Surety's Settlement Without Principal's Consent Is Not Bad Faith
January 05, 2017 —
Tred R. Eyerly – Insurance Law HawaiiThe Sixth Circuit found that the surety did not act in bad faith when it settled the general contractor's claims against the State of Michigan over delays on a construction project. Great Am. Ins. Co. v. E.L. Bailey & Co., 2016 U.S. App. LEXIS 20018 (6th Cir. Nov. 7, 2016).
Bailey, the general contractor, entered into a surety agreement under which Great American would issue surety bonds on behalf of Bailey in the construction of a kitchen at a State prison. Bailey, the principal, paid Great American (GAIC), the surety, to provide bonds guaranteeing contract performance to the State, the obligee or owner. GAIC provided a performance bond, guaranteeing performance of the contract work, and a payment bond, guaranteeing payments to subcontractors and suppliers. Under the agreement, Bailey would indemnify GAIC for all payments or other expenses GAIC incurred due on either bond, and would pay upon demand collateral in an amount to be determined by GAIC. In the event of an alleged breach by Bailey, the agreement assigned to GAIC all Bailey's rights under its contract with the State and well as all its claims against any party.
Bailey never finalized completion, and GAIC reached agreement with the State for another contractor to complete the project.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Don’t Waive Your Right to Arbitrate (Unless You Want To!)
October 19, 2017 —
David Adelstein - Florida Construction Legal UpdatesDoes your construction contract require you to arbitrate (instead of litigate) disputes arising out of the contract? If so, and you want to arbitrate, you do NOT want to do anything inconsistent or adverse with your right to arbitrate. Arbitration can be waived and you do not want arbitration to be waived if you believe this is the best forum to resolve your construction dispute. For instance, actively participating in a lawsuit through the prosecution or defense of issues in the lawsuit is certainly inconsistent with your right to arbitrate. This will result in a waiver of your right to compel arbitration.
In a non-construction dispute—a dispute involving a law firm and its former partner—the law firm sued the partner. Chaikin v. Parker Waichman LLP, 42 Fla. L. Weekly D2165b (Fla. 2d DCA 2017). There was a partnership agreement that required disputes to be resolved by arbitration. The law firm sued the partner claiming he violated a previously entered employment agreement that did not require arbitration. When the partner counterclaimed, the law firm claimed that the counterclaim must be compelled to arbitration because the counterclaim arose out of the partnership agreement that required arbitration. Guess what? The trial court actually compelled the counterclaim to arbitration! Crazy! Clearly, any employment agreement and partnership agreement were intertwined such that the dispute would involve the same set of facts and any claims would have a significant relationship to the partnership agreement.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
South Dakota Supreme Court Holds That Faulty Workmanship Constitutes an “Occurrence”
September 14, 2017 —
Samantha Martino - Saxe Doernberger & Vita, P.C.The South Dakota Supreme Court recently determined that damage resulting from a subcontractor’s failure to test soil compaction before constructing a home constituted an “accident” and was therefore an “occurrence” under a commercial general liability (CGL) policy.
In Owners Ins. Co. v. Tibke Construction, Inc., the homeowners hired Tibke Construction, Inc. to build a new house, and Tibke Construction hired subcontractor Jerry’s Excavating to perform excavation work. The homeowners contended that Jerry’s Excavating failed to do soil compaction testing before commencing construction, which resulted in the home being built on highly expansive soils, leading to damage including excessive settlement, cracking and structural unsoundness.
Read the court decisionRead the full story...Reprinted courtesy of
Samantha Martino, Saxe Doernberger & Vita, P.C.Ms. Martino may be contacted at
smm@sdvlaw.com
Century Communities Acquires Dunhill Homes Las Vegas Operations
April 08, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to Big Builder, “Colorado-based Century Communities” has acquired “the Las Vegas operations team and 1,849 lots of Dunhill Homes.” This brings Century’s “total land position of owned and controlled lots to 10,095, an increase of 21% since the end of 2013.”
“More than the homes and land inventory, this acquisition allows us to add an experienced operations team, with a reputation of delivering quality homes in well-located communities,” stated Robert Francescon and Dale Francescon, Co-Chief Executive Officers of Century Communities, in a statement as quoted by Big Builder. “Additionally, Las Vegas remains a land constrained market, and we are now uniquely positioned within communities that would be very difficult to replicate today, with land inventory to drive future growth.”
