Protect Your Right To Payment By Following Nedd
August 03, 2022 —
Denise Motta - Gordon & Rees Construction Law BlogIn order to preserve your right to payment, you must satisfy the contractual requirements supporting a change order for the increased costs or time due to the delay. The key to the successful presentation of change order claims is educating your team on the following:
1. NOTICE
- Review the change order and notice provisions of your contracts. Make your contract searchable and insert the term “Noti” and look for the items listed below.
- Who: Check the designated representative for notice.
- It may not be the project manager.
- Confirm who can authorize the change order.
- Is owner approval required?
- Ensure that the party approving the change order has authority to do so.
- What: Check for specific information required by the contract.
- Provide ALL information available.
- If certain information is not yet available, state that the information will be provided when available.
- Reserve all rights to amend and submit additional information.
- Request both an increase to the Contract Sum and Contract Time.
- Make the request even if you do not believe the delay or time necessary will cause a significant impact.
Read the court decisionRead the full story...Reprinted courtesy of
Denise Motta, Gordon Rees Scully Mansukhani, LLPMs. Motta may be contacted at
dmotta@grsm.com
MTA Debarment Update
December 02, 2019 —
Steven M. Charney, Gregory H. Chertoff & Paul Monte - Peckar & Abramson, P.C.Alliance for Fair and Equitable Contracting Today, Inc., a nonprofit formed by five trade associations, including the GCA, the BTEA and the NY Building Congress, has sued the Metropolitan Transportation Authority over rules that debar contractors for delays and cost overruns on MTA projects without regard to the reasons for the delays and cost overruns.
As described in our prior client alert (see
here), the current rules automatically debar firms that are determined to have gone over the MTA approved contract price or time by more than 10%. The rules do not consider mitigating circumstances. Delays and cost overruns are often caused by unforeseen conditions, design errors and omissions, and changes requested by the MTA. The MTA’s rules could lead contractors to absorb additional costs they shouldn’t be responsible for rather than face the risk of being debarred. As argued in Alliance’s action, “Debarment is the death penalty for a public works contractor, and not just in New York. A debarment by the MTA could result in debarment nationwide, given that public and private contractors throughout the country commonly inquire about bidders’ debarment history when considering project bids. The Debarment Statute and MTA Regulations thus effectively export an unreasonable law not only throughout New York State, but to all other states as well.”
Reprinted courtesy of Saxe Doernberger & Vita, P.C. attorneys
Steven M. Charney,
Gregory H. Chertoff and
Paul Monte
Mr. Charney may be contacted at scharney@pecklaw.com
Mr. Chertoff may be contacted at gchertoff@pecklaw.com
Mr. Monte may be contacted at pmonte@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Fourth Circuit Clarifies What Qualifies As “Labor” Under The Miller Act
May 08, 2023 —
Jeffrey Hummel - The Construction SeytUnder the Miller Act, 40 U.S.C. §§ 3131 et seq., contractors hired to work on federal construction projects are required to furnish payment bonds in order to ensure payment to certain persons that provide labor for the project. The United States Court of Appeals for the Fourth Circuit recently issued a published decision clarifying the type of work that qualifies as “labor” under the Miller Act. Elliot Dickson v. Fidelity and Deposit Company (issued April 26, 2023).
In that case, the U.S. Department of Defense hired Forney Enterprises (Forney) as the prime contractor on a renovation project at the Pentagon. Forney retained Fidelity and Deposit Company of Maryland (Fidelity) to provide the required Miller Act payment bond. Forney then entered into a subcontract with Elliott Dickson (Dickson), a professional engineer, to work as a project manager on the contract. Dickson primarily supervised labor on the site, but also performed other tasks, including logistical and clerical duties, taking various field measurements, cleaning the worksite, moving tools and materials, and sometimes even watering the concrete himself. Dickson’s work required him to be onsite on a daily basis.
Read the court decisionRead the full story...Reprinted courtesy of
Jeffrey Hummel, SeyfarthMr. Hummel may be contacted at
jhummel@seyfarth.com
Mississippi Supreme Court Addresses Earth Movement Exclusion
December 09, 2019 —
Anthony Hatzilabrou - Traub LiebermanRecently, the Mississippi Supreme Court held that structural damages to the foundation of an insured’s home came within the earth movement exclusion in a homeowner’s policy, notwithstanding a provision in the policy which provided coverage for water damage resulting “from accidental discharge or overflow of water … from within … [p]lumbing, heating, air condition or household appliance.”
