Minnesota Addresses How Its Construction Statute of Repose Applies to Condominiums
April 27, 2020 —
William L. Doerler - The Subrogation StrategistCourts often struggle with the question of when the statute of repose starts to run for construction projects that involve multiple buildings or phases. In Village Lofts at St. Anthony Falls Ass’n v. Housing Partners III-Lofts, LLC, 937 N.W.2d 430 (Minn. 2020) (Village Lofts), the Supreme Court of Minnesota addressed how Minnesota’s 10-year statute of repose, Minn. Stat. § 541.051, applies to claims arising from the construction of a condominium complex. The court held that the statute of repose begins to run at different times for: a) statutory residential warranty claims brought pursuant to Minn. Stat. §§ 327A.01 to 327A.08, et. seq.; and b) common law claims arising out of the defective and unsafe condition of the condominium buildings.
As stated in Village Lofts, Housing Partners III-Lofts, LLC (Housing Partners) developed the Village Lofts at St. Anthony Falls, a condominium complex consisting of Building A and Building B. Housing Partners retained Kraus-Anderson Construction Company (Kraus-Anderson) as the general contractor for Building A. Kraus-Anderson retained Elness Sweeney Graham Architects, Inc. (ESG), Doody Mechanical, Inc. (Doody) and Kenneth S. Kendle, P.E. (Kendle) to work on Building A. In September 2002, the City of Minneapolis (City) issued a partial certificate of occupancy (CO) for Building A, including the building’s public spaces. On October 4, 2002, Housing Partners filed the declaration creating the Village Lofts at St. Anthony Falls condominium, to be operated by Village Lofts at St. Anthony Association (Village Lofts Association). On October 10, 2002, Housing Partners sold the first unit in Building A and in November of 2003, the City issued a CO for the entire building, excluding two units.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
Cause Still Unclear in March Retaining Wall Collapse on $900M NJ Interchange
June 07, 2021 —
Stephanie Loder - Engineering News-RecordA probe continues by construction engineer Hardesty and Hanover LLC into what caused the late March collapse of a retaining wall that is part of one of New Jersey's largest roadbuilding projects—the already late-running effort called Direct Connection, which aims to untangle the convoluted interchange of north-south I-295 and east-west Route 42 in Camden County.
Reprinted courtesy of
Stephanie Loder, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Real Estate & Construction News Roundup (8/6/24) – Construction Tech Deals Surge, Senators Reintroduce Housing Bill, and Nonresidential Spending Drops
September 16, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, cybersecurity attacks target contractors, U.S. banks report weaker profits, additional commercial real estate is distressed, and more!
- Spending dropped in almost half of nonresidential subcategories in June, with the decrease stemming from higher interest rates, tighter credit conditions and a softening economy. (Sebastian Obando, Construction Dive)
- Despite the decline in investment dollars for construction technology, the number of deals surged by 18% year-over-year, indicating sustained interest and activity in the sector. (Sebastian Obando, Construction Dive)
- As cybersecurity attacks on U.S.-based businesses ramp up, general contractors are not immune. (Jen A. Miller, Construction Dive)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Trump Administration Waives Border Wall Procurement Rules
March 23, 2020 —
Mary B. Powers & Debra K. Rubin - Engineering News-RecordActing Homeland Security Secretary Chad Wolf on Feb. 20 waived federal contracting rules to expedite construction of the U.S-Mexico border wall in California, Arizona, New Mexico and Texas, citing legal authority under several U.S. laws, some dating back to the 1990s, to deal with what he claimed is "an acute and immediate need to construct physical barriers and roads ... to prevent unlawful entries."
Reprinted courtesy of
Mary B. Powers, Engineering News-Record and
Debra K. Rubin, Engineering News-Record
Ms. Rubin may be contacted at rubind@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Bidder Be Thoughtful: The Impacts of Disclaimers in Pre-Bid Reports
August 04, 2021 —
Joshua A. Morehouse - ConsensusDocsWhen bidding a project, subsurface or latent site conditions that are not immediately apparent can massively impact the costs of performance to general contractors. Were contractors required to bid on projects without any information on pre-existing conditions, they would need either to be assured that any additional costs would be reimbursed by the owner, or to include significant contingencies for subsurface conditions in their bids. For owners, these options result in either increased risk or increased cost—neither of which is particularly palatable. Owners therefore implement several contractual tools to minimize these risks and costs.
