Connecticut Federal District Court Keeps Busy With Collapse Cases
October 19, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court for the district of Connecticut has faced a slew of collapse cases, recently dismissing several such cases.
The policies under consideration in each case cover the "entire collapse of a covered building structure" or "the entire collapse of part of a covered building structure." The collapse must be "a sudden and accidental physical loss caused by one of a list of specific causes such as defective methods or materials. In most of the recent cases, the insured alleged that the concrete in basement walls or foundations was cracking due to a chemical reaction. It was further alleged that the chemical reaction would continue to progressively deteriorate, rendering the building structurally unstable.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Wisconsin Court Enforces Breach of Contract Exclusion in E&O Policy
July 21, 2018 —
TLSS Insurance Law BlogIn its recent decision in Crum & Forster Specialty Ins. Co. v. GHD Inc.,2018 U.S. Dist. LEXIS 111827 (E.D. Wisc. July 5, 2018), the United States District Court for the Eastern District of Wisconsin had occasion to consider the application of a breach of contract exclusion in a professional liability policy.
Crum’s insured, DVO, was sued in connection with its contract to construct a biogas converter mechanism. The underlying suit alleged a sole cause of action; namely, breach of contract based on DVO’s failure to have fulfilled its obligations to design the mechanism to specification.
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman Straus & Shrewsberry LLP
Fla. Researchers Probe 'Mother of All Sinkholes'
August 24, 2017 —
Thomas F. Armistead - Engineering News-RecordIt will take months to complete remediation of the largest sinkhole in Pasco County, Fla.’s recent history, county officials say. Seven houses have been lost or condemned since the sinkhole was reported at 7:21 a.m. on July 14. That day, two houses collapsed into the hole, which initially measured 225 ft long and 50 ft deep. As the cavity’s dimensions grew to between 260 ft and 180 ft, the county red-tagged five additional houses.
Read the court decisionRead the full story...Reprinted courtesy of
Thomas F. Armistead, ENRENR may be contacted at
ENR.com@bnpmedia.com
Does Article 2 of the Uniform Commercial Code Impact Your Construction Project?
November 07, 2022 —
Chris Cazenave - ConsensusDocsThe Uniform Commercial Code (UCC) is a set of statutes governing commercial transactions. Every state has adopted the UCC or some version of it. Understanding when and how the UCC applies to construction contracts is important because it can affect the agreement’s terms.
Article 2 of the UCC applies to the sales of goods, which the UCC defines very broadly to mean “all things (including specialty manufactured goods) which are movable . . . other than money in which the price is to be paid . . . .” UCC § 2-105. For the construction industry, UCC Article 2 governs most, if not all, purchases of materials and equipment installed or incorporated into the project. As a result, contractors and subcontractors should be familiar with the circumstances under which Article 2 may apply and how it may affect the project.
This article provides a brief overview of when Article 2 may affect your construction project and why it matters. The article also generally covers the UCC’s potential effects on the applicable statute of limitations, implied warranties, and when the obligation to make the payment arises.
Read the court decisionRead the full story...Reprinted courtesy of
Chris Cazenave, Jones Walker LLP (ConsensusDocs)Mr. Cazenave may be contacted at
ccazenave@joneswalker.com
Did You Really Accept That Bid? – How Contractors Can Avoid Post-Acceptance Bid Disputes Over Contract Terms
July 28, 2016 —
David A. Harris & Steven M. Cvitanovic – Haight Brown & Bonesteel LLPWhen California general contractors submit bids to an owner, can they force their subcontractors to honor their bids? Can they recover damages if the subcontractor later refuses to do so?
While the general rule in California is that a general contractor who reasonably relies on a subcontractor’s bid may recover damages when the subcontractor reneges, the Court of Appeal for the Second Appellate District recently held that there is a substantial and important exception to the general rule.
In Flintco Pacific, Inc. v. TEC Management Consultants, Inc. (LASC No. YC067984), the Court of Appeal held that where a general contractor requires a subcontractor to enter into a “standard-form subcontract” which materially differs from the subcontractor’s bid, the general contractor has rejected the subcontractor’s bid and has instead issued a counteroffer. The subcontractor is thereafter free to walk, or accept the new terms. If the subcontractor walks, the general contractor may not seek to enforce the terms of the subcontract or seek reliance damages.
