The Right to Repair Act Means What it Says and Says What it Means
December 18, 2022 —
Garret Murai - California Construction Law BlogA rather short case for a short week.
In Gerlach v. K. Hovnanian’s Four Seasons at Beaumont, LLC, 82 Cal.App.5th 303 (2022), the 4th District Court of appeals examined provisions of the Right to Repair Act (Civ. Code §§895 et. seq), also known as “SB 800” after its original bill number, as it applies to roofs.
The Gerlach Case
Lynn Gerlach and Lola Seals are homeowners who purchased their homes in the Four Seasons at Beaumont adult community, for those 55 year old and older, located in Beaumont, California. Gerlach purchased her home when it was built in 2006. Seals purchased her home from the original owners in 2015.
In 2015 and 2016, Gerlach and Seals served the developer, K. Hovnanian’s Four Seasons at Beaumont, LLC, with claim notices under the Right to Repair Act. The Right to Repair Act, as its name implies, provides notice requirements and repair rights by developers of new single-family homes. The Right to Repair Act also includes construction standards, the violation of which, provides homeowners with a statutory basis for bringing construction defect claims.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Dear Engineer: Has your insurer issued a “Reservation of Rights” letter? (law note)
April 20, 2017 —
Melissa Dewey Brumback - Construction Law in North CarolinaIn my previous post, I made reference to getting a “Reservation of Rights” letter. I noted that the carrier may decide to defend you under a Reservation of Rights (i.e., hire your lawyer) but may not, necessarily, accept the responsibility for paying the claim. Does this mean that the insurance company has denied your claim, or will never pay? No.
Reservation of Rights (ROR) letters are sent for a variety of reasons- most notably, when some portion of the construction lawsuit against you is not covered under your E&O policy. The letter must state the reason(s) that the ROR is being issued.
With the ROR, the insurance company is telling you that it reserves the right to withdraw from your defense and/or deny payment of damages at a later date, depending upon how facts in the case develop. The notice is intended to let you know that there *may* be issues later, and to put you notice that you have the right to hire your own lawyer (at your own expense) to protect yourself from that future potential risk.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale Liggett PLLCMs. Brumback may be contacted at
mbrumback@rl-law.com
Georgia Federal Court Holds That Pollution Exclusion Bars Coverage Under Liability Policy for Claims Arising From Discharge of PFAS Into Waterways
December 18, 2022 —
Paul Briganti - White and WilliamsOn December 5, 2022, the U.S. District Court for the District of Georgia held that a total pollution exclusion (TPE) in a CGL policy relieved the insurer of any obligation to defend or indemnify a recycling company in a putative class action alleging PFAS contamination of Georgia waterways. See Grange Ins. Co. v. Cycle-Tex Inc., et al., Order, Civ. A. No. 4:21-cv-00147-AT (N.D. Ga. Dec. 5, 2022). The decision adds to a slowly-developing body of case law addressing coverage issues arising out of PFAS-related claims.
In Grange, the insured, Cycle-Tex, Inc., was the operator of a thermoplastics recycling facility in Dalton, Georgia. Cycle-Tex and other defendants – which included chemical suppliers, carpet manufacturers, intermediaries, the City of Dalton and the Dalton-Whitfield Solid Waste Authority – were named in a putative class action complaint alleging that residents of Dalton had been injured as a result of the defendants’ discharge of PFAS into local waterways. The complaint sought damages for: (1) alleged harm to the residents’ health by virtue of ingesting contaminated water; (2) alleged property damage resulting from the contamination of the public water supply; and (3) the payment of surcharges and heightened water rates as a result of the alleged contamination.
Read the court decisionRead the full story...Reprinted courtesy of
Paul Briganti, White and WilliamsMr. Briganti may be contacted at
brigantip@whiteandwilliams.com
Court Addresses Damages Under Homeowners Insurance Policy
January 21, 2019 —
David R. Cook, Jr. - Autry, Hall, & Cook, LLPDuring a storm, a tree landed on a homeowners house causing damage to the home’s foundation. Homeowners filed a claim on their homeowners insurance policy to recover the resulting damages. After homeowners and insurance company could not come to an agreement on value of the loss, homeowners filed a lawsuit.
