Tenth Circuit Finds Appraisal Can Decide Causation of Loss Under Colorado Law
November 29, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe Tenth Circuit determined that the Colorado Supreme Court would agree with other state courts that appraisers can decide the causation of a loss. Bonbeck Parker, LLC v. The Travelers Indem. Co. of Am., 2021 U.S. App. LEXIS 29607 (10th Cir. Oct. 1, 2021).
A hailstorm damaged three buildings owned by BonBeck. A claim was submitted to Travelers under BonBeck's commercial property policy. Travelers acknowledged that some hail damage occurred to all the buildings except for the roofs. Travelers paid $34,200 for damage to the buildings. Coverage for the roof damage was denied because it resulted not from the hail damage but from uncovered events like wear and tear, deterioration, and improperly installation.
BonBeck requested an appraisal. Travelers insisted that the appraisal would only determine the amount of loss of covered claims. BonBeck rejected these conditions and Travelers filed suit.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
A New Study on Implementing Digital Visual Management
July 31, 2024 —
Aarni Heiskanen - AEC BusinessA new paper, “Implementing Digital Visual Management: A Case Study on Challenges and Barriers,” discusses situational management in complex infrastructure projects. It’s worth reading for anyone interested in improving project management with digital tools.
A complex infrastructure project
The authors interviewed nine project management professionals who worked for the client on constructing the western part of the Metro in Helsinki and Espoo, Finland. The project lasted eight years and had a budget of 1,200 million euros.
The project used a Digital Visual Management (DVM) tool, and the paper discusses the challenges and barriers faced during the tool’s implementation. At the time of the study, the system was used to manage the final documentation and testing status.
KPI management
The project management team was involved in developing a system for combining collected data into a central dashboard and using it to manage the whole project.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
New York Appellate Team Obtains Affirmance of Dismissal of Would-Be Labor Law Action Against Municipal Entities
August 12, 2024 —
Lewis Brisbois NewsroomNew York, N.Y. (July 11, 2024) - In Charlot v. City of New York, ___ A.D.3d ___, 2024 NY Slip Op 03161 (2d Dep’t 2024), New York Associate Dean Pillarella, a member of the Appellate Practice, recently obtained an affirmance of the lower court’s dismissal of the plaintiff’s action against the City of New York (“the City”) for failure to timely serve a notice of claim. New York Partner Meghan Cavalieri, a member of the Construction Practice, and her team authored and argued the initial motion to dismiss.
The plaintiff alleged to have sustained injuries as a result of a construction-site accident on December 8, 2020, on City-owned property in the course of the construction of a school by the New York City School Construction Authority. N.Y. General Municipal Law (“GML”) § 50-e(1)(a), requires service of a notice of claim within 90 days after the claim arises as a condition precedent to the commencement of a tort action. The plaintiff served no notice of claim until June 2021 and commenced an action in January 2022, alleging violations of N.Y. Labor Law §§ 240(1), 241(6), and 200. Given the plaintiff’s failure to comply with GML § 50-e(1)(a), Meghan and her team rejected the notices of claim as untimely. The plaintiff then moved for leave to deem the notices of claim timely served nunc pro tunc. In response, Meghan and her team opposed the motion and cross-moved to dismiss the action.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Pending Sales of Existing Homes in U.S. Decline for Eighth Month
March 31, 2014 —
Shobhana Chandra – BloombergContracts to purchase previously owned U.S. homes unexpectedly fell in February for an eighth straight month, a sign of further weakness in the industry.
The index of pending home sales decreased 0.8 percent after a 0.2 percent drop the prior month that was previously reported as a gain, figures from the National Association of Realtors showed today in Washington. The median forecast of 39 economists surveyed by Bloomberg called for a 0.2 percent rise.
Colder-than-normal weather probably played a role in discouraging prospective buyers faced with rising mortgage rates, higher prices and limited supply of cheaper properties. At the same time, the Realtors group said buyer traffic is stabilizing, which may help spur demand as temperatures warm.
Read the court decisionRead the full story...Reprinted courtesy of
Shobhana Chandra, BloombergMs. Chandra may be contacted at
schandra1@bloomberg.net
Party Loses Additional Insured Argument by Improper Pleading
September 20, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe Archdiocese failed to plead breach of contract against the County for failure to name the Archdiocese as an additional insured under the liability policy. Pachella v. Archdiocese of Philadelphia, 2017 Pa. Commw. Unpub. LEXIS 595 (Pa. Commw. Ct. Aug. 14, 2017).
