Christopher G. Hill - Construction Law MusingsRecently, I’ve been on an “advising” kick here at Construction Law Musings. My last two posts have been about communication and trusting your gut when it comes to a smooth construction project. This post will be the third in the trilogy (and who knows maybe I’ll have a 4th and 5th like the Hitchhiker’s Guide to the Galaxy “trilogy”).
While all construction contractors should use their communication skills and instincts to assure a smooth and hopefully profitable project, all of the gut following and great communication will not help you if your contract is not up to snuff. In the spirit of giving you a few basics things to look at, here’s my list of three basics that you need in your contract and a three things to be on the lookout for in others’ contracts.
First, the good stuff that needs to be there:
- Attorney Fees Clause– without it, a Virginia court (and most other courts) will not award you a judgment for any attorney fees spent to protect your rights.
- Dispute Resolution– whether the specified resolution is through the litigation process, ADR or some combination, such a clause or paragraph will only help define the parameters of what happens with a claim.
- Detailed scope of work– Without the proper detail in the scope of work, the parties cannot properly set expectations and know what happens when things change.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Governor Signs Permit Extension Bill Extending Permit Deadlines to One Year
October 23, 2018 —
Garret Murai - California Construction Law BlogIt’s like that feeling you got when your teacher said you have another week to complete your group project.
On September 21, 2018, Governor Brown signed AB 2913, which, for the first time, provides a uniform 12-month period across the state for work to commence before a building permit expires. Previously, the period was six months.
In addition to doubling the expiration period, the statute includes a “justifiable cause” provision permitting local building departments to extend the time for one or more additional periods of not more than 180 days per extension upon written demonstration of “justifiable cause for the extension.”
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
California Appellate Court Holds “Minimal Causal Connection” Satisfies Causation Requirement in All Risk Policies
July 20, 2020 —
Scott P. DeVries & Michael S. Levine - Hunton Andrews KurthOn May 26, 2020, a California Court of Appeals (4th District) issued its decision in Mosley et al. v. Pacific Specialty Ins. Co. The case arose in the context of a marijuana-growing tenant who rerouted a home’s electrical system and caused an electrical fire. The issue was whether the homeowner’s policy covered the loss. The trial court granted the insurer’s motion for summary judgment and, in a divided decision, the Court of Appeals reversed in part.
The policy excluded losses “resulting from any manufacturing, production or operation, engaged in … the growing of plants.” The parties agreed that the fire resulted from the rewiring of the electrical system, but disagreed on “whether that means the damage” “result[ed] from” “the growing of plants.” The Court held that “resulting from” “broadly links a factual situation with the event creating liability, and connotes only a minimal causal connection or incidental relationship.” In doing so, it equated the terms “results from” and “arising from.” Concluding that a “common sense” approach was to be used, it found a “minimal causal connection” to be present. This expansive standard could be beneficial to policyholders in arguing the causal connection between COVID-19 and ensuing business interruption losses; specifically, that the pandemic, a covered event, is the underlying and proximate cause of the insureds’ physical loss and/or damage and the insured’s resulting business interruption loss, and that intervening events, whether they be orders of civil authority, prevention of ingress/egress or otherwise, would not sever the chain of causation.
Reprinted courtesy of
Scott P. DeVries, Hunton Andrews Kurth and
Michael S. Levine, Hunton Andrews Kurth
Mr. DeVries may be contacted at sdevries@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Illinois Appellate Court Finds That Damages in Excess of Policy Limits Do Not Trigger Right to Independent Counsel
June 22, 2020 —
Jason Taylor - Traub LiebermanUnder Illinois law, an insurer’s duty to defend includes the right to control the defense, which allows insurers to protect their financial interest in the outcome of the litigation. However, where a conflict of interest exists, the insured, rather than the insurer, is entitled to assume control of the defense of the underlying action. If this occurs, the insurer satisfies its obligation to defend by reimbursing the insured for the cost of defense provided by independent counsel selected by the insured. What circumstances and situations arise to the level of an actual conflict of interest between the insurer and insured are often grounds for dispute.
In Joseph T. Ryerson & Son, Inc. v. Travelers Indemnity Co. of America, 2020 IL App (1st) 182491 (Apr. 7, 2020), the Illinois Appellate Court addressed whether damages awarded by a jury in excess of the policy limits were sufficient to trigger a right to independent counsel for post-trial and appellate proceedings. According to the Illinois Appellate Court, at least under the facts of the Ryerson case, the answer is “no.”
