Floating Cities May Be One Answer to Rising Sea Levels
August 07, 2022 —
Adam Minter - BloombergThanks to climate change, sea levels are lapping up against coastal cities and communities. In an ideal world, efforts would have already been made to slow or stop the impact. The reality is that climate mitigation remains difficult, and the 40% of humanity living within 60 miles of a coast will eventually need to adapt.
One option is to move inland. A less obvious option is to move offshore, onto a floating city.
It sounds like a fantasy, but it could real, later if not sooner. Last year, Busan, South Korea's second-largest city, signed on to host a prototype for the world's first floating city. In April, Oceanix Inc., the company leading the project, unveiled a blueprint.
Representatives of SAMOO Architects & Engineers Co., one of the floating city's designers and a subsidiary of the gigantic Samsung Electronics Co., estimate that construction could start in a "year or two," though they concede the schedule might be aggressive. “It's inevitable,” Itai Madamombe, co-founder of Oceanix, told me over tea in Busan. “We will get to a point one day where a lot of people are living on water.”
Read the court decisionRead the full story...Reprinted courtesy of
Adam Minter, Bloomberg
Court Bars Licensed Contractor From Seeking Compensation for Work Performed by Unlicensed Sub
June 06, 2022 —
Garret Murai - California Construction Law BlogIt all started with a tree.
A eucalyptus tree to be exact.
What followed is one of the more important cases to be decided under Business and Professions Code section 7031 in recent years. Yes, that Section 7031. The statute variously described by the state’s courts as “harsh[ ],” draconian” and “unjust,” but, importantly, nevertheless valid.
Under Section 7031, an unlicensed contractor is barred from seeking compensation for work requiring a contractor’s license. This has been called the “shield.” However, in addition to the “shield,” project owners can also employ Section 7031’s “sword,” and seek disgorgement of all monies paid to an unlicensed contractor. Section 7031’s “shield” and “sword” applies even if the project owner knew that the contractor was unlicensed. They also apply even if the unlicensed contractor’s work was flawless. And they also apply even if a contractor was unlicensed during a portion of its work. This is because, as courts have stated, Section 7031 is a consumer protection statute intended to protect the public from unlicensed contractors and applies irrespective of the equities.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Recent Opinions Clarify Enforceability of Pay-if-Paid Provisions in Construction Contracts
May 29, 2023 —
Patrick McKnight - The Dispute ResolverSeveral recent opinions and legislative actions have brought the controversial nature of pay-if-paid provisions into focus in early 2023. Pay-if-paid provisions are contractual mechanisms designed to shift the risk of non-payment from General Contractors to lower-tier subcontractors. In other words, pay-if-paid provisions generally do not require payment to downstream subs until after the GC or Prime are themselves paid in-full by the owner. Recent developments reflect the differing approaches taken by courts when addressing pay-if-paid provisions, ranging broadly from prohibition to full enforceability. Other jurisdictions fall somewhere in the middle, viewing such provisions with varying amounts of skepticism on the grounds heir impact on smaller downstream subs is disproportionate and unfair.
Pay-if-paid provisions are often contrasted against “pay-when-paid” provisions. Pay-when-paid provisions may require payment within a specified duration but remove the upstream contractor’s payment in-full as a condition precedent. The brief discussion below will not explore pay-when-paid, no damage for delay provisions, or statutory prompt payment acts. Instead, this article serves as a primer on recent legal developments related to pay-if-paid provisions exclusively.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick McKnight, Fox Rothschild LLPMr. McKnight may be contacted at
pmcknight@foxrothschild.com
Multiple Occurrences Found For Claims Against Supplier of Asbestos Products
May 07, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe federal district court found that various claims for bodily injury against a supplier of asbestos products arose from multiple occurrences, increasing indemnity amounts available under the policy. Westfield Ins. Co. v. Continental Ins. Co., 2015 U.S. Dist. LEXIS 45437 (N.D. Ohio April 7, 2015).
Mahoning Valley Supply Company (MVS) was sued by numerous claimants who alleged that they had been injured by asbestos-containing products manufactured by third parties, but supplied by MVS. The claimants alleged exposure to asbestos fibers at a variety of job sites, on numerous dates, and under a variety of conditions. Two insurers shared defense and indemnity costs.
In 2013, Continental informed MVS that the three policies issued to MVS were nearly exhausted. Therefore, the parties disputed whether MVS' asbestos claims arose out of a single "occurrence" rather than multiple occurrences. The policies defined "occurrence" as "an accident, including continuous or repeated exposure to conditions, which results in bodily injury or property damage neither expected nor intended from the standpoint of the insured."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
4 Lessons Contractors Can Learn From The COVID-19 Crisis
May 25, 2020 —
Patrick Hogan - Handle.comAt the start of 2020, the industry outlook in construction was positive. Many contractors were optimistic about what the year had in store for construction businesses in terms of profit, expansion of operations, and even payment issues. That was until the COVID-19 pandemic put a wrench in everyone’s business plans.
There’s no question about how huge the impact of the novel coronavirus crisis is on business operations. With the federal and state governments implementing strict measures to slow down the spread of COVID-19, construction businesses are experiencing significant delays and disruptions in their operations. Because of the lockdowns and stay-at-home orders, many construction projects are forced to postpone operations or, worse, cancel them altogether.
Nevertheless, there are lessons in the COVID-19 pandemic that contractors can learn. Here are some of them.
1. Contractors need to be proactive in meeting preliminary notice requirements
Cash is tight in times of crisis. As the economy comes to a standstill, construction businesses will need to deal with decreasing profits. They may even have to dip into their own cash reserves to cover fixed expenses and their employees’ salaries.
In times like this, it is crucial that contractors perform due diligence in protecting their right to get paid. The first step in doing so is to prepare
preliminary notices. These notices are an important step in the mechanics lien process and without them, chances contractors will not be able to recover the unpaid compensation for the materials they furnished and services they rendered.
2. Force majeure provisions are crucial parts of a contract
The novel coronavirus pandemic has highlighted the importance of force majeure provisions in construction contracts. Before the COVID-19 crisis hit business operations, force majeure provisions were typically considered as simple boilerplate clauses. This means they were just there as a standard part of contracts.
However, the same force majeure clauses, as well as impossibility of performance provisions, have become crucial in the current crisis. As many construction businesses experience difficulties with their operations, they may not be able to fulfill their contractual responsibilities. The said clauses can give contractors a much-needed reprieve.
As the current crisis continues, contractors should review contracts as these provisions can give them more time to finish the job. And in the hopefully near future when the crisis ends, business owners should review the contract creation process and ensure that these clauses included in contracts will be able to address the impact of situations similar to COVID-19.
3. Having solid internal communication is crucial
There’s a lot of uncertainty with the COVID-19 situation. With work operations temporarily stopping, the circumstances can be quite stressful for employees. There will be doubts and fears within your workforce on whether work will be back to normal as soon as possible or not.
Keeping your workforce well-informed and trusting of your organization is crucial, especially in this time of uncertainty. That is why it is paramount that you have a solid internal communication infrastructure to disseminate information about the current work situation and the next steps that the business will take. In addition, only through proper employee communication can the implementation of social distancing and hygiene measures be effective.
4. Contractors can benefit from flexible work arrangements
As the coronavirus crisis has made it necessary for everyone to stay at home, construction businesses should look for ways to continue operations. Expanded work arrangements such as work-from-home setups may just be the solution.
Of course, most of the physical work that is needed to be done on-site will be impossible to do at home, but office-based functions such as sales, client relations, design, and administrative roles can still continue. This can even have additional benefits to productivity and health. And when the crisis is over, business owners should consider incorporating these work arrangements into their operations permanently.
The COVID-19 crisis is not showing any sign of stopping soon, and even when it ends, it will take quite a long time before we can be back to business as usual. As the crisis continues, however, business owners should take the situation as a learning experience.
Once the COVID-19 crisis is over, it will take a long time for things to go back to normal. In fact, things may not end up going back to the way they were before and businesses will need to adapt to the new normal. However the situation evolves, business owners should take this opportunity to learn new things and maintain resilience in trying times.
About the Author:
Patrick Hogan is the CEO of Handle.com, where they build software that helps contractors, subcontractors, and material suppliers with late payments. Handle.com also provides funding for construction businesses in the form of invoice factoring, material supply trade credit, and mechanics lien purchasing.
Read the court decisionRead the full story...Reprinted courtesy of
California Supreme Court Holds “Notice-Prejudice” Rule is “Fundamental Public Policy” of California, May Override Choice of Law Provisions in Policies
November 12, 2019 —
Anthony L. Miscioscia & Timothy A. Carroll - White and Williams LLPOn August 29, 2019, in Pitzer College v. Indian Harbor Insurance Company, 2019 Cal. LEXIS 6240, the California Supreme Court held that, in the insurance context, the common law “notice-prejudice” rule is a “fundamental public policy” of the State of California for purposes of choice of law analysis. Thus, even though the policy in Pitzer had a choice of law provision requiring application of New York law – which does not require an insurer to prove prejudice for late notice of claims under policies delivered outside of New York – that provision can be overridden by California’s public policy of requiring insurers to prove prejudice after late notice of a claim. The Supreme Court in Pitzer also held that the notice-prejudice rule “generally applies to consent provisions in the context of first party liability policy coverage,” but not to consent provisions in the third-party liability policy context.
The Pitzer case arose from a discovery of polluted soil at Pitzer College during a dormitory construction project. Facing pressure to finish the project by the start of the next school term, Pitzer officials took steps to remediate the polluted soil at a cost of $2 million. When Pitzer notified its insurer of the remediation, and made a claim for the attendant costs, the insurer “denied coverage based on Pitzer’s failure to give notice as soon as practicable and its failure to obtain [the insurer’s] consent before commencing the remediation process.” The Supreme Court observed that Pitzer did not inform its insurer of the remediation until “three months after it completed remediation and six months after it discovered the darkened soils.” In response to the denial of coverage, Pitzer sued the insurer in California state court, the insurer removed the action to federal court and the insurer moved for summary judgment “claiming that it had no obligation to indemnify Pitzer for remediation costs because Pitzer had violated the Policy’s notice and consent provisions.”
Reprinted courtesy of
Timothy Carroll, White and Williams and
Anthony Miscioscia, White and Williams
Mr. Carroll may be contacted at carrollt@whiteandwilliams.com
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
William Lyon to Acquire RSI Communities
February 22, 2018 —
Dave Suggs - CDJ STAFFAccording to the article “William Lyon Agrees to Buy RSI Communities $460 million deal plants Lyon in Texas and adds to Inland Empire land holdings” published on the website Builder, the Newport Beach home builder is purchasing the Southern California and Texas home builder. This will be Lyon Homes’ first venture in the state of Texas.
RSI Communities works within both San Antonio and Austin, Texas as well as Southern California and the Inland Empire. It was founded by Todd Palmaer, a home building expert and Ron Simon, a building products expert and Newport Beach businessman. First time home buyers have been RSI’s main target.
President and CEO of RSI, Tod Palmaer is optimistic about the acquisition “We are delighted to have our company join the William Lyon Homes organization. We have a great deal of confidence in the William Lyon Homes platform and its executive management team, and believe that its acquisition of RSI Communities will add to Lyon’s continued success in its current and new markets.”
Pat Donahue who has almost 30 years of experience in home building, will serve as President to the Inland Empire Division. John Bohnen, RSI’s present Chief Operating Officer, will be the regional president in Texas. Mr. Bohnen has previously held executive positions with numerous home builders. William Lyon’s president and CEO Mark R. Zaist is excited about adding RSI’s key players to their team, and had this to say about the purchase. “The acquisition of RSI represents our most significant acquisition since our entry into Portland and Seattle with the Polygon Northwest Homes acquisition in 2014 and furthers our strategy of building in the strongest markets in the Western U.S., while also strengthening our pipeline in Southern California, as we continue our mission of being the premier Western Regional home builder.”
Read the court decisionRead the full story...Reprinted courtesy of
Negligent Construction an Occurrence Says Ninth Circuit
June 30, 2011 —
CDJ STAFFOne June 27, the US Court of Appeals has rejected an appeal from Mid-Continent Casualty Company. Mid-Continent had appealed a summary judgment granted to Titan Construction Company.
Titan Construction had built condominiums for the Williamsburg Condominium Association, which later filed a construction defect lawsuit against Titan and other defendants. Titan settled with the developer, Kennydale, assigning its rights against Mid-Continent to Kennydale. Mid-Continent filed suit, claiming that “it had no obligation to indemnify or defend Titan, Kennydale, or various other defendants.” The district court found in favor of Mid-Continent, granting a summary judgment, concluding that Titan’s insurance covered “occurrences,” and none had taken place.
On appeal, the court found that the negligent construction of the condominiums constituted an “occurrence” The case was remanded and the district court this time found in favor of Titan, “concluding that Mid-Continent failed to raise a triable issue as to the applicability of the remaining policy exclusions.
The Ninth Circuit Court of Appeals has now affirmed that decision and Titan’s summary judgment stands.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of