New York Court Enforces Construction Management Exclusion
March 14, 2018 —
Traub Lieberman Straus & Shrewsberry LLPIn its recent decision in
Houston Cas. Co. v. Cavan Corp. of NY, Inc., 2018 N.Y. App. Div. LEXIS 1138 (N.Y. 1st Dep’t Feb. 20, 2018), a New York appellate court had occasion to consider the application of a construction management exclusion in a general liability policy.
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman Straus & Shrewsberry LLP
Brooklyn’s Industry City to Get $1 Billion Modernization
March 12, 2015 —
David M. Levitt – Bloomberg(Bloomberg) -- A late 19th century industrial complex on New York’s Brooklyn waterfront is slated for a $1 billion makeover that aims to transform the property into a modern hub for manufacturing and technology.
The owners of Industry City, Atlanta-based Jamestown and its partners, plan to invest about $890 million over the next 12 years, and anticipate tenants will put in about $150 million of their own money, according to a proposal announced Monday. The project will create one of the largest centers for the “innovation economy” in the U.S., and one of New York’s biggest engines of job growth, said Andrew Kimball, chief executive officer of Industry City.
Read the court decisionRead the full story...Reprinted courtesy of
David M. Levitt, BloombergMr. Levitt may be contacted at
dlevitt@bloomberg.net
BHA Expands Construction Experts Group
October 28, 2011 —
Bert L. Howe & Associates, Inc. - Corporate OfficesBert L. Howe & Associates, Inc., one of the nation’s leading construction forensics firms is pleased to announce the expansion of the company’s civil and structural engineering capabilities.
JERRY M. MILES, PE - Mr. Miles has been a licensed civil engineer in California since 1987 and has served as the lead civil engineer on many projects in several states. His experience includes contract administration services as the owner’s representative on a variety of projects including mastered planned communities, residential subdivisions, shopping centers and multi-family residential projects. He has also been involved in providing water quality management plans and storm water pollution prevention plans. Mr. Miles has also served on the Town of Apple Valley’s Building Department Dispute Resolution Board.
His more than 26 years of engineering experience includes geotechnical evaluations, structural design of wood-framed, masonry, and concrete tilt-up buildings, small and large subdivision engineering construction/improvements plans, hydrology/hydraulic reports and design, forensic investigation and expert witness testimony. Mr. Miles has qualified as an expert in numerous jurisdictions and Federal court. He has been called upon to provide deposition testimony on more than twenty-five occasions and has successfully testified at arbitration and trial. Click here to view Mr. Miles’ Current CV.
MATTHEW J. STIEFEL, PE - With a background that spans a multitude of design and new construction projects to catastrophic claims analysis, Mr. Stiefel brings a unique set of credentials and experience to the construction experts group at Bert L. Howe & Associates. Mr. Stiefel has more than 13 years’ experience in civil, structural, and geotechnical engineering; providing design and construction consulting services on a variety of projects that include multi-family and single family dwellings, commercial buildings, transportation facilities, industrial facilities, storm drain channels, water and wastewater pipelines. His engineering experience encompasses multiple disciplines of civil engineering including geotechnical design and evaluation, foundation design, structural design of wood-framed buildings, preparation of grading plans and site drainage analysis. He has provided cause and origin analysis for insurance adjusters on many residential and commercial sites related to issues involving moisture intrusion and mold, foundation movement, site drainage, soil movement, wind damage, and other various losses. Click here to view Mr. Stiefel’s Current CV.
Read the court decisionRead the full story...Reprinted courtesy of
Administration Seeks To Build New FBI HQ on Current D.C. Site
February 28, 2018 —
Tom Ichniowski – ENRA Senate committee plans to examine a new $3.3-billion Trump administration proposal to demolish the Federal Bureau of Investigation's worn, outmoded headquarters in downtown Washington, D.C., and construct a new facility on that site.