Read the court decisionRead the full story...Reprinted courtesy of
Structural Engineer Found Liable for Defects that Rendered a Condominium Dangerously Unsafe
June 22, 2016 —
Paul R. Cressman, Jr. – Ahlers & Cressman Construction Law BlogOn May 3, 2016, the Washington State Court of Appeals affirmed a jury’s verdict in favor of a condominium HOA against a structural engineer for $1,149,332 in damages.[1]
The project in question was The Pointe, an upscale condominium building in Westport, Washington. The developer was Dodson-Duus, LLC. The architect was Elkins Architects (“Elkins”). The structural engineer was Engineers Northwest, Inc. (“ENW”). ENW contracted with Elkins for the structural engineering work.
Birds flying past 3 construction cranesBoth the design and construction of the building suffered from defects. In particular, the lateral force resistance system was insufficient to withstand a large seismic event. The defects included improperly nailed shear walls, weak connections between shear walls and floor joists, improperly-sized floor sheathing, a weak second-floor diaphragm, and omitted hold-downs connecting shear walls to a steel beam. The use of gypsum sheathing also created a risk of corrosion to the building’s steel structure. Evidence tied each of these defects to some aspect of ENW’s structural calculations and designs. Evidence also tied omission of the hold-downs to the contractor’s construction decisions.
Read the court decisionRead the full story...Reprinted courtesy of
Paul R. Cressman, Jr., Ahlers & Cressman PLLC Mr. Cressman may be contacted at
pcressman@ac-lawyers.com
Project-Specific Policies and Products-Completed Operations Hazard Extensions
May 31, 2021 —
Jeremiah M. Welch - Saxe Doernberger & Vita1. Understanding the “Products-Completed Operations Hazard”
ISO commercial general liability (“CGL”) policies use the term “products-completed operations hazard” (“PCOH”) to define a category of risk which is treated specially by certain exclusions within the policy and often subject to separate limits of insurance. In construction, we think about PCOH as being about coverage for completed work.
Bodily injury and property damage arising out of completed work is a significant construction risk. Most construction contracts include warranty and indemnity obligations for completed work. All states allow lawsuits to be brought alleging bodily injury or property damage because of completed work based on common law. Contract and common law claims are subject to statutes of limitation – laws which define the time in which suits must be brought. Most states provide exceptions to their statutes of limitation for common law claims – the most common example is an extension to file a lawsuit based on a latent defect until the defect is discovered. Most states also have “statutes of repose” – laws that set a date after which suit may no longer be brought, no matter what the circumstances are. A construction contractor, therefore, has potential liability until the statute of repose period has expired. Thus, a contractor looks to ensure that it has coverage for the PCOH for its full statute of repose liability period.
Read the court decisionRead the full story...Reprinted courtesy of
Jeremiah M. Welch, Saxe Doernberger & VitaMr. Welch may be contacted at
JWelch@sdvlaw.com
Janus v. AFSCME
July 18, 2018 —
Ryan Foltz – Gordon & Rees Construction Law BlogOn June 27, 2018, the Supreme Court of the United States issued its decision in Janus v. AFSCME1. By a 5-4 vote, SCOTUS ruled that public employee unions cannot require non-members to pay union dues, even if those employees are benefiting from the services provided by the union. 28 states already had “right-to-work” laws on the books, meaning that unions in those states were already precluded from collecting fees from non-union members. This ruling makes that ban a national standard.
Read the court decisionRead the full story...Reprinted courtesy of
Ryan Foltz, Gordon & Rees Scully MansukhaniMr. Foltz may be contacted at
rfoltz@grsm.com
The General Assembly Adds Some Clarity to Contracts and Unlicensed Contractors
March 28, 2018 —
Christopher G. Hill – Construction Law MusingsFor years, the statute regarding performing construction without a valid license (
Va. Code 54.1-1115) was a bit murky. While that statute listed several prohibited acts, among them contracting without the proper class of license or use of the license of another, the consequences of such activity, in particular the effect that such action would have on the enforcement of a construction contract (Section C of the statute), were less than clear.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. Hill, PCMr. Hill may be contacted at