Construction Costs Must Be Reasonable
May 17, 2021 —
David Adelstein - Florida Construction Legal UpdatesWhen it comes to proving a construction cost, particularly a cost in dispute, the cost must be REASONABLE. Costs subject to claims must be reasonably incurred and the party incurring the costs must show the costs are reasonable.
An example of the burden falling on the contractor to prove the reasonableness of costs is found in government contracting.
“[T]here is no presumption that a [government] contractor is entitled to reimbursement ‘simply because it incurred…costs.’” Kellogg Brown & Root Services, Inc. v. Secretary of Army, 973 F.3d 1366, 1371 (Fed. Cir. 2020) (citation omitted). Stated differently, a federal contractor is not entitled to a presumption of reasonableness just because it incurs costs. Id.
In government contracting, the Federal Acquisition Regulations (known as “FAR”) puts the burden of reasonableness on the contractor that incurred the costs. Id.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Save a Legal Fee: Prevent Costly Lawsuits With Claim Limitation Clauses
April 25, 2012 —
Douglas Reiser, Builders Council BlogEver had that lingering problem with a contracting partner that went away for awhile and then came back to bite you ? years later? In Washington, construction contract claims can be raised for up to six years after substantial completion. Six years!? Why would I want to wait that long to find out if I have a problem? You don’t have to.
Over the past few years, I have discussed the notion of “contractual claim periods” on The Builders Counsel. For today’s Save a Legal Fee column, I cannot think of a better topic. These provisions are specifically intended to save you from unnecessary legal fees that might arise if a problem goes unnoticed for too long.
Contractual claim periods are simply a way to reduce the amount of time that a contracting party has to raise a claim against its contracting partner. For example, a subcontractor might require that a general contractor raise any claim that it might have ? for defective or incomplete work, injury, damages, etc ? within a particular amount of time or forever lose the ability to raise the claim in a legal proceeding.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
The Utility of Arbitration Agreements in the Construction Industry
December 30, 2019 —
Brian L. Gardner & Jason R. Finkelstein - Construction ExecutiveIn today’s ever-evolving world of employment law, it is far from an easy task for construction industry employers to operate their business while successfully navigating all of the potential legal potholes that continue to abound and multiply seemingly with every passing day. This is particularly true in the face of the onslaught of claims lodged by current and former employees in recent years for alleged unpaid wages. While there may not be a “sure bet” way of avoiding such claims, one tool that employers should strongly consider in their arsenal are arbitration and class action waiver agreements.
To that end, last year, the United States Supreme Court rendered its ground-breaking decision in Epic Systems Corp. v. Lewis, 584 U.S. ___ (2018). In Epic Systems, the Supreme Court held that arbitration agreements containing class and collective action waivers of wage and hour disputes are enforceable. At the time of the decision, a split of authority existed among courts across the country as to whether such agreements were viable. On the one hand, several courts contended that class waivers unfairly violated employees’ rights to collectively bargain under the National Labor Relations Act. On the other hand, many other courts were finding that such agreements were fully enforceable and supported by the policies promoted under the Federal Arbitration Act. The Epic Systems Court sided with this latter viewpoint, concluding that the FAA’s clear policy promoting arbitration as a dispute resolution mechanism and private parties’ rights to freely negotiate contracts outweighed any potential arguments against such agreements under the NLRA.
With wage and hour lawsuits being filed against construction industry employers practically daily, the Epic Systems decision is critically important. Construction employers can now freely enter into arbitration and class waiver agreements with their laborers and thereby potentially limit the cost, expense and exposure of fighting such actions in a public forum on a collective or class-wide basis. To be clear, such agreements will not eliminate employees from bringing such wage and hour claims entirely, nor should the use of those agreements signal to employers that they need not make every good-faith effort to comply with their obligations under the Federal Labor Standards Act and/or any applicable state wage and hour laws. But the reality is that arbitration and class waiver agreements can work to avoid tens or hundreds or even thousands of employees from banding together in some of the massive wage and hour lawsuits being filed across the country. Instead, employers can require that those legal battles be conducted by a single plaintiff in a more controlled environment before an arbitrator (or panel of arbitrators).
Reprinted courtesy of
Brian L. Gardner & Jason R. Finkelstein, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Gardner may be contacted at bgardner@coleschotz.com
Mr. Finkelstein may be contacted at jfinkelstein@coleschotz.com
Read the court decisionRead the full story...Reprinted courtesy of
Key Takeaways For Employers in the Aftermath of the Supreme Court’s Halt to OSHA’s Vax/Testing Mandate
January 24, 2022 —
Laura H. Corvo - White and Williams LLPPolitical pundits and legal scholars have been engaged in frenzied debate trying to decipher the fallout of the United States Supreme Court’s decision that stopped stopped the Occupational Safety and Hazard Administration (OSHA) from enforcing its Emergency Temporary Standard (ETS) which mandated that employers with 100 or more employees require workers to show proof of vaccination against COVID-19 or submit to weekly testing. The Court’s decision prevents OSHA from enforcing its ETS until all legal challenges have been heard. Because the Court concluded that those legal challenges are “likely to succeed on the merits” of their argument that OSHA does not have the statutory authority to issue its vaccine and testing mandates, there is significant doubt that they will ever come to fruition.
While the pundits and scholars have now had their say, employers, who are struggling to manage a highly contagious variant, a tight labor market, and employees with divergent and staunch views on vaccination, are also left wondering what the Court’s decision means for them and what they should be doing. Here are some key takeaways for employers in the aftermath of the Court’s decision.
Read the court decisionRead the full story...Reprinted courtesy of
Laura H. Corvo, White and Williams LLPMs. Corvo may be contacted at
corvol@whiteandwilliams.com
When Is a Project Delay Material and Actionable?
January 11, 2022 —
Rick Erickson - Snell & Wilmer Real Estate Litigation BlogWelcome to 2022! This year, the construction industry will undoubtedly reflect on the last two years as unprecedented times plagued by construction project delays. The COVID-19 pandemic contributed to suspension of work and closure of construction projects worldwide in 2020. The end of 2021 brought additional delays caused by an inexplicable clog in the supply chain of construction materials. The combined impact of these events on project milestones and completion deadlines led our clients to ask, with unusual and particular urgency, who is liable for such delays and how do contracting parties lessen the consequences from such unexpected and uncontrollable delays.
Granted that project delays are nothing new or unusual. They were common enough before inflation caused shipping complications and pandemic decimated the construction labor force. All delays, whatever the source, variably cause loss to all players on a construction project. But not all delays matter when it comes to claims and remedies available to the contracting parties in dispute resolution, where the determinative focus is on material delays impacting the entire project and on delays the claimant can credibly prove.
Most, if not all, jurisdictions interpret actionable delays from the contract documents for the project. The contract is definitely where you should start before pursuing any delay remedies. Delay remedies may be a time extension only, or a time extension plus your additional general conditions. Some delay remedies may be barred by the contract’s express terms and may be enforced adversely by the courts when such contract terms are indisputable. See Quinn Constr. v. Skanska USA Bldg., Inc., 730 F. Supp. 2d 401, 411 (D.C. Pa. 2010) (enforcing the subcontractor’s contractual waiver of claims for delay and disruption damages). On the other hand, delay damages that are expressly allowed by the contract—like overtime necessitated by the delays—are usually actionable and recoverable. Id. However, not only the contract terms, but applicable law, may affect the outcome.
Read the court decisionRead the full story...Reprinted courtesy of
Rick Erickson, Snell & WilmerMr. Erickson may be contacted at
rerickson@swlaw.com
Builders Can’t Rely on SB800
October 01, 2013 —
CDJ STAFFIn coming to their ruling on SB800, the California Court of Appeals looked to the legislative intent behind the law. Valentine Hoy, Timothy Hutter, and Erin Sedloff of Allen Matkins, in an article on the ruling, note that SB800 was written in response to Aas v. Superior Court, in which the court found that there was no remedy for construction defects that had not resulted in property damage. In the latest ruling, Liberty Mutual v. Brookfield Crystal Cove, LLC, the court concluded that SB800 was passed to give homeowners a way to address defects that had not lead to damage. However, the court also concluded that the legislature did not intend for SB800 to be the only remedy.
In Liberty Mutual, the insurance company sought reimbursement for claims it had paid on a homeowner’s claim after a fire sprinkler pipe burst. Liberty Mutual had insured the homeowner and sought repayment from the builder. Escrow had closed on the home in 2004, the pipe burst in 2008, and Liberty Mutual filed their claim in 2011, seven years after the close of escrow. But for plumbing issues, SB800 has a four-year statute of limitations.
The writers describe California as “a hotbed for construction defect litigation.” Due to the Liberty Mutual ruling, developers now “cannot rely on the statutes of limitation set forth in SB800.”
Read the court decisionRead the full story...Reprinted courtesy of
LA Metro To Pay Kiewit $297.8M Settlement on Freeway Job
December 08, 2016 —
Greg Aragon – Engineering News-RecordThe Los Angeles County Metropolitan Transportation Authority (LA Metro) has reached an agreement with Kiewit Corp. and will pay the contractor $297.8 million for project change orders on the Interstate 405-Sepulveda Pass Widening Project, in Los Angeles.
Read the court decisionRead the full story...Reprinted courtesy of
Greg Aragon, Engineering News-RecordENR may be contacted at
ENR.com@bnpmedia.com
4 Ways to Mitigate Construction Disputes
March 20, 2023 —
Bill Shaughnessy - ConsensusDocsResolving construction disputes in litigation (court or arbitration) can be expensive and may drag on for years. Most disputes could have been avoided, or at least mitigated, had the parties (both owners and contractors) identified contract risks during negotiations and been more proactive in communicating the risks during execution of the work. This article highlights four practical risk management approaches that help all parties focus on their mutual interest in close coordination and clear communication at the beginning of the project as well as throughout performance:
- Identifying and allocating risks;
- Accurate scheduling;
- Clear project documentation and communication; and
- Real-time dispute resolution.
The intent of these techniques is not to shift legal obligations or risks. Rather, the intent is to keep project personnel and project management for all the participants focused on communicating and working together, including responsibly confronting real problems to avoid or mitigate their impact. Allocating risks, scheduling, project documentation and communication, and real-time dispute resolution are independently relevant on a bilateral basis between the owner, designer, and the various contractors. These approaches and their diligent execution by the parties during construction contribute far more to a successful project than anything lawyers and claims consultants can contribute in after-the-fact legal proceedings.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Shaughnessy, Jones Walker LLP (ConsensusDocs)Mr. Shaughnessy may be contacted at