Read the court decisionRead the full story...Reprinted courtesy of
Tom Ichniowski, Engineering News-RecordMr. Ichniowski may be contacted at
ichniowskit@enr.com
Practical Pointers for Change Orders on Commercial Construction Contracts
December 31, 2014 —
John E. Bowerbank - Newmeyer & DillionConstruction projects pose unique challenges, including keeping costs within budget, meeting project deadlines, and coordinating the work of numerous contractors and subcontractors in the wake of inevitable design revisions and changes to the plans. Anticipating potential project challenges and negotiating contract provisions before commencing work on a project is critical for all parties. Careful planning should reduce the number of contract disputes. This, in turn, can facilitate the completion of a project within budget and on schedule.
“Changes” Clauses in Construction Contracts
Most commercial construction contracts have a clause addressing changes to the contract. A “changes” clause typically requires the mutual agreement of the parties on the scope of any modifications to the contract, as well as the effect on the contract price and timeframe for the work to be performed. This results in what is generally referred to as a “change order.” Many projects have a large number of change orders, which can result in significant cost overruns and delays to the project if the contract contains a complicated change order process. Therefore, in order to minimize cost overruns and project delays, it is crucial to keep the change order process as simplified and streamlined as possible.
In the most basic terms, change orders memorialize modifications to the original contract, and typically alter the contract's price, scope of work, and/or completion dates. A typical change order is a written document prepared by the owner or its design professional, and signed by the owner, design professional, and affected contractors and subcontractors. An executed change order indicates the parties’ agreement as to what changes are taking place, including approval for additional costs and schedule impacts.
While the reasons for change orders and the parties initiating them may vary, all change orders have one feature in common. Effective change orders alter the original contract and become part of the contract. Therefore, from a legal standpoint, change orders must be approached with the same caution and forethought as the original contract.
Practice Pointers for Change Orders
In light of the foregoing, some practice pointers for change orders in commercial construction contracts are as follows:
- Carefully Negotiate and Draft Change Order Provisions in the Original Contract.
A carefully negotiated and drafted “changes” clause that accounts for “unexpected circumstances” or “hidden conditions” can protect the parties from downstream costly disputes.
- Immediately Address Changes by Following the Change Order Process, Including Obtaining Necessary Signatures.
Regardless if you are an owner, general contractor or subcontractor, you should address any proposed change order immediately. Even if a decision maker gives “verbal” approval to go ahead with changed work, the work should not proceed without following the change order process in the original contract. This includes making sure to obtain any necessary signatures for the change order, if at all possible.
- Analyze the Plans and Specifications to Determine Whether “Changes” are Within the Scope of the Original Contract, or Whether They are Extra Work.
Prior to entering an original contract, it is imperative that the parties review the plans and specifications for ambiguities regarding work included in the original contract, versus potential extra work that would require a change order. This is important because a careful review of the plans and specifications sometimes reveals that work believed to be a change order is, in fact, original work, or vice versa.
- Make Sure Requests and Approvals for Change Orders are Done by an Authorized Representative.
When a party requests or gives its approval to a change order, it is important to confirm the request or approval came from an authorized representative.
- Avoid Vague and Open-Ended Change Orders.
Indeed, the vaguer a change order, the more likely it can lead to a dispute. Vague and open-ended change orders, including change orders that provide for payment on a time and materials basis, can be difficult for an owner to budget and schedule. This can lead to disputes as to cost and/or time extensions.
- Oral Assurances for Payment Without a Signed Change Order May Not Be Recoverable.
When a party provides verbal assurances to another party for extra work without following the change order process, there is a much higher likelihood that disputes will occur. Although there is case law that may allow a contractor to recover for extra work in private contracts based on oral promises, the parties should avoid placing themselves in such a legal position. Notably, in public contracts, a contractor may not be able to recover for any extra work without a signed changed order, even with verbal assurances of payment from the owner.
