Top 10 Construction Contract Provisions – Changes and Claims
November 03, 2016 —
James R. Lynch – Ahlers & Cressman PLLCThis is the seventh post in our “Top 10 Construction Contract Provisions” series. Prior posts discussed
Price and Payment,
Liquidated Damages,
Consequential Damages – Part I and
Part II,
Indemnity,
Scope of Work, and
Flow-Down Provisions.
Today’s topic, Changes and Claims, is a contender for the top spot on our list, for both day-to-day impact on the job and importance in disputes. In fact, these provisions[i] are so variable and are involved in so many reported construction law decisions, that this post will not attempt to survey all their various forms, uses, or potential legal ramifications, but instead focuses on bottom line “best practices”—questions to consider as a general contractor, subcontractor, or owner when drafting, negotiating, or managing the Changes and Claims provisions of a contract. There is no “ideal” here, and the changes and claims procedures should be suited to the project, owner, contractor(s), likely issues, and other project-specific considerations. Key considerations include the following:
1. How prescriptive is the Change Order process? At one end of the spectrum, a Change Order provision may include requirements for written direction and request by the owner and formal response by the contractor, with pricing and specific supporting data or documentation, in addition to strict timelines for response, execution, and performance, precise methods to determine the resulting contract adjustment, limits on the type or extent of adjustment, or terms defining the effect of a signed Change Order, e.g. to what extent related claims or impacts might be extinguished. At the other end of the spectrum, the Change Order provision might simply recognize that the owner may direct changes, and the parties intend to document the directions and resulting compensation in a Change Order, with no further elaboration. There is no universal ideal on this spectrum. A highly defined and prescriptive process may be appropriate for a complex, high value, multi-stakeholder project on which significant changes are likely. The same process would be an inefficient waste of resources on a small and simple project where significant changes are unlikely and the parties would be unlikely to comply with more formal procedures.
Read the court decisionRead the full story...Reprinted courtesy of
James R. Lynch, Ahlers & Cressman PLLCMr. Lynch may be contacted at
jlynch@ac-lawyers.com
OSHA Set to Tag More Firms as Severe Violators Under New Criteria
November 01, 2022 —
Richard Korman & Stephanie Loder - Engineering News-RecordIn announcing last month broadened criteria for classifying employers as severe safety violators, U.S. Occupational Safety and Health Administration official Douglas Parker singled out a steel fabricator near El Paso, Texas. The U.S. Labor Dept. assistant secretary for occupational safety and health, he posted a blog stating that OSHA had placed Kyoei Steel Ltd. in its severe violators program, which subjects the firm to numerous re-inspections until it is allowed to exit.
Reprinted courtesy of
Richard Korman, Engineering News-Record and
Stephanie Loder, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Protecting Your Business From Liability Claims Stemming From COVID-19 Exposure
June 01, 2020 —
Andrew Hamelsky, Jenifer Scarcella & Joshua Tumen - White and WilliamsBusinesses of every nature – including grocery stores, banks, daycares, gyms and restaurants – may face increasing liability claims from customers and third parties claiming to have been exposed to the novel coronavirus, or COVID-19, while at their location. The novel virus raises issues as to whether businesses have a heightened duty of care to their customers, and what type of exposure businesses face if a customer claims to have been exposed to COVID-19 while at their premises.
Recently, a lawsuit was filed against Princess Cruise lines for gross negligence in allowing passengers to be exposed to COVID-19 on a cruise ship. The lawsuit alleges that the cruise ship was allowed to go out to sea knowing that it was infected from two previous passengers who came down with symptoms of COVID-19. It further claims that the passengers were not warned of the potential exposure either before or after they boarded the ship.
In other news reports around the country, business owners have reported taking extraordinary precautions to prevent customers’ risk of contracting COVID-19. For example, one grocery store recently reported that it discarded $35,000 worth of food after a customer coughed on fresh produce.
Reprinted courtesy of White and Williams LLP attorneys
Andrew Hamelsky,
Jenifer Scarcella and
Joshua Tumen
Mr. Hamelsky may be contacted at hamelskya@whiteandwilliams.com
Ms. Scarcella may be contacted at scarcellaj@whiteandwilliams.com
Mr. Tumen may be contacted at tumenj@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
From the Ground Up
March 06, 2022 —
Maggie Murphy - Construction ExecutiveAs a veteran of the U.S. Marine Corps, Mari Borrero knows a thing or two about stepping up to a challenge. She describes her time in the military as “one of those milestones that changes your life,” and credits the experience with turning her from a self-described “entitled teenager” into the woman she is today: fearless, bold and relentless in pursuit of her dreams.
A career in the construction industry was never on the table for Borrero, who, after being honorably discharged from the Marine Corps, worked as a hospice-care coordinator and then a teacher in support of her then-third-grade son. The common thread in all these occupations? A genuine desire to put the needs of others before her own. Today, Borrero says she can’t imagine doing anything other than what she now calls work—owning and operating a construction business, Auburn, Washington–based American Abatement & Demo.
