Not in My Kitchen – California Supreme Court Decertifies Golden State Boring Case
November 26, 2014 —
Roger Hughes – California Construction Law BlogOn November 11, 2014, the California Supreme Court rejected the recent California Court of Appeals decision Golden State Boring & Pipe Jacking, Inc. v Eastern Municipal Water District, 228 Cal.App.4th 273 (2014) which we wrote about earlier by “decertifying” it (meaning that lawyers cannot cite to the case as legal precedent) The decertification removed a decision that added substantially to the confusion as to when an action on a payment bond is timely filed. Even though the decision was determined in accordance with pre-2014 statutes, the case was relevant precedent for construction attorneys when determining time deadlines for filing a claim on a bond.
Background
In July of this year, the California Court of Appeals for the Fourth Appellate District upheld a trial court’s granting of summary judgment against a project subcontractor Golden State Boring & Pipe Jacking, Inc. (GSB) who sued Safeco Insurance Company (Safeco) for unpaid contract amounts on a project payment bond issued by Safeco. Both at the trial level and on appeal Safeco successfully argued that GSB’s action on its payment bond claim was time barred by former California Civil Code Sections 3249 (now Section 9558), because it was filed more than six month after the period in which stop notices may be filed as provided by California’s Civil Code Section 3184 (now Section 9558).
Read the court decisionRead the full story...Reprinted courtesy of
Roger Hughes, Wendel Rosen Black & Dean LLPMr. Hughes may be contacted at
rhughes@wendel.com
Key Legal Issues to Consider Before and After Natural Disasters
November 25, 2024 —
Patrick Kelly - Construction ExecutiveWhile legal considerations are often the last thing on the minds of project owners and contractors during an emergency, construction industry stakeholders should bear in mind the impact of natural disasters on their legal rights, remedies and potential exposure to claims.
For all stakeholders, two of the most pressing considerations are: (1) what provisions in their contracts are impacted by a natural disaster and (2) do they have any potential exposure to price-gouging claims?
Reprinted courtesy of
Patrick Kelly, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Kelly may be contacted at
pkelly@grayreed.com
Flooded Courtroom May be Due to Construction Defect
September 01, 2011 —
CDJ STAFFThe General Services Administration wouldn’t pin it on a construction defect, but a spokesperson said that a pipe that was misaligned during installation was the likely cause of a flood in the Thomas F. Eagleton US Courthouse on August 23. According to the St. Louis Dispatch, the burst pipe caused a 17-story waterfall in the courthouse, soaking ceilings and floors, and drenching the building’s contents.
The building was dedicated eleven years ago. During the nearly ten years before the building was complete, there were construction disputes and soil contamination issues.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
California Enacts New Claims Resolution Process for Public Works Projects
January 19, 2017 —
Garret Murai – California Construction Law BlogIf you’re a public entity or contractor involved in public works construction you should be aware of a new law,
AB 626, which took effect on the first of this year and establishes a new mandatory claims resolution process for disputes on public works projects. Here’s what you need to know:
What is the new law and where is it codified at?
AB 626 added new Public Contract Code Section 9204 that according to the bill’s author, Assemblymember David Chiu of San Francisco, establishes “a claim resolution process applicable to any claim by a contractor in connection with a public works project.”
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Court Addresses When Duty to Defend Ends
August 24, 2020 —
Anthony L. Miscioscia & Margo E. Meta - White and WilliamsThere are certain generally held principles regarding an insurer’s duty to defend. One of these principles is that an insurer has a duty to defend its insured if the complaint states a claim that potentially falls within the policy’s coverage. However, there is a lack of consistency regarding the point at which the insurers’ duty to defend ends. When the only potentially covered claim has been dismissed, must the insurer continue to defend?
Certain jurisdictions, such as Hawaii and Minnesota, have held that an insurer’s duty to defend continues through an appeals process, or until a final judgment has been entered, disposing of the entire case. Commerce & Industry Insurance Company v. Bank of Hawaii, 832 P.2d 733 (Haw. 1992); Meadowbrook, Inc. v. Tower Insurance Company, 559 N.W. 2d 411 (Minn. 1997).
Earlier this week, the U.S. District Court for the Eastern District of Pennsylvania took a different approach to this question in Westminster American Insurance Company v. Spruce 1530, No. 19-539, 2020 U.S. Dist. LEXIS 106534 (E.D. Pa. June 17, 2020) – holding that the trial court’s dismissal of the only potentially covered claim was sufficient to terminate Westminster’s duty to defend.