In Ryerson, Nancy Hoffman sued Ryerson for injuries sustained in a tractor-trailer accident. Ryerson tendered the suit to its primary insurer, Travelers, and its umbrella insurer, Illinois National. The policy limits were $2 million and $25 million, respectively. A jury found in favor of Hoffman for over $27.6 million in damages, and Ryerson appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Jason Taylor, Traub LiebermanMr. Taylor may be contacted at
jtaylor@tlsslaw.com
Contract Not So Clear in South Carolina Construction Defect Case
November 07, 2012 —
CDJ STAFFThe South Carolina Court of Appeals has reversed a partial summary judgment issued by one of the lower courts in the case of The Retreat at Edisto Co-Owners Association v. The Retreat at Edisto. The underlying issues of the case deal with a construction defect complaint.
The lower court had concluded “Developer’s ‘First Amendment’ to the Master Deed required the Developer to satisfy the provision in the paragraph labeled ‘Master Deed Amendment or Phase II’ as a condition precedent to its election to proceed with the development of Phase II.”
The appeals court found that “the language of the First Amendment to the Master Deed is susceptible to more than one interpretation.” The court additionally concluded that the “Developer presented the requisite scintilla of evidence on the question of its intent in order to establish a genuine issue of material fact. As the material facts were in dispute, the appeals court reversed the summary judgment and remanded the case to the circuit court for further proceedings.
Read the court decisionRead the full story...Reprinted courtesy of
Hawaii Federal District Court Denies Motion for Remand
December 21, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe federal district court refused to remand the insureds' case after the insurer removed from state court. Maui Land & Pineapple Co. v. Liberty Ins. Underwriters, 2016 U.S. Dist. LEXIS 15681 (D. Haw. Nov. 10, 2016).
The underlying case was filed in state court on Maui. The underlying plaintiffs were condominium owners who brought claims against the insured, Maui Land and Pineapple Co., Inc. (MLP), and other defendants allegedly involved in the development of the project. Ryan Churchill, one of the named defendants, served as president of MLP and was on the board of the project's Association of Apartment Owners (AOAO). The underlying plaintiffs asserted claims for: breach of fiduciary duty; seeking access to books and records of the AOAO; and for injunctive/declaratory relief against MLP, Mr. Churchill, and all other defendants.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Sometimes a Reminder is in Order. . .
June 21, 2021 —
Christopher G. Hill - Construction Law MusingsRecently, I was talking with my friend Matt Hundley about a recent case he had in the Charlottesville, VA Circuit Court. It was a relatively straightforward (or so he and I would have thought) breach of contract matter involving a fixed price contract between his (and an associate of his Laura Hooe) client James River Stucco and the Montecello Overlook Owners’ Association. I believe that you will see the reason for the title of the post once you hear the facts and read the opinion.
In James River Stucco, Inc. v. Monticello Overlook Owners’ Ass’n, the Court considered Janes River Stucco’s Motion for Summary Judgment countering two arguments made by the Association. The first Association argument was that the word “employ” in the contract meant that James River Stucco was required to use its own forces (as opposed to subcontractors) to perform the work. The second argument was that James River overcharged for the work. This second argument was made without any allegation of fraud or that the work was not 100% performed.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Amendments to Federal Rule of Evidence 702 – Expert Testimony
October 30, 2023 —
William L. Doerler - The Subrogation StrategistIn April, the Supreme Court sent a list of proposed amendments to Congress that amend the Federal Rules of Evidence. Absent action by Congress, the rules go into effect December 1, 2023. The proposed amendments affect Rules 106, 615 and, relevant to this article, 702.
Rule 702 addresses testimony by an expert witness. The proposed rule reads as follows (new material is underlined; matters omitted are lined through):
A witness who is qualified as an expert by knowledge, skill, experience, training, or education may testify in the form of an opinion or otherwise if the proponent demonstrates to the court that it is more likely than not that:
- the expert’s scientific, technical, or other specialized knowledge will help the trier of fact to understand the evidence or to determine a fact in issue;
- the testimony is based on sufficient facts or data;
- the testimony is the product of reliable principles and methods; and
- the expert has reliably applied expert’s opinion reflects a reliable application of the principles and methods to the facts of the case.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com