Terms of Your Teaming Agreement Matter
July 30, 2019 —
Christopher G. Hill - Construction Law MusingsThese days in construction, and other pursuits, teaming agreements have become a great method for large and small contractors to work together to take advantage of various contract and job requirements from minority participation to veteran ownership. With the proliferation of these agreements, parties must be careful in how they draft the terms of these agreements. Without proper drafting, the parties risk unenforceability of the teaming agreement in the evewnt of a dispute.
One potential pitfall in drafting is an “agreement to agree” or an agreement to negotiate a separate contract in the future. This type of pitfall was illustrated in the case of InDyne Inc. v. Beacon Occupational Health & Safety Services Inc. out of the Eastern District of Virginia. In this case, InDyne and Beacon entered into a teaming agreement that provided that InDyne as Prime would seek to use Beacon, the Sub, in the event that InDyne was awarded a contract using Beacon’s numbers. The teaming agreement further provided:
The agreement shall remain in effect until the first of the following shall occur: … (g) inability of the Prime and the Sub, after negotiating in good faith, to reach agreement on the terms of a subcontract offered by the Prime, in accordance with this agreement.
InDyne was subsequently awarded a contract with the Air Force and shortly thereafter sent a subcontract to Beacon and requested Beacon’s “best and final” pricing. Beacon protested by letter stating that it was only required to act consistently with its original bid pricing. Beacon then returned the subcontract with the original bid pricing and accepting all but a termination for convenience provision. Shortly thereafter, InDyne informed Beacon that InDyne had awarded the subcontract to one of Beacon’s competitors. Beacon of course sued and argued that the teaming agreement required that InDyne award the subcontract to Beacon.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
What I Learned at My First NAWIC National Conference
September 25, 2023 —
Ivette Kincaid - Kahana FeldOn August 9-12, 2023, I attend my first National Association of Women in Construction (“NAWIC”) National Conference in beautiful Portland, Oregon. What is NAWIC, you ask? NAWIC originated as Women in Construction of Fort Worth, Texas and was founded in 1953 by sixteen women in the construction industry. Knowing that back then women only represented a fraction of the construction industry, the founders organized to create a support network for women to work in a male dominated field. The organization has grown by leaps and bounds and now consists of 115 chapters throughout the United States.
NAWIC’s core purpose is to “Strengthen and amplify the success of women in the construction industry.”
I joined this organization in December of 2022 at the suggestion of my law partner Jason Feld. Before Jason’s suggestion I had never heard of NAWIC. I joined the Orange County chapter and attended my first meeting in December and did not look back. In NAWIC I found a group of women kindred spirits in whom a found a commonality of interests, experiences, and goals. This is an organization that provides support, encouragement, education, and advocacy for women in all aspects of the construction industry. It also provides an outlet to share ideas, network and build relationships. I am happy to report that on September 12, 2023, I will be installed as one of the directors of the Orange County Chapter.
Read the court decisionRead the full story...Reprinted courtesy of
Ivette Kincaid, Kahana FeldMs. Kincaid may be contacted at
ikincaid@kahanafeld.com
Pending Home Sales in U.S. Increase Less Than Forecast
October 29, 2014 —
Michelle Jamrisko – BloombergThe number of contracts to buy existing homes rose less than forecast in September, signaling demand will probably plateau heading into the end of 2014.
The pending home sales index increased 0.3 percent after dropping 1 percent in August, the National Association of Realtors said today in Washington. The median projection in a Bloomberg survey of economists called for a 1 percent gain.
Home resales have yet to regain last year’s peak as still-tight credit and low inventories remain hurdles for the industry, which means residential real estate will make a limited contribution to the expansion. The recent drop in mortgage rates and pickup in hiring will probably help underpin demand, even as first-time buyers struggle to enter the market.
Read the court decisionRead the full story...Reprinted courtesy of
Michelle Jamrisko, BloombergMs. Jamrisko may be contacted at
mjamrisko@bloomberg.net
Where Breach of Contract and Tortious Interference Collide
July 18, 2022 —
Christopher G. Hill - Construction Law MusingsClaims for breach of contract are numerous in the construction law world. Without these claims we construction attorneys would have a hard time keeping the doors open. A 2021 case examined a different sort of claim that could arise (though, “spoiler alert” did not in this case) during the course of a construction project. That type of claim is one for tortious interference with business expectancy.