Reprinted courtesy of
Anthony L. Miscioscia, White and Williams and
Margo E. Meta, White and Williams
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Ms. Meta may be contacted at metam@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Connecticut Supreme Court Finds Duty to Defend When Case Law is Uncertain
October 12, 2020 —
Eric B. Hermanson & Austin D. Moody - White and WilliamsThe Connecticut Supreme Court recently addressed whether an insurer has a duty to defend when faced with legal uncertainty as to whether coverage is owed: for example, when there is no Connecticut case law on point, and courts outside of the state have reached conflicting decisions.
The Court suggested that an insurer, in these circumstances, should defend the insured, and should seek a declaratory judgment from a court as to whether coverage is owed.
The issue in Nash St., LLC v. Main St. Am. Assurance Co.,[1] arose out of a home collapse in Milford, Connecticut. The owner of the home (Nash) hired a contractor (New Beginnings) to renovate the home. New Beginnings, in turn, retained a subcontractor to lift the house and to do concrete work on the foundation. While the subcontractor was lifting the house, the house shifted off the supporting cribbing and collapsed.
Reprinted courtesy of
Eric B. Hermanson, White and Williams and
Austin D. Moody, White and Williams
Mr. Hermanson may be contacted at hermansone@whiteandwilliams.com
Mr. Moody may be contacted at moodya@whiteandwiliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Falling Crime Rates Make Dangerous Neighborhoods Safe for Bidding Wars
March 19, 2015 —
Heather Perlberg, Prashant Gopal and John Gittelsohn – Bloomberg(Bloomberg) -- LaTasha Gunnels was outbid four times before she snagged a home in Anacostia, the southeast Washington, D.C. neighborhood that comes with a discount because of its reputation for drugs and crime.
The 35-year-old nurse said the area, in a section of the city across a river from Capitol Hill known for its historically high murder rates, is changing rapidly. Buyers like Gunnels, priced out of costlier spots, helped lift values 21 percent in the Anacostia area in 2014, the biggest surge of any D.C. neighborhood, according to data provider Real Estate Business Intelligence.
“I’m not going to sugarcoat it -- crime is still there -- but police officers are on every single corner and nobody has bothered me yet,” Gunnels said. “What I’m paying for my mortgage, people are paying for one-bedroom apartments in other parts of D.C.”
Reprinted courtesy of Bloomberg reporters
Heather Perlberg,
Prashant Gopal, and
John Gittelsohn
Ms. Perlberg may be contacted at hperlberg@bloomberg.net
Mr. Gopal may be contacted at pgopal2@bloomberg.net
Mr. Gittelsohn may be contacted at johngitt@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Where Breach of Contract and Tortious Interference Collide
January 11, 2022 —
Christopher G. Hill - Construction Law MusingsClaims for breach of contract are numerous in the construction law world. Without these claims we construction attorneys would have a hard time keeping the doors open. A 2021 case examined a different sort of claim that could arise (though, “spoiler alert” did not in this case) during the course of a construction project. That type of claim is one for tortious interference with business expectancy.
In Clark Nexsen, Inc. et. al v. Rebkee, the U. S. District Court for the Eastern District of Virginia gave a great explanation of the law of this type of claim in analyzing the following basic facts:
In 2018, Clark Nexsen, Inc. (“Clark”) and MEB General Contractors, Inc. (“MEB”) responded to Henrico County’s (“Henrico”) Request for Proposals (“RFP”) for the design and construction of a sport and convocation center (the “Project”). Henrico initially shortlisted Clark and MEB as a “design-build” team for the Project, but later restarted the search, issuing a second RFP. Clark and MEB submitted a second “design-build” proposal, but Henrico selected Rebkee Co. (“Rebkee”) for certain development aspects of the Project. MEB also submitted proposals to Rebkee, and Rebkee selected MEB as the design-builder for the Project. MEB, at Rebkee’s request, solicited proposals from three design firms and ultimately selected Clark as its design partner. From December 2019 to May 2020, Clark and MEB served as the design-build team to assist Rebkee in developing the Project. In connection therewith, Clark developed proprietary designs, technical drawings, and, with MEB, several cost estimates. In February 2020, MEB submitted a $294,334.50 Pay Application to Rebkee for engineering, design, and Project development work. Rebkee never paid MEB. Henrico paid MEB $50,000.00 as partial payment for MEB’s and Clark’s work. MEB then learned that Rebkee was using Clark’s drawings to solicit design and construction proposals from other companies. On July 23, 2020, Rebkee told MEB that Henrico directed it to cancel the design-build arrangement with MEB and Clark and pursue a different planning method. MEB and Clark sued and Rebkee for, among other claims, tortious interference with a business expectancy. Rebkee moved to dismiss the tortious interference claim.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com