One of these tools is providing bidders with a report on latent conditions, often called a “geotechnical data report” or “GDR”, but otherwise shifting as much of the subsurface-related risk as possible to the contractor. In theory, these reports permit contractors to appropriately adjust their contingencies for latent conditions, thus saving owners money. However, several independent and thorny issues arise where site reports provided by the owner are either inconsistent with or silent on the actual conditions of a project site. Hence owners often include disclaimers with these reports, such as noting that the report is for “informational purposes only” or that the report is “not part of the contract documents."
Read the court decisionRead the full story...Reprinted courtesy of
Joshua A. Morehouse, Peckar & Abramson, P.C.Mr. Morehouse may be contacted at
jmorehouse@pecklaw.com
Call to Conserve Power Raises Questions About Texas Grid Reliability
July 05, 2021 —
Autumn Cafiero Giusti - Engineering News-RecordWith the days getting hotter and tropical activity picking up in the Gulf of Mexico, concerns are mounting about the reliability of the Texas power supply after the state’s main grid operator asked residents to go on a five-day energy conservation diet.
Reprinted courtesy of
Autumn Cafiero Giusti, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Project Completion Determines Mechanics Lien Recording Deadline
April 08, 2024 —
William L. Porter - Porter Law GroupThe California mechanics lien is one of the most powerful collection remedies available to contractors, subcontractors and suppliers who are unpaid for work performed and materials supplied in relation to a California private works construction project. The mechanics lien allows the claimant to actually sell the property where the work was carried out in order to obtain payment, entirely of course, against the wishes of the property owner. There are a number of important steps to follow and timelines to be met in order to pursue this remedy.
First, Understand Your Preliminary Notice Deadline
Working within deadlines is absolutely crucial to preserving mechanics lien rights under California law. The deadlines differ, depending on whether you are a “direct” contractor, also known as “original” or “prime” contractor (one who contracts directly with the property owner) or a subcontractor or material supplier. The process begins with the serving of a “preliminary notice” no later than 20 days after the party serving the preliminary notice begins supplying labor or materials to the project. Direct contractors are only required to serve the preliminary notice on the construction lender (Civil Code section 8200-8216), whereas subcontractors and material suppliers must serve not only the construction lender, but also the owner and direct contractor (see Civil Code section 8200(e)).
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Safeguarding the U.S. Construction Industry from Unfair Competition Abroad
November 07, 2022 —
Ric Macchiaroli - Gravel2Gavel Construction & Real Estate Law BlogIn April 2015, the U.S. International Trade Commission (ITC) issued an exclusion order prohibiting the importation of certain foreign-made crawler cranes into the United States for a period of at least 10 years. That order was the result of a 20-month investigation by the ITC, initiated by a Wisconsin-based crane manufacturer based on allegations of patent infringement and trade secret misappropriation by a China-based company. Defined by powerful injunctive remedies, unique rules, and a lightning-fast docket, the ITC can help protect American industry from unfair acts in the importation of articles into the United States. This post explores the traits that make the ITC an attractive venue for potential complainants.
ITC Site Plan
The ITC is a specialized trade court located in Washington, D.C., that has broad authority to investigate and remedy unfair trade practices. One of the ITC’s primary functions is to conduct unfair import investigations, also known as “section 337” investigations, after the authorizing statute. A section 337 investigation can be instituted based on any number of unfair acts, including, but not limited to, patent infringement (utility and design), registered and common law trademark infringement, copyright infringement (including violations of the Digital Millennium Copyright Act), trade dress infringement, and trade secret misappropriation. Business torts such as passing off, false advertising, and tortious interference with business relations have also formed the bases of investigations.
Read the court decisionRead the full story...Reprinted courtesy of
Ric Macchiaroli, PillsburyMr. Macchiaroli may be contacted at
ric.macchiaroli@pillsburylaw.com