After the Fire, Should Some Parts of Los Angeles Never Rebuild?
January 28, 2025 —
Akshat Rathi - BloombergThe fires in and around Los Angeles are coming under control. The city’s mayor has already issued an executive order to speed up rebuilding. But equally catastrophic blazes are likely to strike again on a hotter planet, raising the question of whether some parts of the region should still be considered livable.
It’s not an unthinkable notion. There have been a handful of attempts at systematically moving populations away from regions severely affected by climate change. This kind of “managed retreat” has typically been applied to risks from rising sea levels, with recent programs in the US involving relocating tribal populations in Alaska and Washington.
But people affected by wildfires are only just starting to see efforts from governments to help them to move away from high-risk areas, including in LA county. A California program launched last year that offered up to $350,000 in loans to those affected by fires in 2018 and 2020 to shift to safer places fully allocated its funds within weeks.
Read the court decisionRead the full story...Reprinted courtesy of
Akshat Rathi, Bloomberg
Eleventh Circuit Reverses Attorneys’ Fee Award to Performance Bond Sureties in Dispute with Contractor arising from Claim against Subcontractor Performance Bond
February 27, 2019 —
CDJ STAFFOn October 26, 2018, the United States Court of Appeals for the Eleventh Circuit (the “Eleventh Circuit”) issued a decision which reversed an award of prevailing party attorneys’ fees to performance bond sureties in their dispute with a contractor arising from the contractor’s claim against a subcontractor’s performance bond. Had the lower court’s decision been affirmed, the performance bond sureties would have been able to recover prevailing party attorneys’ fees against the contractor even though they were not parties to the underlying subcontract and the subcontract did not contain a prevailing party attorneys’ fee provision.
The underlying case is complicated and arose from the construction of Brickell CityCentre in Miami. Americaribe-Moriarty JV (the “Contractor”) asserted a claim against a performance bond procured by a defaulted subcontractor and issued by International Fidelity Insurance Company and Allegheny Casualty Company (collectively, the “Sureties”). The Sureties filed a declaratory judgment action against the Contractor in the United States District Court for the Southern District of Florida (the “District Court”), seeking a declaration that the Contractor failed to perfect its claim against the performance bond.
Reprinted courtesy of
Gary M. Stein, Peckar & Abramson and
K. Stefan Chin, Peckar & Abramson
Mr. Stein may be contacted at gstein@pecklaw.com
Mr. Chin may be contacted at kschin@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
With VA Mechanic’s Liens Sometimes “Substantial Compliance” is Enough (but don’t count on it) [UPDATE]
October 14, 2019 —
Christopher G. Hill - Construction Law MusingsVirginia mechanic’s liens are a powerful and tricky beast that in most cases require absolute precision in their preparation. However, an interesting opinion recently came out of the Virginia Supreme Court that may provide a bit of a “safe harbor” from the total form over function nature of a mechanic’s lien.
In Desai, Executrix v. A.R. Design Group Inc., the Court considered a lien memorandum that had what could be described as technical flaws in the preparation of the mechanic’s lien by A. R. Design Group. The basic facts are that A. R. Design Group used the form of lien found in Va. Code Sec. 43-5 (also found as Form CC-1512 at the Virginia Judiciary website) when it recorded two lien memoranda for two pieces of property owned by a trust. Relating to one of the two properties, the memorandum failed to identify the “Owner” as the trustee of the trust. On the memoranda relating to both properties the affidavit verifying the amounts claimed did not identify the signatory as agent for A. R. Design Group, instead listing the agent as the claimant and further failed to state a date from which interest is claimed or a date on which the debt was due.
Needless to say, the owner argued that each of these technical defects invalidated the memoranda and therefore they should have been released. Somewhat surprisingly the Fairfax, Virginia Circuit Court disagreed and held the liens to be valid. On appeal, the Virginia Supreme Court affirmed the lower court. The held that the failure to add the word “Trustee” after Ulka Desai’s name did not invalidate the lien because the trustee had all of the rights of ownership and furthermore that naming Desai in the memorandum served the purpose of putting third parties on notice of the lien.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Measure Of Damages for Breach of Construction Contract
October 18, 2021 —
David Adelstein - Florida Construction Legal UpdatesHow do you determine damages for a breach of a construction contract? If you are interested in pursing a breach of a construction contract action, this is something you NEED TO KNOW!
