Limiting Liability: Three Clauses to Consider in your Next Construction Contract
June 25, 2019 —
Tara Lynch - Gordon & Rees Construction Law BlogIn your next contract, consider including some (or all!) of the following clauses to limit your liability and maximize your profits.
Waiver of Consequential Damages
While a proven breach of contract will leave a design professional or contractor exposed to direct or compensatory damages, a waiver of consequential damages will help “stop the bleeding” and protect the design professional or contractor from paying every damage that might flow from the breach. Consequential damages include those damages which indirectly flow from the breach of contract, for example, lost rents, lost profits, lost use, lost opportunity, loss of employee productivity, and damages to reputation.
The American Institute of Architects (AIA) has included a mutual waiver of consequential damages in its sample A201 for over 20 years. The AIA provision includes a definition of consequential damages which are waived, including many of the examples cited above. However, the AIA waiver of consequential damages clause carves out an exception for liquidated damages to the owner. Prudent design professionals and contractors will strike this exception so as not to render the clause meaningless. A well-drafted waiver clause will be mutual, will define which damages are consequential versus direct, and will not contain exceptions.
Read the court decisionRead the full story...Reprinted courtesy of
Tara Lynch - Gordon & Rees Scully MansukhaniMs. Lynch may be contacted at
tlynch@grsm.com
California Appeals Court Remands Fine in Late Completion Case
November 18, 2011 —
CDJ STAFFThe California Court of Appeals in Stanislaus County has reversed the decision of the lower court in Greg Opinski Construction Inc. v. City of Oakdale. The earlier court had awarded the city of judgment of $54,000 for late completion, $3,266 for repair of construction defects and interest, and $97,775 in attorneys’ fees. The late completion of the project was due to actions by the City of Oakdale, however, the court rejected Opinski’s argument that the California Supreme Court decision in Kiewit did not allow this, as his contract with the city established a procedure for claiming extensions.
The appeals court noted that the Kiewit decision has been “criticized as an unwarranted interference in the power of contracting parties to shift the risk of delays caused by one party onto the other party by forcing the second party to give the first notice of any intention to claim an extension of time based on delays caused by first.” They cited Sweet, a professor at Boalt Hall, UC Berkeley’s law school, that Kiewit “gutted” the “provision that conditions the contractor’s right to claim an extension of time for delays beyond his control.”
Further changes in California law in response to the Kiewit decision lead to the current situation which the court characterized as “if the contractor wished to claim it needed an extension of time because of delays caused by the city, the contractor was required to obtain a written change order by mutual consent or submit a claim in writing requesting a formal decision by the engineer.”
Opinski also argued that the lower court misinterpreted the contract. The Appeals court replied that “Opinski is mistaken.” He cited parts of the contract regarding the increase of time, but the court rejected these, noting that “an inability to agree is not the same as an express rejection.”
The court also rejects Opinski’s appeal that “the evidence the project was complete earlier than September 30, 2005, is weightier than the evidence to the contrary,” which they describe as “not a winning appellate argument.” The court points out that the role of an appeals court is not to reweigh the evidence, but to determine “whether the record contains substantial evidence in support of the judgment.”
The court did side with Opinski on one question of the escrow account. They rejected most of his arguments, repeating the line “Opinski is mistaken” several times. They decided that he was mistaken on the timing of the setoff decision and on whether the city was the prevailing party. However, the appeals court did find that Opinski was not liable for interest on the judgment.
The appeals court rejected the awarding of prejudgment interest to the city as the funds from which the judgment was drawn was held in an escrow account. The court noted that the city had access to the funds and could “access the funds when it determined that Opinski had breached the contract.” The appeals court noted that the judgment exhausted the escrow balance and remanded the case to the lower court to determine the amount own to Opinski.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Tenth Circuit Reverses District Court's Ruling that Contractor Entitled to a Defense
October 24, 2023 —
Tred R. Eyerly - Insurance Law HawaiiAfter the district court granted the insured contractor's motion for judgment on the pleadings on the duty to defend, the Tenth Circuit found there was no coverage and reversed. Owners Ins. Co. v. Greenhalgh Planning & Development, Inc., 2023 U.S. App. LEXIS 20137 (10th Cir. Aug. 4, 2023).
Greenhalgh remodeled a house and barn for Michelle and Steven Pickens. After completion of the project, the Pickens sold the property to Teague and Michelle Cowley. The Cowleys later sued the Pickenses asserting various fraud and breach of contract claims. The complaint alleged that the Pickenses misled them into reasonably believing that the barn was a habitable structure, even though it did not qualify as such under the applicable building code because it lacked a fire-sprinkler system.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Dispute Over Exhaustion of Primary Policy
May 20, 2015 —
Tred R. Eyerly – Insurance Law HawaiiIn a dispute between the excess and primary carriers, the Fifth Circuit determined the primary policy was exhausted, triggering coverage under the excess policy. Amerisure Mut. Ins. Co. v. Arch Spec. Ins. Co., 2015 U.S. App. LEXIS 6627 (5th Cir. April 21, 2015).
Amerisure issued a CGL policy to Admiral Glass & Mirror Co. The policy provided excess over any coverage under a controlled insurance program policy. Arch issued an Owner Controlled Insurance Program (OCIP) policy to Endeavor Highrise, LP and to its contrators and subcontractors for bodily injury and property damage arising out of the construction of the Endeavor Highrise. Admiral was a subcontractor insured under the OCIP.
The OCIP had combined bodily injury and property damage limits of $2,000,000 per occurrence, a general aggregate limit of $2,000,000 and a products-completed operations aggregate limit of $2,000,000. The OCIP contained a Supplementary Payments provision which provided that Arch would pay "[a]ll expenses we incur" in connection with any covered claim, and that "[t]hese payments will not reduce the limits of insurance." Endorsement 16, however, expressly deleted and replaced this statement with: "[supplementary payments] will reduce the limits of insurance." The OCIP also provided that Arch's duty to defend ended "when we have used up the applicable limit of insurance in the payment of judgments or settlements."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Intricacies of Business Interruption Claim Considered
January 07, 2015 —
Tred R. Eyerly – Insurance Law HawaiiReaching into the weeds to analyze a business interruption claim, the Massachusetts Court of Appeals determined the cost of ordinary payroll could be included in the calculation of net profit or loss in determining business loss income when business is resumed quickly after a fire. Verrill Farms, LLC v. Farm Family Cas. Ins. Co., 2014 Mass. App. LEXIS 145 (Mass. App. Ct. Nov. 4, 2014).
The insured suffered a fire loss at its farm store. Within two days, the business was reopened at alternate locations at reduced capacity. Within a month, the business had resumed nearly full capacity in temporary locations. No employees were laid off. This allowed the insured to maintain its business and generate income.
The insured submitted a claim for loss of business income, based on its loss of net income in the year after the fire. The insurer paid a sum considerably less than the claim based upon its interpretation of what expenses could be included in a calculation of net profit or loss in order to determine loss of business income. The trial court held that the insurer did not have to pay the cost of ordinary payroll beyond the sixty-day limit, and granted summary judgment in the insurer's favor.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Damp Weather Not Good for Wood
May 10, 2013 —
CDJ STAFFCold and wet weather was not bad news for the lumber industry. The weather in the first quarter set or tied records for both precipitation and low temperatures. Not good weather for building. Construction was delayed as a result, leading to less call for lumber.
In response, there was a 15 percent drop in lumber futures, continuing a decline.
Read the court decisionRead the full story...Reprinted courtesy of
How the Jury Divided $112M in Seattle Crane Collapse Damages
April 04, 2022 —
Richard Korman - Engineering News-RecordThe jury verdict in a wrongful death lawsuit against companies involved in a 2019 Seattle crane collapse that killed four people split damages among three different companies—and also blamed a fourth firm that wasn't a defendant—but not in a way that matched the state safety fines proposed against the firms.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
The Woodland Hills Office Secures a Total Defense Award on Behalf of their High-End Custom Home Builder Client!
June 04, 2024 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPPartner Daniel Crespo and Associate Theresa Mallen secured a total defense award in arbitration. Our client is a high-end custom home builder with a decades-long flawless record of museum quality construction. Our client was accused of performing substandard construction and the homeowners asserted a multiple million-dollar cost of repair. We took a zero-liability position and argued that the alleged defects were not defects at all but were rather mere reflections of an incomplete project. In sum, our client was forced to terminate the contract and cease construction due to the homeowners’ failure to make progress payments as they became due. The arbitration endured 16 days of testimony scattered over the course of 7 months.
Ultimately, the arbitrator ruled that there were no construction defects at the project and that the homeowners “shall take nothing.” The arbitrator also ruled in favor of our client on its affirmative claim for monies owed by the homeowners’ breach of contract plus interest. A total victory for our client.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP