Performance Bonds: Follow the Letter of the Bond and Keep The Surety Informed
December 06, 2021 —
Bill Shaughnessy, Jones Walker, LLP - ConsensusDocsConstruction surety bonds are risk management tools utilized by parties on large construction projects. However, bonds are not insurance, and a surety is not an “insurer” of the project. Different from insurance, a surety’s obligation to act typically arises if the principal fails to perform in accordance with the construction contract, and if the claimant satisfies the conditions precedent to enforcing the bond.[1]
This article focuses exclusively on performance bonds on private projects,[2] and highlights practical considerations and surety defenses to enforcement of the performance bond.[3] Spoiler alert – the party making a claim on the bond must strictly adhere to the conditions precedent set forth in the bond throughout the construction project and when calling upon the surety to take action, otherwise the performance bond may be rendered void and unenforceable.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Shaughnessy, Jones Walker, LLPMr. Shaughnessy may be contacted at
bshaughnessy@joneswalker.com
How One Squirrel Taught us a Surprising Amount about Insurance Investigation Lessons Learned from the Iowa Supreme Court
April 03, 2019 —
Graham C. Mills - Newmeyer & DillionA recent decision issued by the Iowa Supreme Court, City of West Liberty, Iowa v. Employers Mutual Casualty Company, highlights the importance for a policyholder to investigate a loss fully so that a wide range of evidence can be gathered and presented to show why there is coverage. The facts of City of West Liberty are a little unusual, but its lesson is not limited to Iowa insurance law; the issues litigated in this case show the value of investigating what caused a loss regardless of whether the loss occurred in California, Iowa, or elsewhere.
Background on the Case
City of West Liberty involved an insurance coverage dispute between a municipality owned electrical power plant and its insurance company. The dispute arose from a single adventurous squirrel who climbed onto an outdoor electrical transformer, touching two different parts of the power plant: a portion of the steel frame and a bare cable clamp. In doing so, the squirrel created a “conductive path,” in the words of the Iowa Supreme Court, between the high voltage clamp and the grounded frame. The path, once created, caused significant damage to the transformer and other electrical equipment at the city’s power plant.
The city submitted a claim for the resulting damage, but the insurance company denied it. The insurer denied based on an exclusion in the insurance policy for property damage “caused by arcing or by electrical currents other than lightning.” According to the insurance company, the squirrel had no role in causing the damage; all of the damage resulted from arcing, which was excluded from coverage. The ensuing lawsuit focused upon whether the squirrel had a role in causing the damage. If yes, then there would be coverage according to Iowa insurance law; when a loss results from two causes, one of which is covered and the other is not, then there is coverage if the loss occurs from the covered cause. Due to this legal standard, the city contended that, apart from the arcing causing any damage, the squirrel caused the damage too. Because the insurance policy provided protection against mischievous actions performed by squirrels, the city contended that it was entitled to coverage, even if the excluded arcing contributed to the same damage too. Unfortunately, for the city, the Iowa Supreme Court rejected that argument, finding instead that the property damage resulted only from the arcing, which was excluded from coverage. In reaching its conclusion, the court absolved the squirrel of any wrongdoing, finding that it did not cause any of the property damage.
Read the court decisionRead the full story...Reprinted courtesy of
Graham C. Mills, Newmeyer & DillionMr. Mills may be contacted at
graham.mills@ndlf.com
From Singapore to Rio Green Buildings Keep Tropical Tenants Cool
June 07, 2021 —
Andrew Janes & Shawna Kwan - BloombergOn a typically hot and humid afternoon in Singapore, a fresh breeze blows beneath the canopy of the South Beach development, keeping temperatures several degrees cooler than on the surrounding streets.
The rippling 280-meter (919 feet) wave of steel-and-aluminum runs the length of the Norman Foster-designed complex, funneling prevailing winds over outdoor patrons of restaurants and bars and saving on air conditioning for the mixed-use complex. The canopy is covered with solar panels and catches rainwater to irrigate the gardens.
Offices and apartment blocks designed to be green are springing up all over the world as architects reverse almost a century of trying to insulate workers from nature and instead try to adapt structures to their natural surroundings. The change is being driven by stricter building codes, a desire to cut energy costs and, in particular, demands from corporations and startups that need to show shareholders and customers they are meeting environmental standards.
Reprinted courtesy of
Andrew Janes, Bloomberg and
Shawna Kwan, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Is Your Contract “Mission Essential?” Recovering Costs for Performing During a Force Majeure Event Under Federal Regulations
May 10, 2022 —
Joneis M. Phan & Sarah K. Bloom - ConsensusDocsFederal contractors have faced unprecedented challenges performing during the COVID-19 pandemic. Additional costs have included delays and inefficiencies, site closures, quarantines, unavailability of supplies and materials, and full shutdowns of subcontractor operations. For contractors performing under fixed price contracts, the cost impact of COVID-19 was likely severe.
The Federal Acquisition Regulation (“FAR”) recognizes “epidemics” as a force majeure event that may excuse non-performance. Many federal contracts include some version of the Default clause, which prevents the government from terminating a contractor for default due to impacts of force majeure events that are beyond a contractor’s control, such as an epidemic. See, e.g., FAR 52.249-10. See also Pernix Serka Joint Venture v. Dep’t of State, CBCA No. 5683 (Apr. 20. 2020). The Default clause, however, operates as a shield from liability, not a sword authorizing recovery. Contractors are now left wondering whether any avenue exists to recover additional costs incurred after performing in the face of the COVID-19 pandemic.
In response to a likely influx of claims and requests for equitable adjustment due to COVID-19 impacts, the federal government largely took the position that contractors were entitled to extensions of time, but not to additional costs. This article explores the avenues that may be available for contractors to recover costs for performing during a force majeure event that would otherwise be non-compensable.
Reprinted courtesy of
Joneis M. Phan, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs and
Sarah K. Bloom, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs).
Mr. Phan may be contacted at jphan@watttieder.com
Ms. Bloom may be contacted at sbloom@watttieder.com
Read the court decisionRead the full story...Reprinted courtesy of
Sanctions Award Against Pro Se Plaintiff Upheld
June 22, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe plaintiff's failure to timely name an expert witness in his bad faith action led to sanctions being awarded against him in favor of the insurer. Black v. Fireman's Fund Ins. Co., 2020 Cal. App. Unpub. LEXIS 2477 (Cal. Ct. App. April 23, 2020).
After Black's claim was denied by Fireman's Fund, he communicated with company through letters, emails and phone conversations. Black complained that Fireman's Fund handled his claim improperly, engaged in illegal activities and had ties to the Nazi regime in Germany. Fireman's Fund sued Black alleging that his communications amounted to civil extortion, interference with contractual relations, interference with prospective economic advantage, and unfair business practices. Fireman's Fund eventually dismissed its complaint without prejudice.
Black, however, had filed a cross-complaint in which he asserted a number of claims, including bad faith. Black designated attorney Randy Hess as an expert on insurance claims. Over the next year and a half, Fireman's Fund repeatedly attempted to take Hess's deposition. In March 2018, Fireman's Fund moved to compel the deposition or exclude the testimony. The court set a July 20, 2018 deadline for the disposition to take place or else the testimony would be excluded.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
A Primer on Suspension and Debarment for Federal Construction Projects
August 10, 2020 —
Hal J. Perloff - Construction ExecutiveWe’ve all heard the expression that those who deal with the government must turn square corners. This is because the government has a broad array of tools at its disposal to motivate, coax and cajole contractors and federal grant recipients to play by the rules. Those tools include harsh measures such as criminal prosecution and civil false claims act enforcement on the one hand and poor CPARS ratings on the other. A seemingly less severe administrative option available to the government is suspension and debarment. However, any entity that has been suspended or debarred knows that these measures can prove harsh and disruptive.
While the numbers of suspensions and debarments have declined from the all-time high in 2011, there is still significant activity. In its FY 2018 report, the Interagency Suspension and Debarment Committee reported 2444 referrals, 480 suspensions, 1542 proposed debarments and 1334 debarments. The number of referrals for suspension and debarment in FY 2018 is almost exactly the same as the number of GAO bid protests filed that year.
WHAT IS SUSPENSION AND DEBARMENT?
Suspension and debarment are the government’s tools to avoid entities it views as a high risk for poor performance, fraud, waste and abuse. Suspension and debarment preclude a business entity or individual from contracting with the government or from receiving grants, loans, loan guarantees or other forms of assistance from the government. A suspension is a temporary exclusion when the government determines immediate action is necessary pending the completion of an investigation or legal proceeding. A debarment is an exclusion for a defined, reasonable period of time—often three years.
Reprinted courtesy of
Hal J. Perloff, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Perloff may be contacted at
hal.perloff@huschblackwell.com
User Interface With a Building – Interview with Esa Halmetoja of Senate Properties
September 14, 2017 —
Aarni Heiskanen - AEC BusinessArchitect Mies van der Rohe once said that, “An office is a machine for working in.” From a maintenance person’s point of view that might be true. For a user, an office should offer a productive working environment. A pilot project, led by Esa Halmetoja of Senate Properties, is trying to find out how a digital twin of a building would serve both the needs of the maintenance worker and the office worker.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
info@aepartners.fi
Construction Contract Basics: Attorney Fee Provisions
November 13, 2023 —
Christopher G. Hill - Construction Law MusingsI have discussed the need for
attorney fee provisions in your construction contracts in prior posts here at Construction Law Musings, but thought it merited a restatement of the reasons for the inclusion of such fee provisions (and changing of such provisions when presented) here with the second of my
construction contract basics posts.
Why would you want such a provision? The answer is that without it, or a statute specifically allowing for such fees, a Virginia court will not award your attorney fees without such a provision. Virginia, and a lot of other states, follow the so-called “American Rule” when it comes to attorney fees and costs. In short, that rule states that the parties to litigation pay their own way unless they agree otherwise. While it may seem unfair to make a successful litigant pay for the privilege of being right, that is the rule in Virginia. Throw in the fact that Virginia courts
strictly construe construction contracts and voila we have a situation where without a provision in the contract stating that one party or both will be able to collect attorney fees should that contractor or subcontractor prevail, a construction professional that gets sued (whether rightly or wrongly) will be left with a hefty attorney fees bill and no way to recoup those fees through the courts or any other method.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at