Homeowners presented the testimony of a contractor as an expert witness regarding the damage and the resulting loss of value. Contractor testified that the home value was reduced in half as a direct result of the damage to the home’s foundation. Insurance company sought to exclude the contractor’s testimony, arguing he was not qualified as an expert and did not apply appropriate methodology to reach his opinions.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Jr., Autry, Hall, & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Details Matter: The Importance of Strictly Following Public Bid Statutes
September 22, 2016 —
Wally Zimolong – Supplemental ConditionsContractors bidding on public contracts know that failing to strictly following all of the technical aspects contained in the instructions to bidders can mean the difference between a winning and losing bid. In the span of two weeks, I was involved with two cases that underscored the importance of this axiom. Both cases involved New Jersey’s public bid laws. While these cases show the importance of following a specific section of New Jersey’s public bid statute, the take away – that details matter – is universal.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Cumulative Impact Claims and Definition by Certain Boards
June 21, 2024 —
David Adelstein - Florida Construction Legal UpdatesWhat is a cumulative impact claim? This is commonly referred to as the unforeseeable ripple effect of changes, i.e., the death by a thousand cuts. Cumulative impact claims refer to a disruption on productivity based on the cumulative impact of changes and their impact on unchanged work. Cumulative impact claims are difficult claims to prove, particularly based on the causation standpoint (and argument they could be released based on change order language). If pursuing or considering a cumulative impact claim, you will need to work with a consultant(s) and lawyer that understand the dynamic of these claims to best maximize your arguments and recovery from a causation and damages standpoint. Cumulative impact damages are real. They occur. But they are not damages you can just throw out there or use loosely and expect to develop traction on compensation.
Below is how cumulative impact claims are defined by certain Boards of Contract Appeals. The definitions are important.
In Appeal of Centex Bateson Construction, Co., Inc., 9901 BCA P 30153, VABCA 4613 (VABCA 1998), the Board explained:
Direct impact, as the immediate and direct effect of a change on unchanged work, is considered foreseeable.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Determining Occurrence for Injury Under Commercial General Liability Policy Without Applying “Trigger Theory”
July 19, 2021 —
David Adelstein - Florida Construction Legal UpdatesOftentimes an occurrence in a commercial general liability policy is defined as “an accident, including continuous or repeated exposure to substantially the same general harmful conditions.” It is this occurrence that causes the bodily injury or property damage that may be covered by the policy.
An interesting non-construction case determined an occurrence under a commercial general liability policy occurred when the negligent act occurred irrespective of the date of discovery or the date the claim was discovered or asserted. See Certain Underwriters at Lloyd’s, London Subscribing to Policy No. J046137 v. Pierson, 46 Fla.L.Weekly D1288c (Fla. 4thDCA 2021). This is interesting because the appellate court did NOT apply a “trigger theory” to first determine the occurrence’s policy period. The appellate court found it did not need to determine which “trigger theory” applied to determine the occurrence for the injury and relied on a cited case: “trigger theories are generally used in the context of deciding when damage occurred ‘in cases involving progressive damages, such as latent defects, toxic spills, and asbestosis’ because the time between the ‘injury-causing event (such as defective construction, a fuel leak, or exposure to asbestos), the injury itself, and the injury’s discovery or manifestation can be so far apart.” Pierson, supra, citing and quoting Spartan Petroleum Co. v. Federated Mut. Ins. Co., 162 F.3d 805, 808 (4th Cir. 1998).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Price Escalation Impacts
August 22, 2022 —
Denise Motta - Gordon & Rees Construction Law BlogThis Bulletin provides guidance to contractors, subcontractors, suppliers, and others to ensure compliance with contractual change order requirements in the event work on a construction project is impacted by price escalation.
Construction projects are being impacted by increased costs for most construction materials. The Producer Price Index shows a 69% increase in the cost of construction materials from March 2020 to March 2022. Many construction contracts do not address escalation or specifically exclude change orders for material escalation, leaving the risk of escalation of construction materials with the contractor, subcontractor, or suppliers.
Bid Protection Tips:
- Keep bids open for less than 30 days with a designated sunset date:
- Keeping your bids open for less than 30 days can help protect you from sudden changes in pricing and help maintain your bids’ competitive status.
- If asked to extend time a bid is open, reconfirm prices before agreeing.
Read the court decisionRead the full story...Reprinted courtesy of
Denise Motta, Gordon Rees Scully Mansukhani, LLPMs. Motta may be contacted at
dmotta@grsm.com