Cumulative Impact Claims and Definition by Certain Boards
June 21, 2024 —
David Adelstein - Florida Construction Legal UpdatesWhat is a cumulative impact claim? This is commonly referred to as the unforeseeable ripple effect of changes, i.e., the death by a thousand cuts. Cumulative impact claims refer to a disruption on productivity based on the cumulative impact of changes and their impact on unchanged work. Cumulative impact claims are difficult claims to prove, particularly based on the causation standpoint (and argument they could be released based on change order language). If pursuing or considering a cumulative impact claim, you will need to work with a consultant(s) and lawyer that understand the dynamic of these claims to best maximize your arguments and recovery from a causation and damages standpoint. Cumulative impact damages are real. They occur. But they are not damages you can just throw out there or use loosely and expect to develop traction on compensation.
Below is how cumulative impact claims are defined by certain Boards of Contract Appeals. The definitions are important.
In Appeal of Centex Bateson Construction, Co., Inc., 9901 BCA P 30153, VABCA 4613 (VABCA 1998), the Board explained:
Direct impact, as the immediate and direct effect of a change on unchanged work, is considered foreseeable.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Old Case Teaches New Tricks
March 16, 2017 —
Angela A.L. Connor & Curtis W. Martin - Peckar & Abramson, P.C.Eight years after completion of the wharf project, Zachry and the Port of Houston continue to slug
it out in the appellate courts and continue to refi ne Texas construction law along the way. In the
latest appellate opinion, the Court of Appeals details the general contractor’s control of the means
and methods of their work without interference from a governmental entity. It also supports a
subcontractor’s use of a pass-through claim as a cost efficient way to recover damages.
By now most of us are familiar with the project and the previous decisions. Zachry sued the Port
claiming breach after the Port denied Zachry the right to continue construction using its frozen
cutoff wall. The Texas Supreme Court upheld the jury’s $20 million verdict for Zachry, ruling that
the Port’s “no damages for delay” clause would not bar Zachry’s claim in light of the Port’s active
interference with Zachry’s work. The Supreme Court then sent the case back to the Court of
Appeals to consider other arguments that the Port had made.
That led to the most recent decision. In December, 2016, the Houston Fourteenth Court of Appeals
ruled in favor of Zachry on all issues and affirmed the jury verdict. In doing so, the Court of Appeals
provides several lessons or reminders on Texas Construction law.
Reprinted courtesy of
Angela A.L. Connor, Peckar & Abramson, P.C. and
Curtis W. Martin, Peckar & Abramson, P.C.
Ms. Connor may be contacted at aconnor@pecklaw.com
Mr. Martin may be contacted at cmartin@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
California Superior Court Overrules Insurer's Demurrer on COVID-19 Claim
February 15, 2021 —
Tred R. Eyerly - Insurance Law HawaiiA Superior Court in California overruled the insurer's demurrer to the policy holder's complaint seeking business interruption coverage after government shutdown orders were issued because of the coronavirus pandemic. Goodwill Industries of Orange County, California v. Philadelphia Indemnity Ins. Co., Cal. Superior Ct., Civil No. 30-2020-01169032-CU-IC-CXC (Minute Order Jan. 28,, 2021). The minute order is here [Goodwill Decision].
The insurer demurred on the ground that the insured had not alleged sufficient facts to show "direct physical loss" under the business income, extra expenses and civil authority provisions in the policy because coronavirus and COVID-19 did not physically alter the structure.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
A Court-Side Seat: “Inholdings” Upheld, a Pecos Bill Come Due and Agency Actions Abound
January 25, 2021 —
Anthony B. Cavender - Gravel2GavelHere are some significant environmental and regulatory rulings and administrative actions from December 2020.
