Recent Opinions Clarify Enforceability of Pay-if-Paid Provisions in Construction Contracts
May 29, 2023 —
Patrick McKnight - The Dispute ResolverSeveral recent opinions and legislative actions have brought the controversial nature of pay-if-paid provisions into focus in early 2023. Pay-if-paid provisions are contractual mechanisms designed to shift the risk of non-payment from General Contractors to lower-tier subcontractors. In other words, pay-if-paid provisions generally do not require payment to downstream subs until after the GC or Prime are themselves paid in-full by the owner. Recent developments reflect the differing approaches taken by courts when addressing pay-if-paid provisions, ranging broadly from prohibition to full enforceability. Other jurisdictions fall somewhere in the middle, viewing such provisions with varying amounts of skepticism on the grounds heir impact on smaller downstream subs is disproportionate and unfair.
Pay-if-paid provisions are often contrasted against “pay-when-paid” provisions. Pay-when-paid provisions may require payment within a specified duration but remove the upstream contractor’s payment in-full as a condition precedent. The brief discussion below will not explore pay-when-paid, no damage for delay provisions, or statutory prompt payment acts. Instead, this article serves as a primer on recent legal developments related to pay-if-paid provisions exclusively.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick McKnight, Fox Rothschild LLPMr. McKnight may be contacted at
pmcknight@foxrothschild.com
Examining Best Practices for Fire Protection of Critical Systems in Buildings
July 16, 2023 —
Jon Jones - Construction ExecutiveProtecting building occupants and first responders is critically important when designing and constructing commercial buildings. The National Fire Protection Association (NFPA), devoted to eliminating death, injury, property and economic loss from fire, electrical and related hazards, was formed in 1896. Shortly afterward, in 1897, the National Electrical Code (NEC) was established to standardize electrical safety for wiring, alarms and related equipment. Since the birth of these two important standardizing organizations, fire codes have been constantly modified to meet the changing safety needs of new infrastructure.
In 1996, the NEC identified key circuits for fire survivability, including emergency systems, fire pumps and fire alarms. Per the 1996 code, these circuits needed to be able to survive for one hour in case of fire. However, in the late 1990s and early 2000s, these requirements began to shift to demand two hours of survivability.
Reprinted courtesy of
Jon Jones, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Revolutionizing Buildings with Hybrid Energy Systems and Demand Response
January 08, 2024 —
Aarni Heiskanen - AEC BusinessA recent study conducted by the Finnish Building Services 2030 group explores the potential technologies and business prospects for adaptable energy systems within buildings.
Building Services 2030 is a Finnish consortium of Aalto University, Tampere University, and 14 industry partners. The consortium has defined a shared vision for the Finnish building service sector and researches topics that help reach the vision. My company is responsible for the group’s communication, so I eagerly read the research reports as they come out.
One of the new reports I found very timely is about the energy flexibility of buildings. The authors are Senior Researcher Juha Jokisalo and Professor Matti Lehtonen from Aalto University. They highlight how the contemporary energy landscape is undergoing a significant transformation.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
The Advantages of Virtual Reality in Construction
August 20, 2019 —
Spivey Lipsey - Construction ExecutiveVirtual realty provides an unparalleled spatial sense for visualization at a lower cost than full-scale replicas. Today, VR is being used heavily in preconstruction to align owner expectations and educate design team stakeholders. For those already employing BIM solutions, coordination can be made much more effective by leveraging existing design models with very little added cost.
As anyone who has tried a VR headset before can attest, the ability to accurately perceive spatial relationships in design cannot be replicated through traditional 2D media such as screens or paper. VR solutions also have the ability to iterate rapidly. These technologies are linked to BIM, providing real-time feedback as the design changes. This is in stark contrast to traditional full-scale mockups and offline renders, which are cumbersome and time-consuming to update with design changes.
Substantial benefits without a hefty price tag
Budget limitations and ROI are always a concern with emerging technology. Fortunately, VR comes cheaply with BIM production. These solutions are significantly less expensive than full-scale mockups and far more efficient when compared to longhand sequencing explanations and esoteric detailing of complex designs. Even the most elaborate VR setups are a fraction of overall construction cost, ranging from a few hundred to a few thousand dollars depending on the level of adoption.
Reprinted courtesy of
Spivey Lipsey, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
The Economic Loss Rule: From Where Does the Duty Arise?
January 24, 2022 —
Taylor Hite - Colorado Construction LitigationWhen entering a contract under Colorado law or attempting to enforce your rights when the other party breaches a contract, it is important to know and understand what rights you have and what claims you can bring or defenses you may have. One important consideration is Colorado’s version of the economic loss rule. The Colorado Supreme Court has issued several opinions clarifying the scope of the economic loss rule since it adopted the rule in 2000. The purpose of the economic loss rule is to maintain the boundary between contract law and tort law.
