Candlebrook Adds Dormitories With $230 Million Purchase
November 05, 2014 —
John Gittelsohn - BloombergCandlebrook Properties LLC, a closely held company with about 5,000 apartments in the eastern U.S., is diversifying into student housing with the $230 million acquisition of five off-campus properties.
Candlebrook joined with Lubert-Adler Partners on the purchase of buildings with about 3,400 beds near colleges in Georgia, Indiana, Kentucky and Virginia. Formerly known as Vantage Properties LLC, Candlebrook began as an investor in New York City apartments in 2005 and later expanded to New Jersey and the Philadelphia area.
“Student housing is a natural extension of our pre-existing business line,” Neil Rubler, president of New York-based Candlebrook, said in a telephone interview. It’s “a business that’s far less crowded than multifamily, which has been our core business.”
Capitalization rates on apartments, a measure of profitability, have dropped as investors drive up property prices. Student housing has become an attractive alternative, luring homebuilder Toll Brothers Inc. (TOL) and private-equity firm Colony Capital LLC to an industry already home to real estate investment trusts American Campus Communities Inc. (ACC), Campus Crest Communities Inc. (CCG) and Educational Realty Trust Inc. (EDR)
Read the court decisionRead the full story...Reprinted courtesy of
John Gittelsohn, BloombergMr. Gittelsohn may be contacted at
johngitt@bloomberg.net
City of Pawtucket Considering Forensic Investigation of Tower
October 08, 2014 —
Beverley BevenFlorez-CDJ STAFFPawtucket, Rhode Island’s mayor, Donald Grebien, has asked their city council to approve “a forensic investigation of the Pawtucket City Hall tower to determine whether the city should sue the contractor that repaired it eight years ago,” the Valley Breeze reported.
Back in 2011, “city officials had been unable to locate a signed contract for the tower project as they sought to hold NER responsible for continued leaking into the structure just five years after the company's $3 million renovation project was complete,” according to the Valley Breeze. “The costs of that project grew to $4.6 million once interest was factored in.”
Documents have recently been discovered that Grebien believes may open the possibility to sue NER.
Read the court decisionRead the full story...Reprinted courtesy of
Be a Good Neighbor: Techniques to Mitigate the Risk of Claims from Adjacent Landowners
December 07, 2020 —
Joshua Levy, Josh Neudorfer & Madeleine Bailey - Construction ExecutiveIn May 2020, a real estate developer performing excavation work in New York was sued by a neighboring property owner for property damage. A court overturned an injunction preventing the developer from continuing excavation work after reviewing a preconstruction assessment that showed the damage to the neighboring property was preexisting—not caused by the excavation (see Feldman v. 3588 Nostrand Ave. LLC as an example)
A preconstruction assessment is one of the most important tools in the arsenal of a developer protecting itself from neighbors bringing claims for property damage. Part two of this series will review the benefits of risk mitigation tools recommended for developers such as postconstruction assessments and monitoring during construction.
Preconstruction Assessment Overview
A preconstruction assessment is a review of a property adjacent to a site where demolition and/or construction activities are to take place. The goal of the assessment is to establish baseline conditions by conducting an inspection of buildings and infrastructure, including identification of existing damage to improvements, so that causation of any alleged damages can be more easily determined.
Reprinted courtesy of
Joshua Levy, Josh Neudorfer & Madeleine Bailey, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Levy may be contacted at joshua.levy@huschblackwell.com
Mr. Neudorfer may be contacted at jneudorfer@thesigmagroup.com
Read the court decisionRead the full story...Reprinted courtesy of
No Coverage for Negligent Misrepresentation without Allegations of “Bodily Injury” or “Property Damage”
February 10, 2012 —
Tred R. Eyerly - Insurance Law HawaiiJeff City Industries was the general contractor for a sewer system improvement project in Branson, Missouri. Bituminous Cas. Corp. v. United HRB Gen. Contractors, Inc., 2011 U.S. Dist. LEXIS 145666 (W.D. Mo. Dec. 19, 2011). Branson sued Jeff City, alleging breach of the construction contract for the project. The claims included improperly bedded sewer piping, improper aligning portions of trenching for the sewer piping, improper service line connections to the sewer piping, etc.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Appeals Court Reverses Summary Judgment over Defective Archway Construction
February 10, 2012 —
CDJ STAFFA judge has ruled that a plaintiff can go forward with her suit that she was injured by a defective archway during a birthday party. A three-judge panel of the California Court of Appeals issued this ruling on January 23, 2012, in the case of Trujillo v. Cosio.
Ms. Trujillo attended a birthday party at the home of Maria Cosio and Joel Verduzco. A piñata was hung between a tree and a brick archway. Ms. Trujillo went to get candy that had fallen from the piñata, during which the archway fell on her hand. Subsequent examination of the archway showed that it had not been “properly anchored to the supporting pillars to protect the arch from falling.”
