Do Change Orders Need to be in Writing and Other Things That Might Surprise You
June 02, 2016 —
Garret Murai – California Construction Law BlogYou’ve likely heard it before or maybe you’ve even said it yourself: “Go ahead and get started, we’ll get you a change order later.”
The only thing is, “later” never happens, and after you’ve finished performing the work you find yourself in a fight over whether you’re entitled to get paid for the work you performed.
So, do you need a written change order to get paid for extra work you performed? Read on, you may be surprised.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Wait! Don’t Sign Yet: Reviewing Contract Protections During the COVID Pandemic
April 13, 2020 —
Danielle S. Ward - Balestreri Potocki & HolmesAs the circumstances of the COVID pandemic change day by day, and we all rush to keep business moving where and when we can, companies should consider hitting the “pause button” before renewing or executing any new contracts. Developing contracts often takes considerable time and expense, and companies are not in the habit of reworking them often. A change in law may prompt a company to revisit their contract terms, but otherwise business is often carried out with a standard form contract for a period of years. With the COVID pandemic affecting nearly every business and industry, life is not business as usual, and companies should make sure their contracts consider what previously seemed like an unforeseeable event.
Force Majeure clauses are included in many contracts to excuse contract performance when made impossible by some unforeseen circumstance. These clauses typically fall under two categories: general and specific. General force majeure clauses excuse performance if performance is prevented by circumstances outside the parties’ control. By contrast, specific force majeure clauses detail the exhaustive list of circumstances (acts of god, extreme weather, war, riot, terrorism, embargoes) which would excuse contract performance. Force majeure clauses are typically interpreted narrowly. If your contract has a specific clause and pandemic or virus is not one of the listed circumstances it may not apply. Whether a particular existing contract covers the ongoing COVID pandemic will vary depending on the language of the contract.
Force majeure clauses previously made headlines when the great economic recession hit in 2008. A number of courts held that simple economic hardship was not enough to invoke force majeure. The inability to pay or lack of desire to pay for the contracted goods or services did not qualify as force majeure. In California, impossibility turns on the nature of the contractual performance, and not in the inability of the obligor to do it. (Kennedy v. Reece (1964) 225 Cal. App. 2d 717, 725.) In other words, the task is objectively impossible not merely impossible or more burdensome to the specific contracting party.
California has codified “force majeure” protection where the parties haven’t included any language or the circumstances in the clause don’t apply to the situation at hand. Civil Code section 1511 excuses performance when “prevented or delayed by an irresistible, superhuman cause, or by the act of public enemies of this state or of the United States, unless the parties have expressly agreed to the contrary.” (Civ. Code § 1511.) What qualifies as a “superhuman cause”? In California, the test is whether under the particular circumstances there was such an insuperable interference occurring without the party's intervention as could not have been prevented by the exercise of prudence, diligence and care. (Pacific Vegetable Oil Corp. v. C. S. T., Ltd. (1946) 29 Cal.2d 228, 238.)
If you find yourself in an existing contract without a force majeure clause, or the statute does not apply, you may consider the doctrine of frustration of purpose. This doctrine is applied narrowly where performance remains possible, but the fundamental reason the parties entered into the contract has been severely or substantially frustrated by an unanticipated supervening circumstance, thus destroying substantially the value of the contract. (Cutter Laboratories, Inc. v. Twining (1963) 221 Cal. App. 2d 302, 314-15.) In other words, performance is still possible but valueless. Note this defense is not likely to apply where the contract has simply become less profitable for one party.
Now that COVID is no longer an unforeseeable event, but rather a current and grave reality, a party executing a contract today without adequate protections may have a difficult time proving unforeseeability. Scientists are not sure whether warm weather will suppress the spread of the virus, as it does with the seasonal flu, but to the extent we get a reprieve during the summer we may see a resurgence of cases this Fall or Winter. Companies should take care in reviewing force majeure clauses, and other clauses tied to timely performance such as delay and liquidated damages before renewing or executing new contracts.
Your contract scenario may vary from the summary provided above. Please contact legal counsel before making any decisions. During this critical time, BPH’s attorneys can be reached via email to answer your questions.
Read the court decisionRead the full story...Reprinted courtesy of
Danielle S. Ward, Balestreri Potocki & HolmesMs. Ward may be contacted at
dward@bph-law.com
7 Sustainability Ideas for Modular Classrooms in the Education Industry (guest post)
June 10, 2015 —
Melissa Dewey Brumback – Construction Law in North CarolinaToday, a guest post on sustainable modular classrooms from Kathy Werder, a freelance architect by profession and a researcher by nature. According to Kathy, most of her research papers focus on promoting integration that leads to sustainable and lean design and construction practices. Kathy is obsessed with the latest rage in the construction industry – modular building solutions. She is also an avid writer, and loves blogging about green buildings and portable construction units. Welcome, Kathy!
According to Wikipedia, a sustainable building refers to “ a structure and using process that is environmentally responsible and resource-efficient throughout a building’s life-cycle from sitting, to design, construction, operation, maintenance, renovation, and demolition.”