Easing Transitions
Born in Bayamón, Puerto Rico, Borrero was five when her mother moved the family to Dallas to seek life-saving treatment at Children’s Medical Center Dallas for her brother, who had a rare kidney disease. A local church supported the family, providing housing, food and clothing until they were able to transition into their own space.
Reprinted courtesy of
Maggie Murphy, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Hawaii Supreme Court Says Aloha to Insurers Trying to Recoup Defense Costs From Policyholders
January 02, 2024 —
Lara Degenhart Cassidy & Yosef Itkin - Hunton Insurance Recovery BlogThe Hawaii Supreme Court emphatically rejected insurer efforts to seek reimbursement of defense costs absent a provision in the policy providing for such reimbursement in St. Paul Fire & Marine Insurance Company v. Bodell Construction Company, No. SCCQ-22-0000658, 2023 WL 7517083, (Haw. Nov. 14, 2023). The state high court’s well-reasoned decision rests on bedrock law regarding insurance policy construction and application, follows the nationwide trend of courts compelling insurers to satisfy their contractual obligations in full, and should carry great weight as other jurisdictions continue to debate the same issue.
In Bodell, the Hawaii Supreme Court joined the swelling ranks of courts recognizing that an insurer may not use a reservation of rights to create the extra-contractual “right” to recoup already paid defense costs for a claim on which the insurer ultimately owes no coverage. See, e.g., Am. & Foreign Ins. Co. v. Jerry’s Sport Ctr., Inc., 2 A.3d 526 (Pa. 2010). Other jurisdictions, such as California, will permit an insurer to seek reimbursement from a policyholder for defense costs incurred in defending claims later determined to be uncovered. See Buss v. Superior Court, 16 Cal.4th 35 (1997) (holding insurers have a right to reimbursement of defense costs incurred for noncovered claims).
Reprinted courtesy of
Lara Degenhart Cassidy, Hunton Andrews Kurth and
Yosef Itkin, Hunton Andrews Kurth
Ms. Cassidy may be contacted at lcassidy@HuntonAK.com
Mr. Itkin may be contacted at yitkin@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
General Contractors Must Plan to Limit Liability for Subcontractor Injury
May 18, 2011 —
Douglas Reiser in the Builders Counsel BlogIt takes more than a hard hat, but safety checks, a good policy and a smart contract might save you some problems.If you are a general contractor, you will want to pay close attention to this article. A new Washington appellate decision showcases a general contractor’s liability to subcontractors who are injured on the job, when security barriers fail. But can a general limit this liability? Will its contract help?
In Wrought Corporation, Inc., Appellant V. Mario Interiano (quick note: this opinion is unpublished, but we are here to talk about an issue that was not determined on appeal – WISHA compliance), a subcontractor was injured when a security barrier failed and he fell into an elevator shaft.
A jury awarded a $1.56 million verdict against the general contractor, and the court of appeals affirmed on the basis that the general contractor has a non-delegable duty to ensure compliance with the Washington Industrial Safety and Health Act of 1973, codified under RCW 49.17 (WISHA).
Read the full story… Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Litigation Roundup: “You May Want an Intervention …”
June 10, 2024 —
Daniel Lund III - LexologyYou may want an intervention … but you are not getting one!
So said a federal court in New Orleans to a masonry supplier seeking to intervene in in an upstream subcontractor’s lawsuit against a payment bond surety for allegedly unpaid subcontract sums.
It all seems so obvious: the masonry supplier indicates it is unpaid, and the subcontractor to which it supplied materials is saying the same thing and pursuing monies from the general contractor’s surety. Eventually, if the subcontractor prevails against the surety, monies ought to flow to the supplier – a set of facts lending itself to an intervention.
The federal district court disagreed, however. Referring to Federal Rule of Civil Procedure 24(a)(2) and prior United States Fifth Circuit Court of Appeals case law the topic, the court opined that the masonry supplier lacked an interest in the subcontractor’s potential recovery that was “related to the property or transaction that forms the basis of the controversy…an interest that is ‘direct, substantial, [and] legally protectable.’"
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
How to Make the Construction Dispute Resolution Process More Efficient and Less Expensive
July 09, 2014 —
Beverley BevenFlorez-CDJ STAFFJohn P. Ahlers on the Ahlers & Cressman PLLC blog has posted the first of a two-part series on Ways to Make the Construction Dispute Resolution Process More Efficient and Less Expensive: “In our view, construction is well suited to streamlining the resolution process, particularly when experienced lawyers and judges / arbitrators are involved.”
“Discovery can take vast amounts of time and cost a company significant resources,” Ahlers wrote. “Many times, only small portions of a deposition might actually be used at the hearing in cross examination. The question then becomes whether the cost of the discovery is providing a return.”
Ahlers listed several steps and requirements that arbitrators, judges, or the parties themselves can impose to make the process more efficient, such as client involvement, avoiding too much process at the expense of practical outcomes, discovery limitations, among others.
Read the court decisionRead the full story...Reprinted courtesy of