Fannie Overseer Moves to Rescue Housing With Lower Risk to Lenders
May 21, 2014 —
Kathleen M. Howley – BloombergMelvin Watt, the overseer of Fannie Mae and Freddie Mac, broke five months of silence to help boost lending as slowing sales threatens the housing recovery.
Watt, 68, in his first speech as director of the Federal Housing Finance Agency, announced new rules to reduce the risk that lenders will have to repurchase bad mortgages. The changes, designed to allow banks to relax credit standards, probably will increase housing sales by 5 percent this year, said Stephanie Karol, an economist at Englewood, Colorado-based research firm IHS Inc.
“It means a restart for the real estate recovery,” said Mark Zandi, chief economist of Moody’s Analytics Inc. “We’re not going to get back on track until we start making credit more available to potential buyers.” He said he expects Watt’s moves to spur “meaningful” sales growth.
Read the court decisionRead the full story...Reprinted courtesy of
Kathleen M. Howley, BloombergMs. Howley may be contacted at
kmhowley@bloomberg.net
Most Common OSHA Violations Highlight Ongoing Risks
July 27, 2020 —
David M. McLain – Colorado Construction LitigationIn the 12 months from October 2018 through September 2019, the most recent period reported by OSHA,[1] the workplace safety agency cited the following standards[2] more than any other in the 28 states which do not have OSHA-approved state plans, including Colorado:
- 1926.501 – Duty to have fall protection – included in 459 citations, resulting in $2,475,596 in penalties ($5,393/citation);
- 1926.451 – General requirements for scaffolds – included in 265 citations, resulting in $834,324 in penalties ($3,148/citation);
- 1926.1053 – Requirements for ladders including job-made ladders – included in 164 citations, resulting in $354,853 in penalties ($2,163/citation);
- 1926.503 – Training requirements related to fall protection - included in 114 citations, resulting in $156,076 in penalties ($1,369/citation);
- 1926.405 - Wiring methods, components, and equipment for general use – included in 93 citations, resulting in $150,821 in penalties ($1,621/citation);
- 1926.20 - General safety and health provisions – included in 85 citations, resulting in $328,491 in penalties ($3,864/citation);
- 1926.1052 – Requirements for stairways – included in 79 citations, resulting in $155,651 in penalties ($1,970/citation);
- 1926.102 – Requirements for eye and face protection - included in 67 citations, resulting in $165,595 in penalties ($2,471/citation);
- 1926.403 – General requirements for electrical conductors and equipment – included in 63 citations, resulting in $146,050 in penalties ($2,318/citation), and;
- 1926.100 – Requirements for head protection – included in 55 citations, resulting in $127,274 in penalties ($2,314/citation).
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & RoswellMr. McLain may be contacted at
mclain@hhmrlaw.com
Court Agrees to Stay Coverage Matter While Underlying State Action is Pending
October 29, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe federal district court granted the insured's motion to stay the coverage action while the construction defect case was pending in state court. Auto Owners Ins. Co. v. Essex Homes Southeast, Inc., 2014 U.S. Dist. LEXIS 133120 (D. S.C., Sept. 23, 2014).
The homeowners sued Essex Homes in state court for construction defects in a home built and sold to them by Essex Homes. The suit sought damages for property damage based on negligence, breach of implied warranty, and breach of express warranties arising out of the alleged construction defects. The complaint alleged that a water leak in the house caused water damage and resulted in mold growth that was not discovered for several years.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Construction Law Advisory: Mechanical Contractor Scores Victory in Prevailing Wage Dispute
September 03, 2014 —
Steven M. Cvitanovic & Jessica M. Lassere Ryland - Haight Brown & Bonesteel LLPOn August 27, 2014, the First District Court of Appeal weighed in on whether prevailing wages are required for public contracts in situations where work is performed in furtherance of the project but at a permanent offsite manufacturing facility that is not exclusively dedicated to the project. In Sheet Metal Workers' International Association, Local 401 v. John C. Duncan and Russ Will Mechanical, the project at issue was for a community college district where Russ Will was the HVAC subcontractor. The contract documents required contractors to pay prevailing wages but they did not limit where or how Russ Will would fabricate sheet metal required for the job. Russ Will used its existing fabrication facility to form the sheet metal.