Reprinted courtesy of
David A. Harris, Haight Brown & Bonesteel LLP and
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP
Mr. Harris may be contacted at dharris@hbblaw.com
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Don’t Ignore the Dispute Resolution Provisions in Your Construction Contract
June 05, 2023 —
David Adelstein - Florida Construction Legal UpdatesDon’t ignore dispute resolution provisions in a construction contract. Sometimes, you may want to. But dispute resolution provisions should be one of the first provisions you look to when a dispute arises recognizing these provisions will be raised if you fail to comply. Not only will they be raised, but the presumption is they will be enforced. This is the situation that was raised in Seminole County, Florida v. APM Construction Corp., 2023 WL 3555356 (Fla. 5th DCA 2023).
Here, a contractor was terminated for cause by Seminole County. The contractor then filed suit against the County. The County moved to dismiss the lawsuit because the contractor failed to comply with contractual presuit administrative procedures in the contract prior to filing a lawsuit. While the trial court denied the County’s motion to dismiss, the appellate court granted the County’s petition for writ of certiorari quashing the trial court’s order denying the motion to dismiss. For purposes of granting the writ of certiorari, the appellate court held irreparable harm existed because “certiorari jurisdiction is properly exercised when a trial court permits a party to litigate when there is a contractual or legal obligation to first administrative proceed.” Seminole County, supra, at *2.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
The 2023 Term of the Supreme Court: Administrative and Regulatory Law Rulings
December 03, 2024 —
Anthony B. Cavender - Gravel2Gavel Construction & Real Estate Law BlogIt is instructive to review the Supreme Court’s record in its most recent term, concentrating on regulatory and administrative law cases, which are usually back-burner issues. But not this term.
The Supreme Court began the current term on October 7, 2024. The Court has already chosen many cases to review in the new term, and it promises to be as interesting as the 2023 term, which produced several significant rulings affecting regulatory and administrative law, chiefly the Loper Bright Enterprises ruling. Loper Bright overturned the Court’s landmark administrative law ruling of Chevron, USA v. Natural Resources Defense Council, Inc., 467 U.S. 837 (1984).
The Background to Loper Bright
In 1984, the Supreme Court decided Chevron USA, Inc. v. National Resource Defense Council. (See 467 U.S. 839 (1984).) The unanimous decision, written by Justice Stevens, reversed then-D.C. Circuit Judge Ruth Bader Ginsburg’s ruling that set aside EPA’s Clean Air Act “bubble policy,” which was intended to provide regulatory relief from certain EPA permitting requirements.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Back Posting with Thoughts on Lien Waivers
May 20, 2015 —
Christopher G. Hill – Construction Law MusingsAfter a week of being unable to post due to the rigors of my solo construction practice, I’m back on the blogging train. For those of you that missed my new musings this past week, I hope that you had a chance to look through some of the past Guest Post Friday posts for some good stuff to read.
During the course of my busy week last week, a question came up regarding the mechanic’s lien waivers that commercial construction companies routinely execute as part of the payment process. The waiver forms vary, but each essentially states that in exchange for payment the payee, whether a subcontractor or supplier (or even general contractor) waives its future rights to record a mechanic’s lien for the work that is covered by the payment received. Most if not all of these forms further require a certification that the funds paid will either be used to pay suppliers or that suppliers have already been paid. This general description is not the reason for this post.
As is always the case in the Commonwealth of Virginia where the contract is king and a court is unlikely to reinterpret any written contractual document, the devil is in how that waiver is worded. Some waivers are worded in such a way that they essentially require a payee to certify receipt of the funds prior to payment being received. These same forms require the same pre-payment certification that all suppliers and subcontractors of the payee have already been paid. In short they require a payee to both place complete trust in the payor that the check will be paid and that the check will not bounce while in many cases (often with an unstated “wink and nod”) claiming payment was already made when all know the likelihood is that it has not.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at