So if we accept this definition to be true, in order to make an actual sustainable building we have to consider the entire process of building right from the blueprint stage all the way to demolition, and ensure that at every step of the way there is minimal or no negative impact on the environment, especially in terms of resource efficiency.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback may be contacted at
mbrumback@rl-law.com
Top 10 Cases of 2019
February 10, 2020 —
Jeffrey J. Vita, Grace V. Hebbel & Andrew G. Heckler - Saxe Doernberger & Vita, P.C.In the 2019 edition of SDV’s Top Ten Insurance Cases, we probe wiretapping claims under an armed security services policy, delicately sniff out E&O coverage for a company using cow manure to create electricity, scour the earth for coverage for crumbling foundation claims, and inspect D&O policies for government investigation coverage. In addition, we preview some important and exciting decisions due in 2020. Without further ado, SDV raises the curtain on the most informative and influential insurance
coverage decisions of 2019.1
1.
ACE American Ins. Co. v. American Medical Plumbing, Inc.,
206 A.3d 437 (N.J. Super. Ct. App. Div. 2019)
April 4, 2019
Is waiver of subrogation language in a standard AIA201 contract sufficient to bar an insurer’s subrogation rights?
The New Jersey Supreme Court held that it was. Equinox Development obtained a comprehensive blanket all-risk policy with limits of $32 million per occurrence from ACE American Ins. Co. (“ACE”). The policy covered Equinox’s new project in Summit, New Jersey. Equinox hired Grace Construction as GC, who in turn subcontracted the plumbing scope of work to American Medical Plumbing, Inc. (“American”). After completion of the work under the subcontract, a water main failed and flooded the entire project. ACE paid the limits of the policy and subrogated against American to recover its losses. American argued that there was a waiver of subrogation in the AIA201 contract that barred the suit. ACE challenged the validity of the AIA provision, arguing that it applied only to claims before completion of construction and that it only applied to damage to the work itself and not to adjacent property. The court rejected both arguments, finding that the AIA provision effectively barred ACE’s subrogation claim. This decision provides guidance on a frequently used contract form for contractors across the country.
Reprinted courtesy of Saxe Doernberger & Vita, P.C. attorneys
Jeffrey J. Vita,
Grace V. Hebbel and
Andrew G. Heckler
Mr. Vita may be contacted at jjv@sdvlaw.com
Ms. Hebbel may be contacted at gvh@sdvlaw.com
Mr. Heckler may be contacted at agh@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Feds, County Seek Delay in Houston $7B Road Widening Over Community Impact
March 15, 2021 —
Mary B. Powers - Engineering News-RecordThe Federal Highway Administration has asked Texas to delay issuing requests for proposals and pause ongoing contracting on a $7-billion, three-phased highway expansion project in metropolitan Houston as it evaluates complaints that up to 1,000 homes and multifamily buildings and 350 businesses would be condemned to build the project.
Reprinted courtesy of
Mary B. Powers, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Digitalizing the Hospital Design Requirements Process
April 02, 2019 —
Aarni Heiskanen - AEC BusinessDecisions made at the early stages of a hospital project can have a huge impact on its life cycle value. To make sure that a hospital will be a good investment, its future users should be involved in helping set out the design requirements. A Finnish team of experts wanted to see if they could improve the process and set up an experiment to see how it could be done digitally.
Currently, over one billion euros are budgeted to hospital construction and renovation in Finland. Globally, the sum is around US$400 billion. You would imagine that the design for such large investments would be very efficient from the start. Unfortunately, that is not the case.
During the design phase, doctors, specialists, nurses, and other stakeholders take part in workshops in which they express their needs and requirements. For a large hospital project, 40 to 100 workshops are the norm. The work is done with a variety of tools, with sticky notes being the predominant technique.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Four Things Construction Professionals Need to Know About Asbestos
September 23, 2019 —
Daniel King - Construction ExecutiveAlthough asbestos had its heyday in America half a century ago, asbestos exposure remains a major health risk and financial liability for construction professionals. One study estimates that at least 1.3 million construction industry workers are still at risk for occupational asbestos exposure.
Up until the 1980s, U.S. manufacturers mixed asbestos into thousands of construction products. Asbestos is a unique mineral that can be worked into flexible fibers while still retaining its durability and heat resistance. Unfortunately, the fibrous nature of asbestos also makes it highly toxic.
This article provides an overview of what construction professionals need to know about asbestos, including:
- potential long-term health consequences of asbestos exposure for workers and short-term financial consequences for employers;
- Occupational Safety and Health Administration asbestos regulations;
- how to identify and safely remove asbestos-containing materials; and
- what people should do if they have a history of asbestos exposure.
Reprinted courtesy of
Daniel King, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. King may be contacted at
dking@asbestos.com
Taking Service Network Planning to the Next Level
July 22, 2019 —
Aarni Heiskanen - AEC BusinessCities and municipalities are basically systems for delivering services for the benefit of their citizens. An experimental project demonstrated how improving the flow of data between these services could save a lot of time and taxpayer money.
Emilia Rönkkö is an architect who worked for the Finnish city of Kuopio. Besides that, she is a Docent of Urban Planning at the University of Oulu.
“In Kuopio, my job included doing architectural programming for public investments and service network reviews. More specifically, surveys about Growth and Learning Services that were focused on daycares and schools,” Rönkkö explains. “Typically, a service network review with manual data collection procedures takes place every three to five years. I and other functionaries involved in the process wondered if there might be a better, more efficient way to do the reviews.”
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi