Indemnity: What You Don’t Know Can Hurt You!
September 19, 2022 —
Caitlin Kicklighter & Bill Shaughnessy - ConsensusDocsRisk allocation between the parties is a critical component of any construction contract. Indemnity obligations can be some of the important risk-shifting provisions of any design or construction contract. Indemnity provisions typically require one party, the Indemnitor, to agree to “hold harmless,” and/or reimburse another party, the indemnitee, from claims and liability arising out of the party’s work. Considering the financial consequences that an indemnity provision can have on a construction project, it is critical that all parties to a construction contract know the legal implications of the contract indemnity provisions and understand any limitations in enforcing the indemnity provisions depending on the controlling jurisdiction. While most indemnity clauses and obligations are enforceable, many states have enacted anti-indemnity statutes prohibiting or restricting specific indemnification provisions. These anti-indemnity statutes afford protection to contractors and subcontractors not generally in a position to protect themselves from overly extensive indemnity obligations.
This article highlights several examples of indemnity provisions typically seen in construction contracts, the measures are taken by a growing number of states to protect parties with less bargaining power in the form of anti-indemnity statutes, and offers practical considerations when negotiating or drafting indemnity provisions.
[1]
Reprinted courtesy of
Caitlin Kicklighter, Emory Law Student (2024 Graduate), (ConsensusDocs) and
Bill Shaughnessy, Jones Walker LLP (ConsensusDocs)
Mr. Shaughnessy may be contacted at bshaughnessy@joneswalker.com
Read the court decisionRead the full story...Reprinted courtesy of
First Circuit: No Coverage, No Duty to Investigate Alleged Loss Prior to Policy Period
May 18, 2020 —
Eric B. Hermanson & Austin D. Moody - White and WilliamsOn April 1, 2020, the First Circuit, applying Massachusetts law, issued a potentially useful decision addressing the Montrose “known loss” language in ISO Form CGL policies. In Clarendon National Insurance Company v. Philadelphia Indemnity Insurance Company,[1] the court applied this language to allow denial of defense for claims of recurring water infiltration that began before the insurer’s policy period, and it found an insurer had no duty to investigate whether the course of property damage might have been interrupted, or whether other property damage might have occurred during the policy period, so as to trigger coverage during a later policy.
In the underlying dispute, a condominium owner (Doherty) asserted negligence claims against her association’s property management company (Lundgren) stemming from alleged water infiltration into her condominium. The complaint said leaks developed in 2004 in the roof above Doherty’s unit, and repairs were not made in a timely or appropriate manner. The following year, the complaint said, a Lundgren employee notified Doherty that the threshold leading to her condominium's deck was rotting. In February 2006, Doherty discovered a mushroom and water infiltration on the threshold and notified Lundgren. At that time, Lundgren asked its maintenance and repair contractor (CBD) to replace the rotting threshold. According to the complaint, CBD did not do this repair in a timely manner and left debris exposed in Doherty’s bedroom.
In March 2006, the complaint said, a mold testing company hired by Lundgren found hazardous mold in Doherty's unit, caused by water intrusions and chronic dampness. Lundgren’s attempts at remediation were ineffectual. In September 2008, Doherty's doctor ordered her to leave the condominium and not to return until the leaks were repaired and mold was eliminated.
Reprinted courtesy of
Eric B. Hermanson, White and Williams and
Austin D. Moody, White and Williams
Mr. Hermanson may be contacted at hermansone@whiteandwilliams.com
Mr. Moody may be contacted at moodya@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
BWB&O Expands to North San Diego
December 09, 2019 —
Bremer Whyte Brown & O’MearaBremer Whyte Brown & O’Meara is excited to announce our expansion to North San Diego County. Our new office location in Encinitas is strategically located between our Newport Beach and Downtown San Diego offices. The new North San Diego office will provide further resources to better serve our clients.
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O’Meara
City and Contractor Disclaim Responsibility for Construction Error that Lead to Blast
November 13, 2013 —
CDJ STAFFThe city of Grand Junction, Colorado and their contractor, Aperion Utility Construction, LLC, have both denied any wrongdoing in the construction accident that lead to the destruction of two homes. Aperion was drilling in order to repair traffic signals. Their drill damaged a gas line. In the subsequent explosion, three people were injured and two homes destroyed. Homes for 10 blocks were subsequently evacuated.
The three men who were injured have filed a lawsuit claiming negligence on the part of the contractor and the city. The city has released a report from their insurers that concluded that the city was not responsible.
Read the court decisionRead the full story...Reprinted courtesy of
WATCH: 2023 Construction Economic Update and Forecast
January 09, 2023 —
Construction ExecutiveConstruction Executive presented its "2023 Construction Economic Update and Forecast" webinar with
Associated Builders and Contractors Chief Economist Anirban Basu on Dec. 14, sponsored by
Aerotek,
Bluebeam,
CMiC and
Raken.
Basu started by announcing the Federal Reserve’s rate increase of 0.5%, the latest in a series of increases aimed at combating inflation. Calling 2022 a “year of tumult and a year of surprise,” Basu further noted that the Russian invasion of Ukraine surprised many, further disrupting global supply chains and causing a shockwave to ripple through global energy prices.
Citing the U.S. Consumer Price Index, with 7.1% year-over-year inflation in November, Basu believes we’ve “peaked in terms of inflation for this cycle”; while inflation hit higher-than-expected levels throughout 2022, it leveled off at lower-than-expected rates by the end of the year. Basu predicted inflation will continue to be problematic through 2023 as it has shifted from transitory inflation due to supply-chain disruptions in 2020 and 2022 to broader inflation due to the labor market, noting that the worst of the supply-chain issues seem to be over, reaching a high point in late 2021.
Blaming the injection of fiscal stimulus coming from the federal government, monetary stimulus from the Federal Reserve and the fact that inflation has now become ingrained in the economy and in people’s expectations, leading to wage and price increases, Basu calls the economy “overheated.”
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Fires, Hurricanes, Dangerous Heat: The US Is Reeling From a String of Disasters
August 22, 2023 —
Will Wade & Brian K Sullivan - BloombergFrom deadly wildfires to floods, the US is reeling from several natural disasters in quick succession — and more are likely on the way.
Torrential rains from the remnants of Hurricane Hilary are inundating parts of California. Two tropical storms, one post-tropical cyclone and two potential storms are lined up in the Atlantic Ocean. Almost 100 wildfires are burning across 15 states as officials in Hawaii investigate the deadliest US blaze in more than a century. And record heat will test Midwest power grids this week.
All of this, all at once, is a lot — and it’s not just bad luck. Climate change has triggered heat waves around the world, leading to ideal fire conditions in forests across the Northwest and Canada. It’s also boosting Atlantic water temperatures, which can intensify storms as the peak of hurricane season approaches. And unusually warm Pacific Ocean waters fueled Hilary, which in turn will contribute to scorching heat in the Midwest.
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg
Uniform Rules Governing New York’s Supreme and County Courts Get An Overhaul
February 08, 2021 —
Andrew I. Hamelsky, Jenifer A. Scarcella & Monica Doss - White and Williams LLPBy Administrative Order effective February 1, 2021, New York’s Uniform Civil Rules for the Supreme Court will incorporate a number of changes to the general part that reflect many of New York’s Commercial Division Rules, in an effort to streamline court processes. The general part rule changes are a step forward for improving the efficiency, modernization and cost-effectiveness of the New York Courts, and will require practitioners to be more conscientious of court appearances and deadlines. Judges will likely be strict on adherence to the new Uniform Rules. Some notable changes to the rules are highlighted below.
Court Appearances and Scheduling Orders
Uniform Rule 202.1 has been revised to require that counsel who appear before the court must be familiar with the case they are appearing for, and be fully prepared and authorized to discuss and resolve the issues that are the subject of the appearance.
Reprinted courtesy of
Andrew I. Hamelsky, White and Williams LLP,
Jenifer A. Scarcella, White and Williams LLP and
Monica Doss, White and Williams LLP
Mr. Hamelsky may be contacted at hamelskya@whiteandwilliams.com
Ms. Scarcella may be contacted at scarcellaj@whiteandwilliams.com
Ms. Doss may be contacted at dossm@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
The Clock is Ticking: Construction Delays and Liquidated Damages
September 18, 2023 —
Tiffany Harrod - ConsensusDocsWith the on-going shortage of construction workers in the industry and other factors ranging from weather to procurement problems, the threat of project delay is real. When a contract contains a liquidated damages clause for assessing project delays, real financial consequences for contractors can result. Courts have long allowed parties to apportion contractual risks as they deem appropriate especially in the commercial context where the parties are considered to be sophisticated even if their bargaining power is not equal. Liquidated damage provisions such as those for delay that are found in construction contracts are not unusual but they must be crafted in such a way as to be enforceable and not violate public policy.
A liquidated damage clause in a construction contract is a customary way for the parties to deal with the possibility of delay in the completion of a project and the potential losses flowing from the delay.[
1] In their most basic form, the party in breach, which is more often than not the contractor, is obligated to pay the non-breaching party, usually the project owner, some fixed sum of money for the period that exceeds the designated completion date that was agreed upon in advance and memorialized in the contract. (It is after all no secret that these provisions are primarily for the owner’s benefit.) The non-breaching party is then compensated for losses associated with the delay without the time and expense of having to prove in either a civil suit or an arbitration proceeding what the actual damages are. This option is particularly attractive to project owners because the liquidated damages assessment can simply be withheld from payments owed to the contractor once the agreed-upon completion date has been passed.
Read the court decisionRead the full story...Reprinted courtesy of
Tiffany Harrod, Peckar & AbramsonMs. Harrod may be contacted at
tharrod@pecklaw.com