating the work of numerous contractors and subcontractors in the wake of inevitable design revisions and changes to the plans. Anticipating potential project challenges and negotiating contract provisions before commencing work on a project is critical for all parties. Careful planning should reduce the number of contract disputes. This, in turn, can facilitate the completion of a project within budget and on schedule.
“Changes” Clauses in Construction Contracts
Most commercial construction contracts have a clause addressing changes to the contract. A “changes” clause typically requires the mutual agreement of the parties on the scope of any modifications to the contract, as well as the effect on the contract price and timeframe for the work to be performed. This results in what is generally referred to as a “change order.” Many projects have a large number of change orders, which can result in significant cost overruns and delays to the project if the contract contains a complicated change order process. Therefore, in order to minimize cost overruns and project delays, it is crucial to keep the change order process as simplified and streamlined as possible.
In the most basic terms, change orders memorialize modifications to the original contract, and typically alter the contract's price, scope of work, and/or completion dates. A typical change order is a written document prepared by the owner or its design professional, and signed by the owner, design professional, and affected contractors and subcontractors. An executed change order indicates the parties’ agreement as to what changes are taking place, including approval for additional costs and schedule impacts.
While the reasons for change orders and the parties initiating them may vary, all change orders have one feature in common. Effective change orders alter the original contract and become part of the contract. Therefore, from a legal standpoint, change orders must be approached with the same caution and forethought as the original contract.
Practice Pointers for Change Orders
In light of the foregoing, some practice pointers for change orders in commercial construction contracts are as follows:
- Carefully Negotiate and Draft Change Order Provisions in the Original Contract.
A carefully negotiated and drafted “changes” clause that accounts for “unexpected circumstances” or “hidden conditions” can protect the parties from downstream costly disputes.
- Immediately Address Changes by Following the Change Order Process, Including Obtaining Necessary Signatures.
Regardless if you are an owner, general contractor or subcontractor, you should address any proposed change order immediately. Even if a decision maker gives “verbal” approval to go ahead with changed work, the work should not proceed without following the change order process in the original contract. This includes making sure to obtain any necessary signatures for the change order, if at all possible.
- Analyze the Plans and Specifications to Determine Whether “Changes” are Within the Scope of the Original Contract, or Whether They are Extra Work.
Prior to entering an original contract, it is imperative that the parties review the plans and specifications for ambiguities regarding work included in the original contract, versus potential extra work that would require a change order. This is important because a careful review of the plans and specifications sometimes reveals that work believed to be a change order is, in fact, original work, or vice versa.
- Make Sure Requests and Approvals for Change Orders are Done by an Authorized Representative.
When a party requests or gives its approval to a change order, it is important to confirm the request or approval came from an authorized representative.
- Avoid Vague and Open-Ended Change Orders.
Indeed, the vaguer a change order, the more likely it can lead to a dispute. Vague and open-ended change orders, including change orders that provide for payment on a time and materials basis, can be difficult for an owner to budget and schedule. This can lead to disputes as to cost and/or time extensions.
- Oral Assurances for Payment Without a Signed Change Order May Not Be Recoverable.
When a party provides verbal assurances to another party for extra work without following the change order process, there is a much higher likelihood that disputes will occur. Although there is case law that may allow a contractor to recover for extra work in private contracts based on oral promises, the parties should avoid placing themselves in such a legal position. Notably, in public contracts, a contractor may not be able to recover for any extra work without a signed changed order, even with verbal assurances of payment from the owner.
About the Author:
John E. Bowerbank, Newmeyer & Dillion
Mr. Bowerbank is a partner in the Newport Beach office and practices in the areas of business, insurance, real estate, and construction litigation. You can reach John at john.bowerbank@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Arizona – New Discovery Rules
May 16, 2018 —
John Belanger - Bremer Whyte Brown & O'Meara LLPEffective July 1, 2018
New Rules of Civil Procedure are taking effect in Arizona on July 1, 2018. The new Rules will change how discovery works in civil litigation in the state. Here is a sneak peek at the changes that will impact your file handling the most:
Tiered Discovery
- How much discovery is allowed in a case will now depend on the amount and type of relief sought
- Cases will be assigned to one of three tiers
- Parties can agree on a tier assignment, the court can assign a tier, or a tier can be assigned based on the amount of damages, or a combination of monetary and non-monetary damages
Read the court decisionRead the full story...Reprinted courtesy of
John Belanger, Bremer Whyte Brown & O'Meara LLPMr. Belanger may be contacted at
jbelanger@bremerwhyte.com
Consumer Prices Rising as U.S. Housing Stabilizes: Economy
June 18, 2014 —
Jeanna Smialek and Shobhana Chandra – BloombergConsumer prices rose in May by the most in more than a year, showing U.S. companies are gaining some pricing power as the economy strengthens, and the homebuilding industry stabilized after a first-quarter swoon.
The cost of living increased 0.4 percent, the biggest advance since February 2013, according to Labor Department data released today in Washington. Other figures showed builders broke ground on 1 million homes at an annualized rate after 1.07 million in April, the best two-month reading since late 2013.
The reports will be welcome news to Federal Reserve policy makers meeting today and tomorrow as the pickup in inflation lessens the threat of a prolonged drop in prices that hurts economic growth. Central bankers are projected to continue scaling back their bond-buying program, while an increase in interest rates is delayed until well into 2015.
Ms. Smialek may be contacted at jsmialek1@bloomberg.net; Ms. Chandra may be contacted at schandra1@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Jeanna Smialek and Shobhana Chandra, Bloomberg
North Carolina Court Rules In Favor Of All Sums
July 13, 2020 —
Lorelie S. Masters & Patrick M. McDermott - Hunton Andrews KurthA North Carolina court recently ruled in favor of all sums allocation. Duke Energy Carolinas, LLC v. AG Insurance SA/NV, No. 17 CVS 5594 (N.C. Sup. Ct.). In that case, Duke Energy is seeking coverage for “liabilities linked to coal combustion residuals (‘CCRs’), i.e., coal ash, at fifteen Duke-owned power plants in North and South Carolina.” In a recent summary judgment decision, the court resolved a dispute between Duke and TIG Insurance Company, as successor to Ranger Insurance Company, about whether all sums allocation or pro rata allocation applied.
The court found that “the non-cumulation provisions make plain” that all sums allocation applied. It also noted that “a large majority of the courts in other jurisdictions that have considered this issue have recognized that non-cumulation provisions such as those here compel all sums rather than pro rata allocation.” The decisions to the contrary, according to the court, had ruled “done so on public policy grounds” and not based on “the application of the rules of contract interpretation.”
Reprinted courtesy of
Lorelie S. Masters, Hunton Andrews Kurth and
Patrick M. McDermott, Hunton Andrews Kurth
Ms. Masters may be contacted at lmasters@HuntonAK.com
Mr. McDermott may be contacted at pmcdermott@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Vinny Testaverde Alleges $5 Million Mansion Riddled with Defects
January 15, 2014 —
Melissa Zaya-CDJ STAFFFormer Tampa Bay Buccaneers quarterback Vinny Testaverde and his wife Mitzi filed suit December 20, 2013 claiming breach of contract and building code violations on their $5 million, Odessa, Florida mansion, according to the Tampa Tribune. The Testaverdes allege that their six-year old, 6,700 square foot home has multiple defects, including “wet floors and walls when it rains and a grand staircase leading to the front door that is sinking, taking with it two columns that support the porch roof,” The Tampa Tribune reports.
Gray Homes of Tampa Bay were contracted by the couple to build their mansion on Lake Keystone. The Tampa Tribune stated that several months before filing suit, the Testaverdes sent a certified letter to Gray Homes stating they had uncovered “a series of defects.” According to the article, Gray Homes had not yet responded to the Tampa Tribune’s message asking for a comment.
Read the court decisionRead the full story...Reprinted courtesy of
Precedent-Setting ‘Green’ Apartments in Kansas City
September 17, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to the Kansas City Star, the Missouri riverfront apartment development, Second and Delaware, is being constructed with “greener-than-green technology” and features the following: “Sixteen-inch-thick concrete walls. Rooftop gardens. A 90 percent reduction in energy use compared to current building codes.”