In Colorado, the economic loss rule provides that a party suffering only economic loss from the breach of an express or implied contractual duty may not assert a tort claim for the breach without an independent duty of care under tort law. In most instances the economic loss rule will not bar intentional tort claims. The question becomes: from where does the duty arise? Is there an independent duty in tort law? Did the duty arise solely from the contract?
Read the court decisionRead the full story...Reprinted courtesy of
Taylor Hite, Higgins, Hopkins, McLain & Roswell, LLCMs. Hite may be contacted at
Hite@hhmrlaw.com
Best Practices for Installing Networks in New Buildings
August 14, 2023 —
Patrick Chown - Construction ExecutiveA previous article, "
How to Install Networks in an Old Building," discussed the various challenges of implementing networking infrastructure in older spaces. The building layout, age of the building and use cases were the major challenges involved. New buildings provide an opportunity to incorporate state-of-the-art networking infrastructure from the ground up. Careful planning and foresight are essential to ensure optimal network performance and avoid future issues.
In new buildings, including corporate offices, multifamily residential complexes, hospitals, educational institutions and retail spaces, the potential use cases and users can vary significantly. Each of these spaces comes with its unique networking requirements. Regardless of the specific network applications, there are fundamental frameworks and best practices that can be employed to build a solid network foundation. By following these guidelines and adapting them to the specific needs of your new building, you can ensure a robust and flexible network infrastructure that accommodates ever-evolving technological demands.
Reprinted courtesy of
Patrick Chown, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
William Lyon to Acquire RSI Communities
February 22, 2018 —
Dave Suggs - CDJ STAFFAccording to the article “William Lyon Agrees to Buy RSI Communities $460 million deal plants Lyon in Texas and adds to Inland Empire land holdings” published on the website Builder, the Newport Beach home builder is purchasing the Southern California and Texas home builder. This will be Lyon Homes’ first venture in the state of Texas.
RSI Communities works within both San Antonio and Austin, Texas as well as Southern California and the Inland Empire. It was founded by Todd Palmaer, a home building expert and Ron Simon, a building products expert and Newport Beach businessman. First time home buyers have been RSI’s main target.
President and CEO of RSI, Tod Palmaer is optimistic about the acquisition “We are delighted to have our company join the William Lyon Homes organization. We have a great deal of confidence in the William Lyon Homes platform and its executive management team, and believe that its acquisition of RSI Communities will add to Lyon’s continued success in its current and new markets.”
Pat Donahue who has almost 30 years of experience in home building, will serve as President to the Inland Empire Division. John Bohnen, RSI’s present Chief Operating Officer, will be the regional president in Texas. Mr. Bohnen has previously held executive positions with numerous home builders. William Lyon’s president and CEO Mark R. Zaist is excited about adding RSI’s key players to their team, and had this to say about the purchase. “The acquisition of RSI represents our most significant acquisition since our entry into Portland and Seattle with the Polygon Northwest Homes acquisition in 2014 and furthers our strategy of building in the strongest markets in the Western U.S., while also strengthening our pipeline in Southern California, as we continue our mission of being the premier Western Regional home builder.”
Read the court decisionRead the full story...Reprinted courtesy of
Common Law Indemnification - A Primer
April 12, 2021 —
Brian F. Mark - Hurwitz & Fine, P.C.“Common law indemnification is generally available ‘in favor of one who is held responsible solely by operation of law because of his relationship to the wrongdoer.’” McCarthy v. Turner Constr., Inc., 17 N.Y.3d 369, 375 (2011), quoting Mas v. Two Bridges Assocs., 75 N.Y.2d 680, 690 (1990).
What is Common Law Indemnification and Who Can Assert it?
Indemnification, in general terms, is the right of one party to shift a loss to another and may be based upon an express contract or an implied obligation. Bellevue S. Assoc. v. HRH Constr. Corp., 78 N.Y.2d 282 (1991). Based on a separate duty owed the indemnitee by the indemnitor, common law indemnification, or implied indemnification, permits one who was compelled to pay for the wrong of another to recover from the wrongdoer the damages paid to the injured party. D’Ambrosio v. City of New York, 55 N.Y.2d 454, 460 (1982); Curreri v. Heritage Prop. Inv. Trust, Inc., 48 A.D.3d 505, 507 (2d Dept. 2008).
The premise of common law indemnification is vicarious liability, defined as “liability that a supervisory party (such as an employer) bears for the actionable conduct of a subordinate or associate (such as an employee) based on the relationship between the two parties” Black’s Law Dictionary (11th ed. 2019). Common law indemnification “reflects an inherent fairness as to which party should be held liable for indemnity.” McCarthy, 17 N.Y.3d at 375. It is a restitution concept which permits shifting the loss because, to fail to do so, would result in the unjust enrichment of one party at the expense of the other. Mas, 75 N.Y.2d at 680, 690; Kingsbrook Jewish Medical Center v. Islam, 172 A.D.3d 1342, 1343 (2d Dept. 2019).
Read the court decisionRead the full story...Reprinted courtesy of
Brian F. Mark, Hurwitz & Fine, P.C.Mr. Mark may be contacted at