In Mississippi Farm Bureau Cas. Ins. Co. v. Smith, 264 So. 3d 737 (Miss. 2019), the appellee, Smith, filed a lawsuit against her homeowner's insurance company, Mississippi Farm Bureau Casualty Insurance Company (“Farm Bureau”) for its refusal to pay for repairs to the foundation of Smith’s home. Smith alleged that the refusal to pay for repairs amounted to breach of contract and asserted claims for bad faith and tortious breach of contract. In response, Farm Bureau filed a motion for summary judgment on the basis of the policy’s earth-movement exclusion, which provided that Farm Bureau “did not insure for loss caused directly or indirectly by…Earth Movement…[which] means…[a]ny other earth movement including earth sinking, rising or shifting... caused by or resulting from human or animal forces.” Smith filed a cross-motion for partial summary judgment on the basis that the earth-movement exclusion did not preclude coverage because her insurance policy also contained a clause expressly covering water damage.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony Hatzilabrou, Traub LiebermanMr. Hatzilabrou may be contacted at
thatzilabrou@tlsslaw.com
Florida SB 2022-736: Construction Defect Claims
February 07, 2022 —
Kelly A. Johnson - Saxe Doernberger & Vita, P.C.*Special thank you to SDV Law Clerk Iliriana Fteja for contributing to this article.
A new bill (SB 2022-736) was recently introduced to the Florida Senate. The proposed amendments to the statutes of limitations and repose could significantly impact construction defect claims by effectively creating additional exposure to contractors and insurance carriers.
The proposed bill requires all actions founded on the design, planning, or construction of an improvement to real property to be commenced within four years after the time to commence an action begins. Under the proposed amendment, the time to commence an action runs from the date of actual possession by the owner, the date of the issuance of a certificate of occupancy, the date of abandonment of construction if not completed, or the date of completion of the contract or termination of the contract between the professional engineer, registered architect, or licensed contractor and their employer. This provision would effectively alter the time to commence an action to whichever triggering event is earliest instead of the latest triggering event per the previous statute.
Read the court decisionRead the full story...Reprinted courtesy of
Kelly A. Johnson, Saxe Doernberger & Vita, P.C.Ms. Johnson may be contacted at
KJohnson@sdvlaw.com
Jersey Shore Town Trying Not to Lose the Man vs. Nature Fight on its Eroded Beaches
February 26, 2024 —
Associated Press - BloombergNORTH WILDWOOD, N.J. (AP) — A New Jersey shore town locked in a legal battle with the state over tens of millions of dollars it has spent trying -- mostly in vain -- to hold back the ocean now is more vulnerable than ever.
A recent winter storm destroyed part of the sand dunes in North Wildwood, leaving tiny piles about the size of a child’s sand castle to protect a popular resort town with $2.5 billion worth of private property, and at least that much in government buildings and infrastructure.
New Jersey has
fined the town $12 million for unauthorized beach repairs that it says could worsen erosion, while
the city is suing to recoup the $30 million it has spent trucking sand to the site for over a decade.
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg
Second Circuit Court Differentiates the Standard for Determining Evident Partiality for a Neutral Arbitrator and a Party-Appointed Arbitrator
August 07, 2018 —
Celia B. Waters - Saxe Doernberger & Vita, P.C.On June 7, 2018, the Second Circuit Court in Certain Underwriting Members of Lloyds of London v. Fla., Dep’t of Fin. Servs.,1 held that a party-appointed arbitrator should not be held to the same standard as a neutral arbitrator. The Court vacated a district court’s order vacating an arbitral award in a reinsurance dispute between Insurance Company of Americas (“ICA”) and Certain Underwriting Members of Lloyds of London (“Underwriters”). The case was one of first impression for the Second Circuit on how to determine the standard of evident partiality challenged to a party-appointed arbitrator.
Underwriters reinsured ICA under a series of treaties. The treaties each contained an arbitration clause requiring that disputes be adjudicated by an arbitration panel consisting of three members: one party-appointed arbitrator for each party, and a neutral. The clause required only that the arbitrators “be active or retired disinterested executive officers of insurance or reinsurance companies or Lloyd’s London Underwriters.”
Read the court decisionRead the full story...Reprinted courtesy of
Celia B. Waters, Saxe Doernberger & Vita, P.C.Ms. Waters may be contacted at
cbw@sdvlaw.com
OSHA/VOSH Roundup
August 31, 2020 —
Christopher G. Hill - Construction Law MusingsIn an unusual flurry of occupational safety related activity, the Virginia courts decided two cases in the last week relating to either the review of occupational safety regulations themselves or their enforcement.
In Nat’l College of Business & Technology Inc. v. Davenport (.pdf), the Virginia Court of Appeals considered what constitutes a “serious” violation of the exposure to asbestos Virginia Occupational Safety & Health (VOSH) regulations. The facts found by the Salem, Virginia Circuit Court were that employees of the petitioner college were exposed to asbestos insulation when they were required to enter a boiler room to retrieve paper files. However, no evidence was presented regarding the length of time or level of exposure at the Circuit Court level. Despite the lack of evidence regarding the level or extent of exposure, the Circuit Court upheld the VOSH citation for exposure and the level of violation at a “serious” level with the attendant penalty.
The Virginia Court of Appeals disagreed with the second finding. The appellate court determined that the lack of evidence regarding the level of exposure (whether length or extent) made the serious level violation an error. The Court stated that merely presenting evidence that asbestos is a carcinogen is not enough given the number of carcinogenic materials in existence and then remanded the case back to Circuit Court to reconsider the penalty level.
Read the court decisionRead the full story...Reprinted courtesy of