Colorado Court of Appeals Defines “Substantial Completion” for Subcontractors’ Work so as to Shorten the Period of Time in Which They Can Be Sued
October 20, 2016 —
David M. McLain – Colorado Construction Litigation BlogOver the past few years, there has been a battle raging on in district courts and arbitration hearing rooms throughout Colorado regarding when a subcontractor’s work is to be deemed “substantially complete,” for purposes of triggering Colorado’s six-year statute of repose. C.R.S. § 13-80-104 states, in pertinent part:
Notwithstanding any statutory provision to the contrary, all actions against any architect, contractor, builder or builder vendor, engineer, or inspector performing or furnishing the design, planning, supervision, inspection, construction, or observation of construction of any improvement to real property shall be brought within the time provided in section 13-80-102 after the claim for relief arises, and not thereafter, but in no case shall such an action be brought more than six years after the substantial completion of the improvement to the real property, except as provided in subsection (2) of this section.
* * *
(2) In case any such cause of action arises during the fifth or sixth year after substantial completion of the improvement to real property, said action shall be brought within two years after the date upon which said cause of action arises.
C.R.S. § 13-80-104 (emphasis added).
As the battle raged on at the trial court level, subcontractors and design professionals argued that their work should be deemed “substantially complete” when they finished their discrete scope of work within a project. Developers and general contractors, seeking to maintain third-party claims against the subcontractors and design professionals, typically argued either that the subcontractors’ and design professionals’ work should be deemed “substantially complete” upon the issuance of the final certificate of occupancy on the project, or upon the issuance of the final certificate of occupancy for the last building within a project on which the subcontractor or design professional worked. Trial court judges and arbitrators have been split on this issue, with perhaps a slight majority favoring one or the other approaches advocated by developers and general contractors, that the subcontractors’ and design professionals’ work is “substantially complete” upon the issuance of the last certificate of occupancy in a project (the minority view) or upon the issuance of the last certificate of occupancy for the last building within a project on which the subcontractor of design professional worked (the majority view).
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Under Colorado House Bill 17-1279, HOA Boards Now Must Get Members’ Informed Consent Before Bringing A Construction Defect Action
April 11, 2018 —
Luke Mecklenburg – Snell & Wilmer Real Estate Litigation Blog Last year, I wrote
a post calling attention to stalled efforts in the Colorado legislature to pass meaningful construction defect reform. Shortly thereafter, the legislature got it done in the form of House Bill 17-1279. This bill creates an important pre-litigation notice-and-approval process whenever an HOA initiates a construction defect action in its own name or on behalf of two or more of its members.
Before May 2017, the pre-litigation requirements that an HOA had to fulfill before bringing a construction defect claim under the Colorado Construction Defect Action Reform Act (“CDARA”) were generally minor. For example, while many declarations required majority approval from the community prior to initiation of claims, in practice, what the industry was seeing is that some HOAs were making it so that only a majority of the HOA Board had to approve bringing the claim, rather than the majority of interested unit owners. It was also common that, even where the majority of owners were involved, they were often voting in favor of filing a lawsuit or arbitration without fully understanding the risks and costs. This practice presented a risk to developers—it is easier to get approval from a small group than from a larger group, and it is easier to get approval when the voting owners do not fully appreciate the risks and costs inherent in filing a claim.
Colorado House Bill 17-1279, which was signed into law by Governor Hickenlooper in May 2017 and is codified at C.R.S. § 38-33.3-303.5, lessens these risks by amending the Colorado Common Interest Ownership Act (“CCIOA”) to add certain pre-litigation requirements. Section 38-33.3-303.5 applies any time an HOA institutes a construction defect action its own name on behalf of itself or two or more unit owners on matters affecting the common interest community. C.R.S. §§ 38-33.3-302(1)(d), -303.5(1)(a).
Read the court decisionRead the full story...Reprinted courtesy of
Luke Mecklenburg, Snell & WilmerMr. Mecklenburg may be contacted at
lmecklenburg@swlaw.com
Ethical Limits on Preparing a Witness for Deposition or Trial
October 28, 2024 —
Stu Richeson - The Dispute ResolverIn this week’s blog post, we are going to take a brief look at ethical issues associated with preparing a witness for a deposition or to testify at trial. Most attorneys would agree that it is permissible to meet with a witness before the witness’s deposition to discuss what to expect. On the other hand, there is no question that advising a witness to provide false testimony would be improper. But what about the area in between those two extremes? For instance, can an attorney suggest to a witness how to phrase answers to anticipated questions that, while true, might not be the way the witness would have answered the question absent the attorney’s coaching?
A little over a year ago, the American Bar Association Standing Committee on Ethics and Professional Responsibility issued ABA Formal Opinion 508: The Ethics of Witness Preparation. The opinion provides certain examples of things that are and are not permissible in preparing a witness for a deposition or trial.
