Florida Supreme Court Adopts Federal Summary Judgment Standard, Substantially Conforming Florida’s Rule 1.510 to Federal Rule 56
June 07, 2021 —
Lewis BrisboisEffective May 1, 2021, the Florida courts will transition to a new summary judgment standard meant to “align Florida’s summary judgment standard with that of the federal courts and of the supermajority of states that have already adopted the federal summary judgment standard.” In re Amends. to Fla. Rule of Civ. Pro. 1.510, 309 So. 3d 192, 192 (Fla. 2020). Consistent with this amendment, Florida Rule of Civil Procedure 1.510 has been amended to adopt the federal summary judgment rule, with exceptions for timing-related issues. The Florida Supreme Court’s most recent opinion on rule 1.510 and the text of new rule 1.510 can be found here.
As background, on December 31, 2020, the Florida Supreme Court adopted the federal summary judgment standard by amending Florida Rule of Civil Procedure 1.510(c) to include the following sentence: “The summary judgment standard provided for in this rule shall be construed and applied in accordance with the federal summary judgment standard articulated in Celotex Corp. v. Catrett, 477 U.S. 317 (1986); Anderson v. Liberty Lobby, Inc., 477 U.S. 242 (1976); and Matsushita Electric Industrial Co. v. Zenith Radio Corp., 475 U.S. 574 (1986) [(the ‘Celotex trilogy’)].” In re Amends. to Fla. Rule of Civ. Pro. 1.510, 309 So. 3d at 196. The court’s amendment was slated to take effect on May 1, 2021, subject to a public comment period. The court also sought guidance from the Florida Bar’s Civil Procedure Rules Committee. After careful consideration of numerous responses, the court ultimately chose to adopt the substance of the text from federal rule 56. Along with its amendments, the court provides substantial guidance as to how the Florida courts and practitioners should interpret the new rule. A summary of the court’s thorough discussion follows.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Massive Danish Hospital Project Avoids Fire Protection Failures with Imerso Construction AI
December 23, 2023 —
Aarni Heiskanen - AEC BusinessEnsuring regulatory compliance of firewall constructions is getting a high-tech boost. Over the past 16 months, the construction team responsible for the iconic new Nyt Hospital Nordsjælland near Copenhagen used Imerso construction AI technology to achieve remarkable results. By using Imerso, the team enhanced work productivity while preventing costs and delays worth €5.2 million during the construction of the superstructure.
Inspired by this success, the team led by Project Manager Anders Kaas has since been eager to explore the potential of the technology in other areas. The opportunity arose to address a topic that has traditionally posed significant challenges and expenses in numerous construction projects – ensuring regulatory compliance of fire barriers and firewall constructions.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Ownership is Not a Conclusive Factor for Ongoing Operations Additional Insured Coverage
November 15, 2017 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn McMillin Management Services v. Financial Pacific Ins. Co. (No. D069814, filed 11/14/17), a California appeals court held that an insurer had a duty to defend a general contractor under an “ongoing operations” additional insured (AI) endorsement for damage occurring after the named insured subcontractor completed its work, because the endorsement did not limit coverage solely to liability during the subcontractors’ ongoing operations, but rather, broadly provided coverage for liability “arising out of” such operations.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
From Both Sides Now: Looking at Contracts Through a Post-Pandemic Lens
August 03, 2020 —
Lori S. Smith - White and WilliamsA little over a year ago, I wrote a blog post about the danger of relying on precedent. Now, more than ever, clients and their advisors need to revisit contract forms on which they may have been relying for years. While many of us have lived through times that required certain adjustments in how we viewed contractual obligations — recessions, wars, oil embargoes, natural disasters, 9/11 — none of these events had the widespread and long-lasting impact that the current COVID-19 pandemic is having. None of these events shut down the U.S. economy and impacted global supply chains across every industry in the manner we are now experiencing.
With this in mind, there is a need to figure out what the “new normal” will look like for contract negotiations in a post-pandemic world. Business professionals need to now anticipate more widespread disruption than we could have ever before imagined. It isn’t just force majeure clauses or material adverse effect provisions, as these will likely add pandemics and government shutdowns to their ever-growing list of contemplated risks, if they were not already expressly covered. And it is not clear, at least in the near-term, whether a resurgence or mutation of COVID-19 or the emergence of another virus can truly be seen as unforeseeable in a post-COVID world. The issues are much more fundamental to the approach that parties may take in negotiating contracts. Commercial contracts between purchasers, vendors, distributors, licensors and licensees will need to evaluate allocation of risk from both sides and come to a new happy medium that all can live with in an ever-evolving world. While parties should review their standard contracts in their entirety, some key provisions to think about include:
- Length of the contract and exclusivity. Depending on which side you are on, you may want to reconsider a long-term arrangement that ties your company to a particular vendor or distributor. Supply chain disruption can have a seriously detrimental impact on your business. Are requirements contracts where a particular supplier is required to make available all of your needs for a certain good or service really the best arrangement for your business? What about take or pay arrangements where you are obligated to which are common in certain industries pay a minimum amount or a penalty to a supplier whether or not you actually purchase the contemplated volume of goods ? Do you really want to be tied up in an exclusive arrangement, or do you need flexibility to maintain secondary or tertiary sources of supply? Do you want to provide a licensee with an exclusive right to your technology (even within a limited field of use or industry sector)?
Read the court decisionRead the full story...Reprinted courtesy of
Lori S. Smith, White and WilliamsMs. Smith may be contacted at
smithl@whiteandwilliams.com
Know What You’ve Built: An Interview with Timo Makkonen of Congrid
September 09, 2019 —
Aarni Heiskanen - AEC BusinessConstruction contains thousands of big and small tasks. How can a client and contractor know if they have all been completed as intended? Congrid offers an answer to that question.
Congrid is a Finnish construction software developer. The company provides software for punch lists, quality and safety audits, and design document distribution. It operates in Finland, Sweden, and the U.K.
The company’s founding team members, collectively, offer a combination of expertise in construction management, software development, and marketing and sales. “I come from the electronics industry. I came into this business through my old schoolmates,” says Timo Makkonen, Congrid’s CEO. “My specialty is business development and leadership.”
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Court of Appeal Opens Pandora’s Box on Definition of “Contractor” for Forum Selection Clauses
October 02, 2015 —
David A. Harris & Abigail E. Lighthart – Haight Brown & Bonesteel LLPIn Vita Planning and Landscape Architecture, Inc. v. HKS Architects, Inc. (“Vita Planning”), the First Appellate District held California’s Code of Civil Procedure section 410.42 (“Section 410.42”) which prohibits an out-of-state contractor from requiring a California subcontractor to litigate disputes in a state other than California, applies not only to traditional “contractors” and “subcontractors” but also to design professionals and architects.
In Vita Planning, a dispute arose when HKS, a Texas based architectural firm, refused to pay Vita Planning and Architecture (“Vita”), a landscape design firm, for work on a luxury hotel in Mammoth Lakes, California (“Project”). HKS contended it was not required to pay Vita until it was paid by the owner of the Project, and any claims regarding the work needed to be filed in Texas pursuant to a forum selection clause contained in a Prime Contract between HKS and the Owner. The forum clause was “incorporated by reference” into an unsigned “standard form” agreement between HKS and Vita. Despite the forum clause, Vita filed a Complaint against HKS in Marin County Superior Court.
Reprinted courtesy of
Abigail E. Lighthart, Haight Brown & Bonesteel LLP and
David A. Harris, Haight Brown & Bonesteel LLP
Mr. Harris may be contacted at dharris@hbblaw.com
Ms. Lighthart may be contacted at alighthart@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Mediation Tips for Practitioners and 'Eyes Only' Tips for Construction Mediators
December 05, 2022 —
Stacy L. La Scala - Construction ExecutiveConstruction mediation can occur during or after construction and prior to or during arbitration or litigation. But, regardless of when a construction mediation occurs, its success often depends on the parties’ willingness to exchange critical information well in advance of the mediation session.
Tips for the Construction Practitioner
- Schedule a mandatory pre-session call.
A pre-session call with the mediator is the first and most effective opportunity to convey your client’s position and to allow the mediator to absorb and evaluate that information without distraction. On that call, counsel should describe the dispute and identify the decision-makers. Additionally, counsel should address the following questions:
- Are the parties working together and sharing information, or are they at war?
- Have the parties shared expert information?
- Have demands been published?
- Will the parties be publishing their briefs?
- What confidential information is not in the mediation brief?
- Will the decision-makers be participating? Are there any decision-makers who are not available or “behind the scenes”?
Reprinted courtesy of
Stacy L. La Scala, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
NY Appellate Court Holds Common Interest Privilege Applies to Parties to a Merger
January 07, 2015 —
Jay Shapiro, Lori S. Smith and Brittney Edwards – White and Williams LLPThe common interest privilege is a doctrine that operates to maintain the confidentiality of communications between parties and counsel that have aligned interests. It is designed to encourage the free flow of information between these parties, and has historically been utilized primarily in the context of litigation. However, in Ambac Assurance Corp., et al. v. Countrywide Home Loans, Inc., et al., the New York Supreme Court, Appellate Division, First Department recently expanded the common interest privilege by holding that it is applicable in transactional contexts. 2014 WL 6803006, No. 651612/10 (1st Dep’t 2014). The Ambac court defined the common interest doctrine as “a limited exception to waiver of the attorney-client privilege” when a third party is present during a communication between an attorney and his or her client. The doctrine shields such communications from disclosure when they are (1) protected by the attorney client privilege and (2) “made for the purpose of furthering a legal interest or strategy common to the parties.”
Until Ambac, New York courts touched on, but never squarely addressed, whether a third requirement must be satisfied before the common interest doctrine can be invoked: “that the communication must affect pending or reasonably anticipated litigation.” The Ambac court addressed and rejected this purported third requirement while reversing the decision of the trial court which found that defendant Bank of America failed “to cite any New York case that applied the common-interest doctrine outside of either joint-representation of two parties by one attorney, or where parties reasonably anticipated litigation.”
Reprinted courtesy of Haight Brown & Bonesteel LLP attorneys
Jay Shapiro,
Lori S. Smith and
Brittney Edwards
Mr. Shapiro may be contacted at shapiroj@whiteandwilliams.com
Ms. Smith may be contacted at smithl@whiteandwilliams.com
Ms. Edwards may be contacted at edwardsb@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of