Fire Consultants Cannot Base Opinions on Speculation
May 20, 2019 —
Christopher Konzelmann - The Subrogation StrategistLarsen v. 401 Main St. Inc., 302 Neb. 454 (2019), involved a fire originating in the basement of the Quart House Pub (Pub) in Plattsmouth, Nebraska that spread to and damaged Plattsmouth Chiropractic Center, Inc., a neighboring business. Fire investigators could not enter the building because the structure was unsafe and demolished. The chiropractic center nevertheless sued the Pub alleging that its failure to maintain and replace basement mechanical equipment caused ignition.
To prove its claim, the plaintiff retained a mechanical engineer who reviewed documents and concluded that the fire “originated from a failure of one of the items of mechanical equipment located in the area of the [basement] boiler.” Importantly, however, the consultant could not determine the root cause of the fire, could not eliminate the possibility that the fire originated in a compressor, and could not rule out the building’s electrical service as the ignition source because it was outside his area of expertise. The consultant nevertheless found that the fire most likely would not have occurred if the Pub had regularly serviced and replaced the equipment when needed.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher Konzelmann, White and Williams LLPMr. Konzelmann may be contacted at
konzelmannc@whiteandwilliams.com
AI-Powered Construction Optioneering Today
April 08, 2024 —
Aarni Heiskanen - AEC BusinessIn this episode of the AEC Business Podcast, Aarni Heiskanen interviews René Morkos, the founder and CEO of ALICE Technologies. They discuss construction tech, AI, and ALICE Core, the company’s latest product launch.
How the Construction Technology Landscape has Changed
The construction tech industry has evolved significantly since 2015, as discussed with René.
In 2015, there was a lack of understanding and reluctance toward construction tech, with some investors even hesitant to invest in the sector. However, by 2017-2018, there was a noticeable shift as construction tech became a sought-after investment opportunity.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
BOOK CLUB SERIES: Everything You Want to Know About Construction Arbitration But Were Afraid to Ask
October 30, 2023 —
Marissa L. Downs - The Dispute ResolverI recently had the pleasure of speaking with construction law notables John Foust and Andy Ness to discuss the release of their new book—
Construction Arbitration: The Advocate’s Practical Guide. The goal of their book: to teach attorneys what they need to know to maximize their effectiveness in the arbitration context. To that end, the book covers every aspect of the arbitration process including motion practice, conduct as an advocate, presentation of the case, and post-hearing submissions. Read on for Andy and John’s candid, behind-the-scenes take on how this book came to be and why you should get your copy now, while supplies last!
Q: Who is the target audience for this book?
Andy: In the editing process (and in writing my own chapter on Navigating an International Construction Arbitration) I pretended that I was speaking with a construction lawyer who was a few years out of law school, with some litigation experience, who was getting ready to take on a significant and complex construction arbitration for the first time. The book presupposes knowledge of the basics and tries to anticipate the questions that would be asked when you are trying to think through the whole arbitration process from start to finish. What should my pleadings look like? How much discovery am I likely to be able to obtain? How should my demeanor be different from what I would do in a courtroom? How much should I object during the hearing? In a nutshell, it’s “What do I need to know to maximize my chances of success in the arbitration setting?”
Read the court decisionRead the full story...Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLPMs. Downs may be contacted at
mdowns@lauriebrennan.com
World-Famous Architects Design $480,000 Gazebos for Your Backyard
December 10, 2015 —
Katya Kazakina – BloombergStar architects known for dreaming up museums, concert halls, and stadiums are aiming to bring high design into a much more pedestrian segment: prefabricated, mixed-use structures.
If you don't want to spring for one of Zaha Hadid's $50 million penthouses, you can now have your own outdoor dining pavilion by the Pritzker Prize winner. Price tag: $480,000.
Made with wood, stainless steel, and aluminum, the curvy piece comprises a platform and a sprawling, perforated canopy, resembling a giant mushroom straight out of Alice in Wonderland. (This is a Hadid, after all.) It will be made in an edition of 24.
Read the court decisionRead the full story...Reprinted courtesy of
Katya Kazakina, Bloomberg
Judge Tells DOL to Cork its Pistol as New Overtime Rule is Blocked
November 23, 2016 —
Evelin Y. Bailey – California Construction Law BlogEarlier this year we informed you that the federal Department of Labor intended to raise the minimum salary for individuals classified as executive, administrative, and professional (“white collar”) exempt employees. The result? About 4.2 million workers classified as exempt would become eligible for overtime pay on December 1, 2016, the effective date of the new rule. Businesses would need to pay $47,476 starting on December 1, 2016 to maintain the exempt status of workers.