Ms. Cosio and Mr. Verduzco argued that they could not have been aware of the defective nature of the archway’s construction, as it had been built at the request of the prior property owner. The structure was constructed without building permits. Mark Burns, a civil engineer testifying for the plaintiff, said that “a reasonable property owner would have thoroughly tested the archway to ensure it was capable of withstanding such horizontal forces before allowing children to enter into the area.” Mr. Burns noted that twenty rope pulls would have been sufficient to demonstrate the structure’s instability.
The trial court rejected Mr. Burn’s statements, finding that the respondents did not have any knowledge of the defect and that a visual inspection should have sufficed. The court noted that this a triable issue, whether visual inspection suffices, or whether the property owners should have done as Mr. Burns suggested and yank a rope twenty times. The court noted that “although a jury may ultimately disagree with Burn’s opinion, it was supported by sufficient foundation and was not speculative.”
The opinion was written by Judge Flier, with Judges Rubin and Grimes concurring.
Read the court’s decison…
Read the court decisionRead the full story...Reprinted courtesy of
Include Contract Clauses for Protection Against Ever-Evolving Construction Challenges
May 30, 2022 —
Michael Henry & Kevin J. Riexinger - Construction ExecutiveThe first quarter of 2022 provided a valuable glimpse into some of the major issues the construction industry can expect to continue impacting jobsites for the rest of the year.
Early in the pandemic, construction was not immune from the shut-downs that swept across market sectors. Workers were staying home to shield themselves and their families from the COVID-19 virus (and variants). This caused delays with construction projects and failures to meet negotiated benchmarks or deadlines. Contractors were left to wonder whether they remained obligated to perform under their contracts, or whether COVID-19 allowed them to invoke force majeure clauses. Over the past two years, there has been much debate about whether force majeure clauses encompass COVID-19 risks.
Traditionally, force majeure is only invoked for significant weather events or natural disasters. Unsurprisingly, outcomes of legal actions regarding COVID-19 and force majeure varied by state and by contract. It didn’t take long for contractors to seek a more predictable and certain solution.
Reprinted courtesy of
Michael Henry & Kevin J. Riexinger, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Riexinger may be contacted at kriexinger@gllawgroup.com
Mr. Henry may be contacted at MbHenry@tcco.com
Read the court decisionRead the full story...Reprinted courtesy of
Yes, Virginia, Contract Terms Do Matter: Financing Term Offers Owner an Escape Hatch
November 25, 2024 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday, Musings welcomes Timothy R. Hughes, Esq., LEED AP. Tim (@vaconstruction on Twitter) is Of Counsel to the Arlington, Virginia firm of Bean, Kinney & Korman, P.C. In his practice as a business, corporate, and construction law attorney, Tim served as the previous Chair of the Construction Law and Public Contracts Section of the Virginia State Bar. He has served in numerous volunteer, board and leadership roles with such organizations as the Arlington Chamber of Commerce, the Northern Virginia Building Industry Association, Vanguard Services Unlimited, Leadership Arlington, Associated Builders & Contractors (Metro DC and Virginia), and numerous other volunteer and construction trade association activities. A regular speaker and writer, Tim is the lead editor of his firm blog, Virginia Real Estate, Land Use and Construction Law.
A recent Virginia case once again demonstrates that contract terms matter. An unusual financing term allowed the owner of a project a complete escape from any liability on a project despite significant work being performed. The opinion from the Circuit Court of Norfolk involved five separate cases consolidated together, four claims by subcontractors and one by the general contractor Turner. All five cases hinged on an unusual financing clause in Turner’s contract with the other. That provision stated:
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Summary Judgment in Favor of General Contractor Under Privette Doctrine Overturned: Lessons Learned
March 27, 2023 —
Garret Murai - California Construction Law BlogIt seems like we’ve been seeing a lot of Privette doctrine cases recently. Here’s another,
Brown v. Beach House Design & Development, 85 Cal.App.5th 516 (2002), which provides a cautionary tale for general contractors to watch what they include in their scope of work and how they manage projects.
The Beach House Case
Kyle Brown was a carpenter employed by subcontractor O’Rourke Construction, Inc. who contracted with general contractor Beach House Design and Development to provide finish carpentry on a construction project. A&D Plastering Co., another subcontractor on the project, had erected scaffolding on the project.
On June 16, 2017, while using A&D’s scaffolding, Brown fell onto a concrete walkway where he suffered severe injuries. Following the accident, Beach House and A&D inspected the scaffolding and found that some of the scaffolding was not properly secured to the building and that planks, crossbars, ties and guardrails had been cut or were missing.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at