In Clark Nexsen, Inc. et. al v. Rebkee, the U. S. District Court for the Eastern District of Virginia gave a great explanation of the law of this type of claim in analyzing the following basic facts:
In 2018, Clark Nexsen, Inc. (“Clark”) and MEB General Contractors, Inc. (“MEB”) responded to Henrico County’s (“Henrico”) Request for Proposals (“RFP”) for the design and construction of a sport and convocation center (the “Project”). Henrico initially shortlisted Clark and MEB as a “design-build” team for the Project, but later restarted the search, issuing a second RFP. Clark and MEB submitted a second “design-build” proposal, but Henrico selected Rebkee Co. (“Rebkee”) for certain development aspects of the Project. MEB also submitted proposals to Rebkee, and Rebkee selected MEB as the design-builder for the Project. MEB, at Rebkee’s request, solicited proposals from three design firms and ultimately selected Clark as its design partner. From December 2019 to May 2020, Clark and MEB served as the design-build team to assist Rebkee in developing the Project. In connection therewith, Clark developed proprietary designs, technical drawings, and, with MEB, several cost estimates. In February 2020, MEB submitted a $294,334.50 Pay Application to Rebkee for engineering, design, and Project development work. Rebkee never paid MEB. Henrico paid MEB $50,000.00 as partial payment for MEB’s and Clark’s work. MEB then learned that Rebkee was using Clark’s drawings to solicit design and construction proposals from other companies. On July 23, 2020, Rebkee told MEB that Henrico directed it to cancel the design-build arrangement with MEB and Clark and pursue a different planning method. MEB and Clark sued and Rebkee for, among other claims, tortious interference with a business expectancy. Rebkee moved to dismiss the tortious interference claim.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Business Insurance Names Rachel Hudgins Among 2024 Break Out Award Winners
April 22, 2024 —
Hunton Insurance Recovery BlogWe are pleased to announce that counsel
Rachel E. Hudgins has been recognized as one of Business Insurance’s 2024 Break Out Award winners. The magazine’s Break Out Awards honor 40 top professionals each year from a competitive field of nominees who have under 15 years’ experience in the insurance and risk management sector and are “on track to be the next leaders in the risk management and property/casualty insurance field.”
Clients describe Rachel as their “chief contact for high-exposure coverage work.” She meets clients where they are with a curiosity and interest in their business strategies, as well as an ability to distill complex insurance concepts into digestible terms. Rachel also has depth of experience in coverage litigation. She has litigated hundreds of insurance coverage and bad faith claims in state and federal courts across the country and US territories.
Read the court decisionRead the full story...Reprinted courtesy of
Hunton Andrews Kurth LLP
Practical Pointers for Change Orders on Commercial Construction Contracts
December 31, 2014 —
John E. Bowerbank - Newmeyer & DillionConstruction projects pose unique challenges, including keeping costs within budget, meeting project deadlines, and coordinating the work of numerous contractors and subcontractors in the wake of inevitable design revisions and changes to the plans. Anticipating potential project challenges and negotiating contract provisions before commencing work on a project is critical for all parties. Careful planning should reduce the number of contract disputes. This, in turn, can facilitate the completion of a project within budget and on schedule.
“Changes” Clauses in Construction Contracts
Most commercial construction contracts have a clause addressing changes to the contract. A “changes” clause typically requires the mutual agreement of the parties on the scope of any modifications to the contract, as well as the effect on the contract price and timeframe for the work to be performed. This results in what is generally referred to as a “change order.” Many projects have a large number of change orders, which can result in significant cost overruns and delays to the project if the contract contains a complicated change order process. Therefore, in order to minimize cost overruns and project delays, it is crucial to keep the change order process as simplified and streamlined as possible.
In the most basic terms, change orders memorialize modifications to the original contract, and typically alter the contract's price, scope of work, and/or completion dates. A typical change order is a written document prepared by the owner or its design professional, and signed by the owner, design professional, and affected contractors and subcontractors. An executed change order indicates the parties’ agreement as to what changes are taking place, including approval for additional costs and schedule impacts.
While the reasons for change orders and the parties initiating them may vary, all change orders have one feature in common. Effective change orders alter the original contract and become part of the contract. Therefore, from a legal standpoint, change orders must be approached with the same caution and forethought as the original contract.
Practice Pointers for Change Orders
In light of the foregoing, some practice pointers for change orders in commercial construction contracts are as follows:
- Carefully Negotiate and Draft Change Order Provisions in the Original Contract.
A carefully negotiated and drafted “changes” clause that accounts for “unexpected circumstances” or “hidden conditions” can protect the parties from downstream costly disputes.
- Immediately Address Changes by Following the Change Order Process, Including Obtaining Necessary Signatures.