The recent Fourth District Court of Appeal’s decision in Cano, Inc. v. Judet, 46 Fla. L. Weekly D2083b (Fla. 4th DCA 201) explains:
Where a contractor breaches a construction contract, and the owner sues for breach of contract and the cost to complete, the measure of damages is the difference between the contract price and the reasonable cost to perform the contract. See Grossman Holdings Ltd. v. Hourihan, 414 So. 2d 1037, 1039-40 (Fla. 1982). In Grossman, the supreme court adopted subsection 346(1)(a) of the Restatement (First) of Contracts (1932), which it concluded was “designed to restore the injured party to the condition he would have been in if the contract had been performed.” Id. at 1039. In other words, the owner will obtain the benefit of his bargain [and this is known as benefit of the bargain damages]. But where there is a total breach of the contract as opposed to a partial breach, an injured party may elect to treat the contract as void and seek damages that will restore him to the position that he was in prior to entering into the contract or the party may seek the benefit of his bargain. See McCray v. Murray, 423 So. 2d 559, 561 (Fla. 1st DCA 1982).
In Judet, an owner entered into a fixed price contract with a contractor to repair damage from a lightning strike. The contract amount was $300,000 payable in $30,000 installments. A few months after the contractor commenced performance, the owner terminated the contractor because the owner learned the contractor had not obtained required electrical and plumbing permits. At this time, the owner had paid the contractor $90,000. The contractor recorded a $40,000 lien for an amount it claimed it was owed and filed a lawsuit to foreclose its construction lien. The owner counter-sued the contractor to recover a claimed over-payment and a disgorgement of monies for unpermitted work. The owner was NOT claiming benefit of the bargain damages, but rather, damages for the contractor’s total breach “to restore him to the position that he was in prior to entering into the contract.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Broker's Motion for Summary Judgment on Negligence Claim Denied
July 30, 2018 —
Tred R. Eyerly - Insurance Law HawaiiAfter being sued for negligence for failing to secure proper coverage, the broker was unsuccessful in seeking dismissal by way of summary judgment. Liverman Metal Recycling, Inc. v. Arthur J. Gallagher & Co., 2018 U.S. Dist. LEXIS 87957 (E.D. N.C. May 25, 2018).
Plaintiffs were two companies, Empire and Liverman, that processed scrap metal. They were in the process of merging under a management plan by which Empire would acquire Liverman. As part of the plan, Empire's employees were moved on to Liverman's payroll processing system. Concurrently, Liverman renewed its workmen's compensation policy. Defendant Arthur J. Gallagher & Company, an insurance broker, handled the renewal with the insurer, Bridgefield Insurance Company.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Viva La France! 2024 Summer Olympics Construction Features Sustainable Design, Including, Simply Not Building at All
August 26, 2024 —
Garret Murai - California Construction Law BlogIf you’re like me and many others you’ve probably been watching the 2024 Summer Olympics in Paris, France. We were in Paris last year and we passed the construction site of the Aquatics Centre, one of only three new permanent facilities that was constructed for this year’s Olympics. On a side note, Parisian Uber drivers are some of the most aggressive drivers I’ve seen, replete with honking, hand gestures, and cursing at other drivers and pedestrians in, of course, French. Putain!
In recent history, Olympic construction costs have skyrocketed, often vastly exceeding the planned budgets of the host cities, and, in recent years, has caused even some host city hopefuls to reconsider
whether to even throwing their hats in the ring. The 2020/2021Summer Olympics in Tokyo, for example, had an original budget of $7.5 billion. The actual cost was over $13 billion and, depending on what beans you count, may have been over twice that! Paris seeks to change all of this.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
White and Williams Earns Tier 1 Rankings from U.S. News "Best Law Firms" 2019
November 14, 2018 —
White and Williams LLPWhite and Williams has achieved national recognition from U.S. News and World Report as a "Best Law Firm" in the practice areas of Insurance Law, Media Law and Tax Law. Our Boston, New York and Philadelphia offices have also been recognized in their respective metropolitan regions in several practice areas. Firms included in the “Best Law Firms” list are recognized for professional excellence with persistently impressive ratings from clients and peers. Achieving a tiered ranking signals a unique combination of quality law practice and breadth of legal experience.
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP
Is the Sky Actually Falling (on Green Building)?
November 03, 2016 —
Christopher G. Hill – Construction Law MusingsI have spoken on many occasions here at Construction Law Musings and elsewhere about the risks and rewards for contractors found in sustainable construction. The rewards were fairly apparent. New markets, government incentives and the desires of owners to be “green” clearly point toward a need for contractors to get into the sustainable building game.
However, when I was first writing my Eeyore like thoughts most of the thoughts of all us construction attorneys were speculative. Whether because wholesale “green” construction was relatively new or because the court process was relatively slow, there were not many ways to test if our, shall we say “less optimistic,” predictions were going to come to pass.
For better or worse, several of the more dire predictions have come true. One major green construction debacle is the Destiny USA litigation. I cannot possibly set out all of the various issues as well as my friend and colleague Chris Cheatham does in his e-book about the project and its aftermath. I highly recommend this e-book and the posts found at Chris’ Green Building Law Update blog for those of you interested in how the IRS, the USGBC and the Green Bonds Program interact to cause many a pitfall for construction and design professionals.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com