The two buildings “will comprise the largest U.S. multifamily apartment project using Passive House Institute-certified construction, a system that’s more energy-efficient than the highest LEED (Leadership in Energy and Environmental Design) building standard.”
Read the court decisionRead the full story...Reprinted courtesy of
Arizona Court of Appeals Decision in $8.475 Million Construction Defect Class Action Suit
May 09, 2011 —
CDJ STAFFIn the case of Leflet v. Fire (Ariz. App., 2011), which involved an $8.475 million settlement in a construction defect class action suit, the question put forth to the Appeals court was “whether an insured and an insurer can join in a Morris agreement that avoids the primary insurer’s obligation to pay policy limits and passes liability in excess of those limits on to other insurers.” The Appeals court provided several reasons for their decision to affirm the validity of the settlement agreement as to the Non-Participatory Insurers (NPIs) and to vacate and remand the attorney fee awards.
First, the Appeals court stated, “The settlement agreement is not a compliant Morris agreement and provides no basis for claims against the NPIs.” They conclude, “Appellants attempt to avoid the doctrinal underpinnings of Morris by arguing that ‘the cooperation clause did not prohibit Hancock from assigning its rights to anyone, including Appellants.’ This narrow reading of the cooperation clause ignores the fact that Hancock did not merely assign its rights — it assigned its rights after stipulating to an $8.475 million judgment that neither it nor its Direct Insurers could ever be liable to pay. Neither Morris nor any other case defines such conduct as actual ‘cooperation’—rather, Morris simply defines limited circumstances in which an insured is relieved of its duty to cooperate. Because Morris agreements are fraught with risk of abuse, a settlement that mimics Morris in form but does not find support in the legal and economic realities that gave rise to that decision is both unenforceable and offensive to the policy’s cooperation clause.”
The Appeals court further concluded that “even if the agreement had qualified under Morris, plaintiffs did not provide the required notice to the NPIs.” The court continued, “Because an insurer who defends under a reservation of rights is always aware of the possibility of a Morris agreement, the mere threat of Morris in the course of settlement negotiations does not constitute sufficient notice. Instead, the insurer must be made aware that it may waive its reservation of rights and provide an unqualified defense, or defend solely on coverage and reasonableness grounds against the judgment resulting from the Morris agreement. The NPIs were not given the protections of this choice before the agreement was entered, and therefore can face no liability for the resulting stipulated judgment.”
Next, the Appeals court declared that “the trial court abused its discretion in awarding attorney’s fees under A.R.S § 12-341.” The Appeals court reasoned, “In this case, the NPIs prevailed in their attack on the settlement. But the litigation did not test the merits of their coverage defenses or the reasonableness of the settlement amount. And Plaintiffs never sued the NPIs, either in their own right or as the assignees of Hancock. Rather, the NPIs intervened to test the conceptual validity of the settlement agreement (to which they were not parties) before such an action could commence. In these circumstances, though it might be appropriate to offset a fee award against some future recovery by the Plaintiff Leflet v. Fire (Ariz. App., 2011) class, the purposes of A.R.S. § 12-341.01 would not be served by an award of fees against them jointly and severally. We therefore conclude that the trial court abused its discretion in awarding fees against Plaintiffs ‘jointly and severally.’”
The Appeals court made the following conclusion: “we affirm the judgment of the trial court concerning the validity of the settlement agreement as to the NPIs. We vacate and remand the award of attorney’s fees. In our discretion, we decline to award the NPIs the attorney’s fees they have requested on appeal pursuant to A.R.S. § 12-341.01(A).”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Congratulations to Partner Madeline Arcellana on Her Selection as a Top Rank Attorney in Nevada!
July 02, 2024 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is proud to announce that Las Vegas Partner
Madeline Arcellana was once again selected by Nevada Business Magazine as a Top Rank Attorney in Nevada for her work in Civil Litigation, General Liability, and Personal Injury!
Nevada Business Magazine‘s Top Rank Attorneys list is comprised of attorneys in both private and public practice who are voted for by nearly 3,000 Nevada-licensed attorneys.
The attorneys on this list are at the top of their field and each nomination is put through an extensive verification process. To view Nevada’s 2024 Top Rank Attorneys, please click
here.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP