Owners and Contractors Beware: Pennsylvania (Significantly) Strengthens Contractor Payment Act
June 13, 2018 —
Wally Zimolong – Supplemental Conditions Yesterday, Governor Tom Wolf signed into law House Bill 566 which make major changes to Pennsylvania’s Contractor and Subcontractor Payment Act. Owners and General Contractors that fail to take head of the changes could face significant financial consequences.
The Pennsylvania Contractor and Subcontractor Payment Act, known as CAPSA or simply the Payment Act, was passed into law in 1994. The intent was “to cure abuses within the building industry involving payments due from owners to contractors, contractors to subcontractors, and subcontractors to other subcontractors.” Zimmerman v. Harrisburg Fudd I, L.P., 984 A.2d 497, 500 (Pa. Super. Ct. 2009). In reality, abuses still occurred. While the Payment Act purportedly dictated a statutory right to payment within a certain amount of time and imposes stiff penalties for failure make payment, including 1% interest per month, 1% penalty per month, and reasonable attorneys fees, the language of the Payment Act left recalcitrant contractors with wiggle room. Particularly, the Payment Act allowed owners and higher tier subcontractors to withhold payment “deficiency items according to the terms of the construction contract” provided it notified the contractor “of the deficiency item within seven calendar days of the date that the invoice is received.” 73 P.S. Section 506. The problem was that the Payment Act did not expressly state where the notice must be in written, what it must say, and what happened if notice was not given.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
You Cannot Always Contract Your Way Out of a Problem (The Case for Dispute Resolution in Mega and Large Complex Construction Projects)
September 16, 2024 —
Lisa D. Love - The Dispute ResolverMost experienced commercial transaction and construction attorneys strive to negotiate a concisely written and well-drafted contract that addresses all scenarios and issues that creative and highly contemplative professionals can conjure. Although contracts are extremely important in construction projects, “you can’t generally contract your way out of a problem,” states Michael Loulakis, a founder of Capital Project Strategies, LLC and a nationally recognized expert on project delivery systems in complex public sector design-build projects and public-private partnership programs. Loulakis adds, “the contract certainly matters. But particularly when the losses are big, litigators prosecuting the contractors often find effective ways to argue that facts and circumstances trump the contract.” However, “the difference between the best construction projects and the worst construction projects is not the written words of the contracts but how the parties have committed to engage collaboratively and with trust to complete the project,” notes Robynn Thaxton, an attorney and consultant with Thaxton Parkinson PLLC and Progressive Design-Build Consulting, LLC and one of the leading experts in construction law and alternative procurement on a national basis.[i]
In large, complex construction projects, the need for parties to collaboratively resolve disputes is highlighted by the judicial acceptance of the “Doctrine of the Contextual Contract”[ii] to interpret construction contracts. “As construction’s increasing technological and managerial complexity came to be recognized, some common law courts began turning away from strict interpretation of language within the four corners of a contract and moving toward recognizing in the enforcement of contracts the construction industry’s own experience, customs, practices and implied conditions and duties and the factual context underlying the contract. Courts [began the journey] along the road from ‘text’ to ‘context.’”[iii] Thus, the precise wording of the contract has become less important and industry practices and other conditions provide insight for resolving disputes. Consequently, despite the specific language of any construction contract and the clear allocation of responsibilities and risks, early dispute evaluation and resolution are critical to a successful project.
Read the court decisionRead the full story...Reprinted courtesy of
Lisa D. Love, JAMS
Insurers Subrogating in Arkansas Must Expend Energy to Prove That Their Insureds Have Been Made Whole
July 30, 2019 —
Michael J. Ciamaichelo - The Subrogation StrategistArkansas employs the “made whole” doctrine, which requires an insured to be fully compensated for damages (i.e., to be “made whole”) before the insurer is entitled to recover in subrogation.[1] As the Riley court established, an insurer cannot unilaterally determine that its insured has been made whole (in order to establish a right of subrogation). Rather, in Arkansas, an insurer must establish that the insured has been made whole in one of two ways. First, the insurer and insured can reach an agreement that the insured has been made whole. Second, if the insurer and insured disagree on the issue, the insurer can ask a court to make a legal determination that the insured has been made whole.[2] If an insured has been made whole, the insurer is the real party in interest and must file the subrogation action in its own name.[3] However, when both the insured and an insurer have claims against the same tortfeasor (i.e., when there are both uninsured damages and subrogation damages), the insured is the real party in interest.[4]
In EMC Ins. Cos. v. Entergy Ark., Inc., 2019 U.S. App. LEXIS 14251 (8th Cir. May 14, 2019), EMC Insurance Companies (EMC) filed a subrogation action in the District Court for the Western District of Arkansas alleging that its insureds’ home was damaged by a fire caused by an electric company’s equipment. EMC never obtained an agreement from the insureds or a judicial determination that its insureds had been made whole. In addition, EMC did not allege in the complaint that its insureds had been made whole and did not present any evidence or testimony at trial that its insureds had been made whole. After EMC presented its case-in-chief, the District Court ruled that EMC lacked standing to pursue its subrogation claim because “EMC failed to obtain a legal determination that its insureds had been made whole . . . prior to initiating this subrogation action.” Thus, the District Court granted Entergy Ark., Inc.’s motion for judgment as a matter of law and EMC appealed the decision.
Read the court decisionRead the full story...Reprinted courtesy of
Michael J. Ciamaichelo, White and Williams LLPMr. Ciamaichelo may be contacted at
ciamaichelom@whiteandwilliams.com
Time to Update Your Virginia Mechanic’s Lien Forms (July 1, 2019)
May 01, 2019 —
Christopher G. Hill - Construction Law MusingsIn a few of my recent posts here at Construction Law Musings, I’ve discussed a few bills that were considered and/or passed in the General Assembly this year. One of the bills is one close to my heart and a subject much discussed here, namely mechanic’s liens.
HB2409 passed both houses of the General Assembly and has been signed by the Governor. This bill reconciled the language found in Virginia Code Sec. 43-4 with the various forms for general contractor, subcontractor and sub-subcontractor/supplier forms found in later sections of the code. As you will see if you download the .pdf of the bill as signed, this involved some tweaks to 43-4 and some updates to the mechanic’s lien forms that are in the code. The recent Desai case from the Virginia Supreme Court made it clear that such action was necessary.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrissghill@constructionlawva.com
Harmon Towers Duty to Defend Question Must Wait, Says Court
March 01, 2012 —
CDJ STAFFThe Harmon Towers project in Las Vegas was eventually halted short of the planned forty-seven stories after “it was determined that there was substantial defective construction, including defective installation of reinforcing steel throughout the Harmon.” The American Home Insurance Company and Lexington Insurance Company put forth a claim that they had no duty to defend Perini Construction, the builder of the defective Harmon Towers. Further, American Home seeks to recover the monies American reimbursed Perini. The United States District Court of Nevada ruled in the case of American Home Assurance Co. v. Perini Building on February 3, 2012.
The two insurance companies covered Perini and its subcontractors, Century Steel, Pacific Coast Steel, and Ceco Concrete Construction. Century Steel was the initial subcontractor for the reinforcing steel; they were later acquired by Pacific Coast Steel. In this current case, Perini Construction is the sole defendant.
Perini sought a dismissal of these claims, arguing that without the subcontractors joined to the case, “the Court cannot afford complete relief among existing parties.” The court rejected this claim, noting that the court can determine the duties of the insurance companies to Perini, which the court described as “separate and distinct from those of the subcontractors.” The subcontractors “have not claimed an interest in the subject matter of the action.” The court concluded that it could determine whether Perini was entitled or not to coverage without affecting the subcontractors. The court rejected Perini’s claim.
Perini also asked the court to abstain from the case, arguing that it was better heard in a state court. The court noted that several considerations cover whether a case is heard in state or federal courts. The court noted that if the case weighed heavily on state law, the state courts would be the obvious location. Further, if there were a parallel action in the state courts, “there is a presumption that the whole suit should be heard in state courts.” This is, however, no parallel state suit, although the court noted that Perini has “threatened” to do so.
However, the issue of who is to blame for the problems at Harmon Towers has not been resolved. The court concluded that until the “underlying action” was concluded, it was premature to consider the issues raised in this case while the earlier lawsuit was still in progress. The court denied Perini’s motion to dismiss the case. Given that the outcome of the earlier construction defect case may lead to further litigation in state court, the District Court granted Perini’s motion to abstain, but staying their judgment until the construction defect case is resolved.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Hawaii Federal District Court Rejects Insurer's Motion for Summary Judgment on Construction Defect Claims
November 06, 2018 —
Tred R. Eyerly - Insurance Law HawaiiTaking into consideration a "Revised Occurrence Endorsement," the federal district court determined the insurer had a duty to defend. Gemini Ins Co. v. Constrx Ltd., 2018 U.S. Dist. LEXIS 163453 (D. Haw. Sept. 24, 2018).
Constrx Ltd. (CRX) contracted with the AOAO to perform remedial construction repairs to condominium buildings and apartment units. CRX asserted that it completed all work, including charge orders and punch list items and it left the site. CRX was paid less that the contract amount and demanded arbitration against the AOAO. In the arbitration the AOAO relied upon a report by Posard Brock & Associates (PBA) Report which set forth the AOAO's claims against CRX, including corrective work, remaining punch list work, construction delay costs, cost overruns, and other items justifying its payment than less that the contract amount.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
New York’s Second Department Holds That Carrier Must Pay Judgment Obtained by Plaintiff as Carrier Did Not Meet Burden to Prove Willful Non-Cooperation
November 23, 2020 —
Craig Rokuson - Traub LiebermanIn the recent case of DeLuca v. RLI Insurance Company, 2020 WL 5931054 (October 7, 2020), the Supreme Court, Appellate Division, Second Department held that RLI had a duty to pay a judgment obtained by an underlying plaintiff against RLI’s insured, MLSC. The underlying plaintiff brought the action directly against the carrier after obtaining a judgment against MLSC, and when the judgment remained unsatisfied, serving RLI with the judgment. As an initial matter, the court found that the direct action by the plaintiff was proper under New York Insurance Law 3420(a), which allows for an injured plaintiff to maintain a direct action against a carrier if a judgment against that carrier’s insured remains unsatisfied for a period of 30 days and the carrier is served with that judgment. In that event, the plaintiff steps into the shoes of the insured and is entitled to the rights of the insured (and is also subject to the carrier’s coverage defenses).
Reprinted courtesy of
Craig Rokuson, Traub Lieberman
Mr. Rokuson may be contacted at crokuson@tlsslaw.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Commercial Real Estate in 2023: A Snapshot
January 17, 2023 —
Adam J. Weaver - Gravel2Gavel Construction & Real Estate Law BlogAs we close out the last remaining weeks of 2022, all eyes look ahead to 2023. Below is a quick snapshot highlighting three trends and predictions that may continue to shape the commercial real estate landscape in 2023.
- Office space and the digital economy present attractive investment opportunities and potential. Even with all of the chatter about office vacancies during the last three years, according to Moody’s Analytics, “it’s important to note that none of the regions across the U.S. have seen office vacancy rates dip below their pre-pandemic Q4 2019 levels.” This might be due to creative and reimagined office spaces as the return to office continues. The hybrid work format and flexibility in spaces will continue in 2023.
- Data analytics and Proptech will continue to play a larger role, allowing property owners and tenants to collaborate to provide more efficiency, whether to achieve sustainability goals or leverage technology like immersive experiences to entice tenants to new spaces. An increase in demand for technology to solve issues will most likely continue in commercial real estate.
Read the court decisionRead the full story...Reprinted courtesy of
Adam J. Weaver, PillsburyMr. Weaver may be contacted at
adam.weaver@pillsburylaw.com