Richard and Pachella filed a complaint against the Archdiocese, alleging that Mrs. Pachella was injured when she tripped and fell on the sidewalk outside of St. Patrick's Parish. At the time, the County was leasing St. Patrick's premises for use as an election polling place. The Archdiocese filed a third party complaint alleging negligence and breach of contract claims under a Lease Agreement between St. Patrick's and the County.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
The Status of OSHA’s Impending Heat Stress Standard
May 30, 2022 —
Stephen E. Irving - ConsensusDocsThere has been much talk in the last several months about OSHA’s intent to establish a national standard to prevent heat-related injury and illness. OSHA’s Region VI, covering the states of Texas, Louisiana, Arkansas, Oklahoma, and New Mexico
[1], has had a regional emphasis program dealing with the hazards of heat stress for more than two decades, and much of the talk about a new national standard suggests modeling some aspects of the standard after the Region VI program. Region VI’s long-standing program emphasizes water, rest, and shade; acclimatization; and responding to medical emergencies.
In October 2021, OSHA issued its advance notice of proposed rulemaking (ANPRM) for Heat Injury and Prevention. The ANPRM rulemaking established a new Heat Injury and Illness Prevention Work Group within the National Advisory Committee on Occupational Safety and Health (NACOSH.)
Read the court decisionRead the full story...Reprinted courtesy of
Stephen E. Irving, Peckar & AbramsonMr. Irving may be contacted at
sirving@pecklaw.com
Contract Not So Clear in South Carolina Construction Defect Case
November 07, 2012 —
CDJ STAFFThe South Carolina Court of Appeals has reversed a partial summary judgment issued by one of the lower courts in the case of The Retreat at Edisto Co-Owners Association v. The Retreat at Edisto. The underlying issues of the case deal with a construction defect complaint.
The lower court had concluded “Developer’s ‘First Amendment’ to the Master Deed required the Developer to satisfy the provision in the paragraph labeled ‘Master Deed Amendment or Phase II’ as a condition precedent to its election to proceed with the development of Phase II.”
The appeals court found that “the language of the First Amendment to the Master Deed is susceptible to more than one interpretation.” The court additionally concluded that the “Developer presented the requisite scintilla of evidence on the question of its intent in order to establish a genuine issue of material fact. As the material facts were in dispute, the appeals court reversed the summary judgment and remanded the case to the circuit court for further proceedings.
Read the court decisionRead the full story...Reprinted courtesy of
Enforcement Of Contractual Terms (E.G., Flow-Down, Field Verification, Shop Drawing Approval, And No-Damage-For-Delay Provisions)
May 04, 2020 —
David Adelstein - Florida Construction Legal UpdatesWhat you contractually agree to matters, particularly when you are deemed a sophisticated entity. This means you can figuratively live or die by the terms and conditions agreed to. Don’t take it from me, but it take it from the Fourth Circuit’s decision in U.S. f/u/b/o Modern Mosaic, Ltd. v. Turner Construction Co., 2019 WL 7174550 (4th Cir. 2019), where the Court started off by stressing, “One of our country’s bedrock principles is the freedom of individuals and entities to enter into contracts and rely that their terms will be enforced.” Id. at *1.
This case involved a dispute between a prime contractor and its precast concrete subcontractor on a federal project. The subcontractor filed a Miller Act payment bond lawsuit. The trial court ruled against the subcontractor based on…the subcontract’s terms! So, yes, what you contractually agree to matters.
Example #1 – The subcontractor fabricated and installed precast concrete panels per engineering drawings. However, the parking garage was not built per dimensions meaning the panels it fabricated would not fit. The subcontractor had to perform remedial work on the panels to get them to fit. The subcontractor pursued the prime contractor for these costs arguing the prime contractor should have field verified the dimensions. The problem for the subcontractor, however, was that the subcontract required the subcontractor, not the prime contractor, to field verify the dimensions. Based on this language that required the subcontractor to field verify existing conditions and take field measurements, the subcontractor was not entitled to its remedial costs (and they were close to $1 Million). Furthermore, and of importance, the Court noted that the subcontract contained a flow down provision requiring the subcontractor to be bound by all of the terms and conditions of the prime contract and assume those duties and obligations that the prime contractor was to assume towards the owner. While this flow-down provision may often be overlooked, here it was not, as it meant the subcontractor was assuming the field verification duties that the prime contractor was responsible to perform for the owner.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com