THE U.S. SUPREME COURT
Texas v. New Mexico
On December 14, 2020, the U.S. Supreme Court decided a water rights controversy involving sharing the water of the Pecos River. The 1949 Pecos River Compact provides for the equitable apportionment of the use of the Pecos River’s water by New Mexico and Texas, and a “River Master’s Manual,” approved by the Court in 1988, implements the Compact. These are very dry areas, and access to this water is very important. In 2014, a rare tropical storm drenched the Pecos River Basin, and Texas asked New Mexico to temporarily store the water that would otherwise flow into Texas. A few months later, New Mexico released the water to Texas, but the quantity was reduced because some of the water held by New Mexico had evaporated. The River Master awarded a delivery credit to New Mexico, and after Texas objected, Texas “in response” filed the Original Jurisdiction of the Court, suing New Mexico and seeking a review of the River Master’s determination. The Court held for New Mexico, deciding that this dispute was subject to and resolved by the Manual. This case is important because it highlights the high value the states place on the equitable apportionment of water that flows through different states.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Surfside Condo Collapse Investigators Have Nearly Finished Technical Work
March 11, 2024 —
James Leggate - Engineering News-RecordNewly analyzed evidence in the investigation into the June 2021 partial collapse of Champlain Towers South that killed 98 people in Surfside, Fla., shows that the pool deck collapsed more than four minutes before the tower itself. But investigators are still working to determine the initiating event, and aim to finish their technical work this summer.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Stair Collapse Points to Need for Structural Inspections
November 27, 2013 —
CDJ STAFFThe exterior stairways at the Nutmeg Woods apartments in New London, Connecticut have lead to injuries three times in the last three years, with the most recent failure causing fatal injuries. Despite the annual injuries, the city has not been inspecting the stairways on an annual basis. Calvin Darrow, New London’s fire marshal, told The Day, a New London newspaper, that these inspections are supposed to occur annually, but tend to come about once every five years. Mr. Darrow ascribed the matter to staffing issues.
The stairways have now received a preliminary inspection by a structural engineer, and building and fire officials. Kirk Kripas told the paper that the Building Department was still attempting to determine when the stairs were built.
Read the court decisionRead the full story...Reprinted courtesy of
New York's Highest Court Says Asbestos Causation Requires Evidence Of Sufficient Exposure To Sustain Liability
May 10, 2022 —
Rafael Vergara & Jhonattan N. Gonzalez - White and WilliamsOn April 26, 2022, the New York Court of Appeals described that in toxic tort cases a plaintiff can only establish liability-creating causation for an adverse health effect with “expert testimony based on generally accepted methodologies.” See
Francis Nemeth v. Brenntag North America (N.Y. Apr. 26, 2022). The suit involved alleged asbestos exposure from talc.
The plaintiff alleged liability for talc contaminated with asbestos that was ultimately used in a commercial talcum powder, Desert Flower, which the decedent applied daily from 1960 to 1971. At trial, the plaintiff proffered two expert witnesses, a geologist, Sean Fitzgerald, who testified about the “glove box test” and a doctor of internal medicine, Dr. Jacqueline Moline. Fitzgerald’s glove box test consisted of agitating a sample of Desert Flower in a Plexiglas chamber. Fitzgerald concluded that the asbestos fibers in the sample of Desert Flower were “significantly releasable” and that the decedent was exposed to thousands to trillions of fibers through repeated use. Dr. Moline concluded Desert Flower was “a substantial contributing factor” to the decedent’s peritoneal mesothelioma. The jury returned a verdict in the plaintiff’s favor.
Reprinted courtesy of
Rafael Vergara, White and Williams and
Jhonattan N. Gonzalez, White and Williams
Mr. Vergara may be contacted at vergarar@whiteandwilliams.com
Mr. Gonzalez may be contacted at gonzalezj@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Boston Team Obtains Complete Defense Verdict for Engineering Firm in Professional Liability Matter
June 08, 2020 —
Kenneth Walton & Oliver Vega - Lewis BrisboisBoston, Mass. (June 5, 2020) - Boston Partner Kenneth B. Walton and Associate Oliver J. Vega recently obtained a complete defense verdict after a 10-day bench trial in the U.S District Court for the District of South Carolina. The plaintiff in this matter, who is the owner of a newly acquired food processing facility, alleged breach of contract and breach of fiduciary duty claims against our client, a Massachusetts engineering firm, arising out of allegedly defective design and construction management services provided during the renovation of and addition to said facility.
Reprinted courtesy of
Kenneth Walton, Lewis Brisbois and
Oliver Vega, Lewis Brisbois
Mr. Walton may be contacted at Ken.Walton@lewisbrisbois.com
Mr. Vega may be contacted at Oliver.Vega@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of