However, a combination of business groups and states sued to invalidate the regulation, requesting expedited and emergency injunctive relief.
On November 22, 2016, a federal district court in Texas granted the emergency motion for a preliminary injunction barring the DOL from enforcing its new overtime rule. The injunction will remain until the resolution of this legal challenge to the rule.
Read the court decisionRead the full story...Reprinted courtesy of
Evelin Y. Bailey, California Construction Law BlogMs. Bailey may be contacted at
ebailey@wendel.com
California Court of Appeal Provides Clarity On What Triggers Supplemental Analysis Under California Environmental Quality Act
July 20, 2020 —
Kelly Alhadeff-Black & Alexander N. Knaub - Lewis BrisboisIn a recent ruling, California’s Sixth District Court of Appeal clarified the need for supplemental environmental analysis under the California Environmental Quality Act (CEQA). Willow Glen Trestle Conservancy v. City of San Jose (6th Dist., May 18, 2020). Specifically, the court held that seeking additional discretionary approvals, such as regulatory permits, does not constitute a “new discretionary approval for the project” under the California Public Resources Code Section 21166 and the California Code of Regulations, title 14, section 15162 (the CEQA Guidelines).
In 2014, the City of San Jose approved a project that included the demolition and replacement of a wooden railroad bridge known as the Willow Glen Trestle (the Project). CEQA review for the Project was conducted via mitigated negative declaration (MND). The Project was quickly challenged by a local group called Friends of the Willow Glen Trestle, alleging that the City should have prepared an Environmental Impact Report based on the allegation that the Willow Glen Trestle constituted an historic resource for CEQA purposes. Ultimately, the City prevailed in that litigation (See Friends of the Willow Glen Trestle v. City of San Jose, et al. (6th Dist., 2016), which remanded the case to the trial court for further review consistent with the Court of Appeal’s verdict) with the court eventually finding that the City correctly analyzed and answered the question of historic resource classification and significance in reference to the Willow Glen Trestle.
Reprinted courtesy of
Kelly Alhadeff-Black, Lewis Brisbois and
Alexander N. Knaub, Lewis Brisbois
Ms. Alhadeff-Black may be contacted at Kelly.Black@lewisbrisbois.com
Mr. Knaub may be contacted at Alexander.Knaub@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Living Not So Large: The sprawl of television shows about very small houses
March 12, 2015 —
S Jhoanna Robledo – BloombergVince and Sam are newlywed twentysomethings who’ve been bunking with family for a year. Finally, they’ve saved up enough to buy a palace to call their own. Well, sort of: They want to shrink their footprint and expenses by living in a custom-built, 204-square-foot standalone house in southern New Jersey. It has to have room for gym equipment—they’re fitness buffs—and a study for Sam, who’s in medical school. Even Vince’s adorably headbanded mom isn’t sure how it will all fit. When Vince and Sam first see their new digs under construction, tall and narrow like a top-heavy garage, Vince admits they’re “freaking out on the inside.”
So goes a standard episode of Tiny House Nation, the first of a half-dozen miniaturized real estate shows that have recently premiered. “We discovered that for millennials, there was an overriding social trend of extreme downsizing, and we wanted to dig deep into that,” says Gena McCarthy, executive producer of the show, which began airing last year after the Biography Channel morphed into the youth-focused FYI network. Last summer’s first season averaged 257,000 viewers per week, according to Nielsen; this season’s average viewership is up 77 percent, to 465,000.
Read the court decisionRead the full story...Reprinted courtesy of
S Jhoanna Robledo, Bloomberg
Tennessee Court of Appeals Holds Defendant Has the Burden of Offering Alternative Measure of Damages to Prove that Plaintiff’s Measure of Damages is Unreasonable
July 18, 2018 —
Gus Sara - The Subrogation StrategistIn Durkin v. MTown Construction, LLC, 2018 Tenn. App. LEXIS 128, the Court of Appeals of Tennessee considered whether the lower court properly took judicial notice of an alternative measure of damages to the measure of damages advanced by the plaintiff. The Court of Appeals held that the defendant has the burden of offering evidence of alternative measures of damages if it seeks to argue that the plaintiff’s measure of the damages is unreasonable. The Court of Appeals found that the lower court erred in taking judicial notice of alternative measures of damage when the defendant failed to meet its burden of proof. The court’s holding establishes that, if the defendant does not offer evidence of alternative measures of damage, then the measure of damages introduced by the plaintiff will apply.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and Williams LLPMr. Sara may be contacted at
sarag@whiteandwilliams.com