An employee of Russ Will filed a complaint with the DIR alleging he should have been paid prevailing wages for work related to the project. The worker fabricated sheet metal for the project but at Russ Will’s Hayward facility, not at the site. The DIR issued a coverage determination in which it concluded that Russ Will was required to pay prevailing wages for the offsite fabrication work associated with the project. The DIR's determination turned on whether Russ Will was exempt from the prevailing wage law as a material supplier. To qualify for the material supplier exemption, the employer must sell supplies to the general public and its fabrication or manufacturing facility must not be established for the particular public works contract or be located at the site of the public work.
Following the DIR determination, Rush Will filed an administrative appeal. The department reversed its initial coverage determination, concluding that the offsite fabrication performed by Russ Will was not subject to the prevailing wage law.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Jessica M. Lassere Ryland, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com; Ms. Ryland may be contacted at jlassere@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
After $15 Million Settlement, Association Gets $7.7 Million From Additional Subcontractor
November 07, 2012 —
CDJ STAFFThe stucco subcontractor for a condominium complex did not join in with the other defendants in a settlement of more than $15 million, preferring to take the case to a jury trial. That jury has found the stucco installer liable for $7.7 million to make repairs. Mark Wiechnik of Herrick Feinstein LLP wrote about the case on the Lexology web site. Mr. Wiechnik notes that the jury was shown “samples of rotted wood taken from the property as well as numerous pictures of damage resulting from the various defects.”
Read the court decisionRead the full story...Reprinted courtesy of
Request for Stay Denied in Dispute Over Coverage for Volcano Damage
August 10, 2020 —
Tred R. Eyerly - Insurance Law HawaiiAlthough there were concurrent state and federal proceedings regarding the insureds' claims for damage caused by Kilauea Volcano, the federal district court refused to dismiss or stay the federal action. Aqulina v Certain Underwriters at Lloyd's Syndicate #2003, 2020 U.S. District Ct. LEXIS 101832 (D. Haw. June 10, 2020).
Plaintiffs held homeowner's policies from Lloyd's that were brokered and underwritten by various defendants. Coverage from the May 2018 eruption of Kilauea Volcano was denied based upon an exclusion precluding coverage for lava-related damage.
Plaintiffs sued Lloyds and various brokers in federal court, alleging that defendants had engaged in a deceptive scheme to defraud plaintiffs and deprive them of meaningful coverage. Lawsuits were also filed in state court, with plaintiffs arguing their losses were covered by their policies and that defendants wrongfully relied solely on the lava exclusion to deny claims.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
What to Know Before Building a Guesthouse
September 17, 2014 —
Cynthia Flash – BloombergThose tiny, often very cute homes that people are adding on their properties seem to be popping up everywhere these days. The tiny buildings can provide extra rental income, offer a less-expensive housing option or provide a home for a relative.
Accessory dwelling units, or ADUs, are second dwelling units created on a lot with an existing house or attached house. They’re often referred to as mother-in-law apartments, granny flats or studio apartments. As a homeowner, what are the legal issues to consider before building an ADU of your own?
Different cities, different rules
First off, different cities have different rules. Before plotting the space for your new tiny house, check with your city’s planning and zoning department to determine what those rules are. You can start online at accessorydwellings.org for a list of regulations by state and city.
Read the court decisionRead the full story...Reprinted courtesy of
Cynthia Flash, Bloomberg
Risky Business: Contractual Protections in the 'New Normal'
January 04, 2023 —
Daniel Lund III - Construction ExecutiveThe point of contracts is to create certainty to avoid litigated or arbitrated disputes. Still, the various parties in the construction process may have different risk tolerances. For example, general contractors are often characterized as “risk-tolerant.” That risk, though, is usually calculated by the contractor internally, outside the terms of the written contract, based on an assumption that the contractor can get the work done more cheaply and more quickly than the owner anticipated. Project owners typically want and expect close-to-absolute certitude—absolutely as to cost—in their construction contracts. The standard fixed-price or lump-sum construction contract is geared toward protecting that interest.
Post-COVID-19, however, the discussion in the industry suggests that all bets are off when pricing and agreeing to construction work. Labor and materials shortages have sent owners and their design consultants backpedaling when general contractors pursuing a fixed-price contract seek contractual concessions that “un-fix” the price.
Reprinted courtesy of
Daniel Lund III , Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of