Regardless if you are an owner, general contractor or subcontractor, you should address any proposed change order immediately. Even if a decision maker gives “verbal” approval to go ahead with changed work, the work should not proceed without following the change order process in the original contract. This includes making sure to obtain any necessary signatures for the change order, if at all possible.
- Analyze the Plans and Specifications to Determine Whether “Changes” are Within the Scope of the Original Contract, or Whether They are Extra Work.
Prior to entering an original contract, it is imperative that the parties review the plans and specifications for ambiguities regarding work included in the original contract, versus potential extra work that would require a change order. This is important because a careful review of the plans and specifications sometimes reveals that work believed to be a change order is, in fact, original work, or vice versa.
- Make Sure Requests and Approvals for Change Orders are Done by an Authorized Representative.
When a party requests or gives its approval to a change order, it is important to confirm the request or approval came from an authorized representative.
- Avoid Vague and Open-Ended Change Orders.
Indeed, the vaguer a change order, the more likely it can lead to a dispute. Vague and open-ended change orders, including change orders that provide for payment on a time and materials basis, can be difficult for an owner to budget and schedule. This can lead to disputes as to cost and/or time extensions.
- Oral Assurances for Payment Without a Signed Change Order May Not Be Recoverable.
When a party provides verbal assurances to another party for extra work without following the change order process, there is a much higher likelihood that disputes will occur. Although there is case law that may allow a contractor to recover for extra work in private contracts based on oral promises, the parties should avoid placing themselves in such a legal position. Notably, in public contracts, a contractor may not be able to recover for any extra work without a signed changed order, even with verbal assurances of payment from the owner.
About the Author:
John E. Bowerbank, Newmeyer & Dillion
Mr. Bowerbank is a partner in the Newport Beach office and practices in the areas of business, insurance, real estate, and construction litigation. You can reach John at john.bowerbank@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Claim Preclusion: The Doctrine Everyone Thinks They Know But No One Really Knows What it Means in Practice
April 25, 2023 —
Garret Murai - California Construction Law BlogGenerally, I think restraint in litigation is a good thing. Don’t go crazy on your claims, don’t go nut-so in your discovery, and don’t present your case at trial in a way that causes the judge and/or jury to raise their eyebrows or shake their heads in disbelief. But, as with nearly everything, there’s always an exception. One of which is: don’t hold back on a claim because you “think” you might be able to bring it later, because you might not be able to as the next case, 5th and LA v. Western Waterproofing Company, Inc., 87 Cal.App.5th 781 (2023), demonstrates.
The 5th and LA Case
At the outset, let me first say how much I enjoyed reading this case based on the writing alone. The case, as the 2nd District Court of Appeals states, involves “a second lawsuit about an increasingly leaky roof.”
In 2012, property owner 5th and LA hired roofing contractor Western Waterproofing Company, Inc. to remove and recoat a parking lot that served also served as the roof over retail and office space below. Western completed its work in July 2012 and almost immediately 5th and LA noticed water that the coating was failing causing water leaks to the interior of the building.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
The Need to Be Specific and Precise in Drafting Settling Agreements
December 30, 2013 —
W. Berkeley Mann, Jr. — Higgins, Hopkins, McLain & Roswell, LLCThe case of Bituminous Casualty Corp. v. Hartford Casualty Insurance Corp., 2013 WL 452374 (D. Colo. February 6, 2013) is instructive as an example of both the confusion and resulting escalation of litigation that can result from a lack of clarity in settlement negotiations. This is particularly true where parties settle outside of their insurance coverage, and/or without notifying their insurer(s), which have denied coverage.
The case involved coverage litigation following settlement of a multi-party construction defect case involving the Rivergate multi-family residential development in Durango, Colorado. The condominium owners association sued, among others, the developer (Rivergate Lofts Partners, hereafter “RLP”) and the general contractor (Genex Construction, LLC, hereafter “Genex”). This follow-on case involved the insurers for RLP (“Hartford”) and Genex (“Bituminous”). The coverage dispute was complicated by the Bituminous allegations that Hartford insured Genex in its alleged role as a manager for RLP, as part of Hartford’s insurance of RLP more generally.
The underlying facts were that Hartford denied insurance coverage and defense to Genex/Bituminous. The underlying construction defect case went to mediation, with the COA, RLP, and Genex all in attendance with their respective insurer representatives, and coverage counsel. While the evolving facts of that mediation were later disputed as to their motives, intentions, and the contemporaneous knowledge of the parties, the facts reflected in documents were fairly clear.
Read the court decisionRead the full story...Reprinted courtesy of
W. Berkeley Mann, Jr.W. Berkeley Mann, Jr. can be contacted at