About the Author:
John E. Bowerbank, Newmeyer & Dillion
Mr. Bowerbank is a partner in the Newport Beach office and practices in the areas of business, insurance, real estate, and construction litigation. You can reach John at john.bowerbank@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Georgia Supreme Court Determines Damage to "Other Property" Not Necessary for Finding Occurrence
July 31, 2013 —
Tred Eyerly, Insurance Law HawaiiThe Georgia Supreme Court has determined that an "occurrence" may arise under a CGL policy even if "other property" is not damaged. Taylor Morrison Servs. v. HDI-Gerling Am. Ins. Co., 2013 Ga. LEXIS 618 (Ga. July 12, 2013).
Taylor Morrison, the insured, was a homebuilder. It was sued in a class action by more than 400 homeowners in California alleging that the concrete foundations of their homes were improperly constructed. This led to water intrusion, cracks in the floors and driveways, and warped and buckled flooring.
At first, HDI-Gerling defended under a reservation of rights. Subsequently, however, HDI-Gerling sued Taylor Morrison in federal district court in Georgia, seeking a declaratory judgment that there was no coverage. The district court granted summary judgment to HDI-Gerling after determining that there was no "occurrence" when the only "property damage" alleged was damage to work of the insured. Georgia law was applied to the dispute.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
New Mandatory Bond Notice Forms in Florida
December 16, 2019 —
Brian A. Wolf & Miles D. Jolley - Smith CurrieSubcontractors and suppliers must now use new, statutory notice of nonpayment forms to preserve payment bond claims, and sign each notice of nonpayment under oath.
The State of Florida instituted changes to the statutes governing public-project payment bonds (section 255.05, Florida Statutes) and private-project payment bonds (section 713.23, Florida Statutes). The changes went into effect on October 1, 2019. Previously, notices of nonpayment were not required to be signed under oath. Now, the law requires the use of specific statutory notice forms that claimants must sign under oath. Previously, there were no statutory penalties for claimants who exaggerated the amount claimed against a payment bond. Now there are specific statutory penalties against a claimant who willfully or negligently signs a notice of nonpayment that includes a claim for work not performed or materials not furnished, or who is guilty of signing a notice prepared with willful or gross negligence.
Public construction payment bonds are governed by section 255.05, Florida Statues, also known as Florida’s Little Miller Act. This statute requires all payment bond claimants who don’t have a direct contract with the general contractor to serve both the bonding company and the general contractor with a notice of nonpayment no later than 90 days after their last date of work or last delivery of materials. The amended statute now requires that the claimant use the statutory notice form and sign the form under oath. If the claimant includes exaggerated claims, or intentionally makes a claim for work or materials not provided, or otherwise prepares a notice with gross negligence, then the bonding company and the general contractor will be able to use such as a complete defense to an otherwise valid bond claim.
Reprinted courtesy of
Brian A. Wolf, Smith Currie and
Miles D. Jolley, Smith Currie
Mr. Wolf may be contacted at bawolf@smithcurrie.com
Mr. Jolley may be contacted at mdjolley@smithcurrie.com
Read the court decisionRead the full story...Reprinted courtesy of
Hawaii Court of Appeals Finds Insured AOAO Not Liable for Securing Inadequate Insurance
March 04, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe Hawaii Intermediate Court of Appeals (ICA) affirmed the trial court's finding that the insured Association of Apartment Owners (AOAO) was not liable for securing a policy with inadequate coverage. AOAO Queen Emma Gardens, et al v. Wa, 2023 Haw. App. LEXIS 400 (Haw. Ct. App. Dec. 19, 2023).
In October 2002, the Was purchased a condominium located in the Queen Emma Gardens Condominium. The AOAO's bylaws provided that it would procure and maintain insurance "to insure the Board, the Association, and each apartment owner against claims for personal injury, death, and property damage arising out of the condition of the property or activities thereon . . ." The AOAO secured a CGL policy from Insurance Association, Inc., with coverage limits for bodily injury at $1,000,000 and an umbrella policy providing an additional $5,000,000 of coverage. Each of the policies "insured each individual insurance owner of the insured condominium, but only with respect to liability arising out of the ownership, maintenance or repair of that portion of the premises which is not reserved for that unit owner's exclusive use or occupancy."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at