Read the court decisionRead the full story...Reprinted courtesy of
Stu Richeson, PhelpsMr. Richeson may be contacted at
stuart.richeson@phelps.com
Robinson+Cole’s Amicus Brief Adopted and Cited by Massachusetts’s High Court
July 31, 2024 —
Erica Whaley - Construction Law ZoneEarlier this year, the
Associated Subcontractors of Massachusetts hired Robinson+Cole attorney
Joseph Barra to submit an amicus brief to the Massachusetts Supreme Judicial Court for consideration in the appeal pending before it in
Business Interiors Floor Covering Business Trust v. Graycor Construction Co., Inc. In its June 17, 2024 decision in that case, the Court interpreted the Massachusetts Prompt Pay Act, which applies to private construction projects and “requires that parties to a construction contract approve or reject payment within” an allotted time period and in compliance with certain procedures else such payments will be deemed approved. Two years ago, the Massachusetts Appeals Court, in
Tocci Building Corp. v. IRIV Partners, LLC, decided that an owner who fails to timely advise its general contractor of the reasons as to why it was withholding payment, coupled with failure to certify that such funds are being withheld in good faith, violates the Prompt Pay Act and makes the owner liable for funds owed.
[1] However, the Tocci Building Court left open the question of whether one who violates the Prompt Pay Act forfeits its substantive defenses to non-payment, such as fraud, defective work, or breach of material obligation of the contract.
The facts of Business Interiors involve a general contractor, Graycor, which subcontracted Business Interiors to perform certain flooring work for a movie theatre in Boston’s North End. When Graycor failed to formally approve, reject, or certify, in good faith, its withholding of payment of three of Business Interiors’ applications for payment as prescribed by the Prompt Pay Act, Business Interiors brought suit alleging, among other things, breach of contract. Business Interiors then moved for summary judgement arguing that Graycor’s failure to comply with the Act rendered it liable for the unpaid invoices.
Read the court decisionRead the full story...Reprinted courtesy of
Robinson + Cole
Flying Solo: How it Helps My Construction Clients
February 18, 2015 —
Christopher G. Hill – Construction Law MusingsTwo and a half years ago, on July 1, 2010, I opened my solo practice. At the time, I really had no insight into how big this change would be from a positive, customer service, perspective.
When I made the decision to go solo with my construction law practice, I knew I wanted to have flexibility to serve my client base of contractors and subcontractors in Virginia. I started some flat rate billing and had the ability to take cases that were below the dollar value of those that my old firm was willing to take. I also knew that I would be a master of my own destiny for better or worse (and it has been much more of the former than the latter).
What I did not realize is the impact that owning my own business would have on my perspective. I have always believed that, in most cases where construction disputes occur, mediation is a great option. However mediation only occurs with conflict. For any business, whether construction or otherwise, conflict creates expenses that were not likely to have been anticipated or built in to the budget. Litigation is not something that most businesses can, or should, build into their operating budgets.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
English v. RKK. . . The Rest of the Story
December 04, 2018 —
Christopher G. Hill - Construction Law MusingsBack in February, I discussed a case relating to indemnity and ambiguity. The opinion in that case, W.C. English, Inc. v. Rummel, Klepper & Kahl, LLP et al., allowed a breach of contract and indemnity claim to move forward despite the fact that conflicting term sheets between the plaintiff and defendant could have been read to violate Virginia law by requiring indemnity for English’s own negligence. In other words, the ambiguity worked in English’s favor (though that is not something to count on). The Court did not however address whether there was any negligence on English’s part and if there was, what was the contractual effect.
I’ll bet you were wondering what happened later in that case. Well, here’s the answer. In a subsequent opinion, the Court looked at the same ambiguous and conflicting term sheets between and among those defendants that were required to provide quality assurance services for the construction of a bridge in western Virginia. For the full procedural and factual analysis, be sure to read the full memorandum opinion linked above.
Read the court decisionRead the full story...Reprinted courtesy of
Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Georgia Court of Appeals Holds That Policyholder Can “Stack” the Limits of Each Primary Policy After Asbestos Claim
December 19, 2018 —
Michael S. Levine & Alexander D. Russo - Hunton Insurance Recovery BlogA Georgia Court of Appeals judge recently ruled that Scapa Dryer Fabrics was entitled to $17.4 million worth of primary coverage from National Union Fire Insurance Company of Pittsburgh, PA for claims of injurious exposure to Scapa’s asbestos-containing dryer felts. Nat’l Union Fire Ins. Co. of Pittsburgh, PA v. Scapa Dryer Fabrics, Inc., No. A18A1173, 2018 WL 5306693, at *1 (Ga. Ct. App. Oct. 26, 2018). Scapa sought coverage under five National Union policies issued from 1983–1987. The 1983, 1984 and 1985 National Union policies had limits of $1 million per occurrence and $1 million in the aggregate. The liability limits for the 1986 and 1987 renewal policies were amended by endorsement to $7.2 million. Scapa sought to recover the full $17.4 million from all five policies. National Union argued that a “Non-Cumulative Limits of Liability Endorsement” in the 1986 and 1987 policies limited Scapa’s recovery to only $7.2 million. Scapa sued National Union and its sister company, New Hampshire Insurance Company (from which Scapa purchased excess liability coverage), in Georgia state court.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Alexander D. Russo, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Russo may be contacted at arusso@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Congratulations to Nine Gibbs Giden Partners Selected to the 2023 Southern California Super Lawyers List
January 23, 2023 —
Gibbs Giden Locher Turner Senet & Wittbrodt, LLPNine Gibbs Giden partners have been selected to the 2023 Southern California Super Lawyers list for the third year in a row!
Congratulations to partners
Jason Adams
Barbara Gadbois
Sara Kornblatt
William Locher
Christopher Ng (Managing Partner)
Glenn Turner, III
Ted Senet
Richard Wittbrodt
Philip Zvonicek
Read the court decisionRead the full story...Reprinted courtesy of