Saved By The Statute: The Economic Loss Doctrine Does Not Bar Claims Under Pennsylvania’s Unfair Trade Practices and Consumer Protection Law
May 10, 2021 —
Gus Sara - The Subrogation StrategistIn Earl v. NVR, Inc., No. 20-2109, 2021 U.S. App. LEXIS 6451, the U.S. Court of Appeals for the Third Circuit (Third Circuit) considered whether, under Pennsylvania law, the plaintiff’s Unfair Trade Practices and Consumer Protection Law (UTPCPL) claims against the builder of her home were barred by the economic loss doctrine. The UTPCPL is a Pennsylvania statute that prohibits “unfair methods of competition and unfair or deceptive acts or practices in the conduct of any trade or commerce.” 73 Pa. Stat. Ann. § 201-3. The Third Circuit previously addressed the impact of the economic loss doctrine on UTPCPL claims in Werwinski v. Ford Motor Co., 286 F.3d 661 (3d Cir. 2002). In Werwinski, the court held that the plaintiff’s UTPCPL claim was barred by the economic loss doctrine. The Court of Appeals overturned its decision in Werwinski and held that the economic loss doctrine does not bar UTPCPL claims since such claims are statutory, and not based in tort.
In Earl, the plaintiff, Lisa Earl, entered into an agreement with defendant NVR, Inc. (NVR) for the construction and sale of a home in Allegheny County, Pennsylvania. Ms. Earl learned of the home through NVR’s marketing, which described the home as containing “quality architecture, timeless design, and beautiful finishes.” Ms. Earl alleged that during the construction of the home, she had further discussions with agents of NVR, who made representations that the home would be constructed in a good and workmanlike manner and that any deficiencies noted by Ms. Earl would be remedied. The defendant also assured Ms. Earl that the home would be constructed in accordance with relevant building codes and industry standards. After moving into the home, Ms. Earl discovered several material defects in the construction. She provided notice of these defects to NVR, but NVR’s attempts to repair some of the defects were inadequate.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
No Repeal Process for Rejected Superstorm Sandy Grant Applications
February 12, 2014 —
Beverley BevenFlorez-CDJ STAFFEven though it’s been revealed that “faulty data” was used to reject many New Jersey recovery grants for victims of Superstorm Sandy, the state has announced that it’s too late to appeal, according to The Wall Street Journal.
“The applicants were informed by letter that they weren't eligible,” state officials told The Wall Street Journal, “and it should have been clear that they needed to appeal last year, so the application process won't be reopened.”
The majority of the rejected applicants that did appeal within the open period were found to be eligible for the grant: “Nearly 80% of people who appealed their rejections ended up winning their cases, according to data released by the Fair Share Housing Center, a public-interest law firm critical of the Christie administration. And of the 8,007 applicants rejected from both programs, 5,583 didn't appeal, or 70%, according to Fair Share Housing Center's analysis.”
U.S. Representative Bill Pascrell called for “an independent monitor” to be “appointed to oversee the state’s storm spending ‘to ensure there isn’t further mismanagement.’”
Read the court decisionRead the full story...Reprinted courtesy of
New York Bars Developers from Selling Condos due to CD Fraud Case
October 15, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to GlobeSt, New York “Attorney General Eric T. Schneiderman has announced a settlement agreement that bars developers Joseph Scarpinito and Shiraz Sanjana—and five affiliated entities they own and operate—from offering or selling securities, including condo and coop sales, in or from New York State.”
The settlement is in “result of an investigation by the Attorney General’s real estate finance bureau into allegations of fraud by the developers of the Mirada, an eight-story Harlem condominium.” GlobeSt also stated that the agreement “provides for binding arbitration with the condo purchasers for alleged construction defects, and requires the developers to pay $500,000 in penalties and fines to New York State.”
Read the court decisionRead the full story...Reprinted courtesy of
Corps of Engineers to Prepare EIS for Permit to Construct Power Lines Over Historic James River
May 01, 2019 —
Anthony B. Cavender - Gravel2GavelOn March 1, the U.S. Court of Appeals for the District of Columbia decided National Parks Conservation Assoc. v. Todd T. Simonite, Lieutenant General, et al. The case involves an application to the U.S. Army Corps of Engineers (Corps) for a construction permit to build electric power lines over the “historic James River, from whose waters Captain John Smith explored the New World.”
The Corps concluded after reviewing the thousands of comments submitted to it in connection with this application, and after considering the views of several government agencies and conservation groups, that an Environment Impact Statement (EIS) was not required, and that its Environmental Assessment assured the Corps that the project would not result is significant environmental impacts. The Court of Appeals has concluded that, based on this evidence, the Corps’ refusal to prepare an EIS thoroughly discussing all these points was arbitrary and capricious. The Corps has been ordered to prepare the EIS and to take special note of its obligations under the National Environmental Protection Act (NEPA), the Clean Water Act (CWA) and its obligations under the National Historic Preservation Act.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Winning Attorney Fees in Litigation as a California Construction Contractor or Subcontractor
December 27, 2021 —
William L. Porter - Porter Law GroupThe General Rule in California: The Winner Does NOT Receive Attorney Fees and Costs:
There is a common misconception that court decisions require the loser in a lawsuit to reimburse the winner for the fees and costs incurred during the lawsuit. Reliance on this misconception in developing a legal strategy for dealing with disputes is a serious strategic error. Where the legal issue is, for example, “breach of contract,” the general rule in California is that there are only two methods by which the winning litigant will be awarded the attorney fees and costs incurred in bringing or defending the lawsuit. The first of these is if the contract in question contains an effective attorney fee clause specifically providing that the prevailing party will recover their attorney fees and costs. The second is if there is a statute on point which provides that the prevailing party will be awarded those fees and costs. The general rule in California is that each party pays their own attorney fees and costs, unless there is an independent legal basis that provides otherwise. This is known as the “American Rule,” used throughout most of the country.
The Issue is Important Because Spending More Money Than You Can Be Awarded is a Losing Strategy:
The importance of whether the prevailing party in a lawsuit will be awarded their fees and costs cannot be underestimated. The party contemplating whether to bring a lawsuit must seriously consider whether it is even worth the trouble. In many cases, unless the one bringing the lawsuit (the “plaintiff”) is entitled to be reimbursed for the considerable attorney fees and costs incurred in bringing the case, it is just not worth doing so. There is no point spending $50,000 on attorneys on a $40,000 claim unless the plaintiff can be awarded both the $40,000 and the $50,000 if the plaintiff wins. Unless fees and costs are awarded, the plaintiff will still be out $10,000 in the very best of cases. For a party sued (the “defendant”) a similar situation arises in that the defendant faces the reality that it may be less expensive to just pay on a frivolous or false claim than to fight it. Either scenario is unsatisfactory. On the whole, it is beneficial to have an attorney fee clause in a contract when either a plaintiff or a defendant must vindicate its rights. Both deserve to be fully compensated to achieve justice. It is also beneficial to have an attorney fee clause in a contract to encourage the one who is at fault to resolve the case rather than risk paying the fees and costs of the other party who is likely to win the case. In either case, the presence of an attorney fee clause facilitates the party in the right and encourages resolution outside of litigation. These are admirable societal goals.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
California Supreme Court Rights the “Occurrence” Ship: Unintended Harm Resulting from Intentional Conduct Triggers Coverage Under Liability Insurance Policy
June 13, 2018 —
Scott S. Thomas - Payne & Fears Legal AlertSUMMARY
In a ruling that bodes well for policyholders, the California Supreme Court provides much-needed clarity on the question of when a so-called "intentional act" may give rise to insurance coverage under a liability insurance policy. In Liberty Surplus Insurance Corp. v. Ledesma & Meyer Construction Co., Case No. S23765 (Cal. June 4, 2018), the Court holds that an employer's potential liability for negligent hiring, after its employee allegedly abused a 13-year old student, is the result of an "occurrence" and is thus covered under the employer's liability insurance policy.
COURT OPINION
The court's opinion dispels the misguided notion that an intentional act resulting in unintended harm is never an "occurrence" and can never trigger coverage. What matters, according to the Court, is that, from the insured's point of view, the consequences of its conduct are "unexpected, unforeseen, or undesigned" - even if the conduct is intentional. And in a concurring opinion, Justice Liu rightfully questions the legitimacy of the notion that intentional conduct cannot trigger coverage, even when it produces an unintended result, unless, in the words of a 1989 appellate court decision, some "additional, unexpected, independent, and unforeseen happening occurs that produces the damage." As Justice Liu explains, this intervening "happening" may be something as simple as the insured's mistaken belief that he was acting in self-defense, or that the victim had consented to the insured's conduct. This much-needed clarification restores vitality to the fundamental principle that injuries are "accidental" when they are "unexpected, unforeseen, or undesigned," regardless of their cause.
Read the court decisionRead the full story...Reprinted courtesy of
Scott S. Thomas, Payne & FearsMr. Thomas may be contacted at
sst@paynefears.com
New Strategy for Deterring Intracorporate Litigation?: Delaware Supreme Court Supports Fee-Shifting Bylaws
May 13, 2014 —
Marc Casarino and Lori Smith – White and Williams LLPA fee-shifting bylaw of a Delaware non-stock corporation is not facially invalid according to the Delaware Supreme Court’s May 8, 2014 opinion in ATP Tour, Inc. v. Deutscher Tennis Bund.
In this case, ATP Tour, Inc., a non-stock membership corporation (“ATP”) governed by a seven member board, had adopted a bylaw provision which provided that current and former members of ATP would be responsible for the litigation costs arising out of any litigation initiated by any such member against ATP or any of the other members in which the initiating party did not obtain a judgment on the merits that substantially achieved in substance and amount the full remedy sought. The bylaw provision had been adopted, in accordance with ATP’s charter, by the Board unilaterally without any consent from the members. The members had agreed at the time they joined ATP to be bound by the bylaws, as amended from time to time. Two members of ATP initiated a suit against ATP relating to certain actions taken with respect the ATP’s tournament schedule and format alleging both federal antitrust claims and Delaware fiduciary duty claims but did not prevail on any of their claims. ATP then moved to recover its legal fees relating to such actions.
Reprinted courtesy of
Marc Casarino, White and Williams LLP and
Lori Smith, White and Williams LLP
Mr. Casarino may be contacted at casarinom@whiteandwilliams.com; Ms. Smith may be contacted at smithl@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Pacing in Construction Scheduling Disputes
September 14, 2017 —
Luke Mecklenburg - Snell & Wilmer Real Estate Litigation BlogOn a high level, construction delay litigation involves sorting out the impacts to the critical project path and determining which party is responsible for those impacts. One of the more difficult elements of this process is determining whether a delay would have occurred regardless of one party’s critical path impact due to a separate, independent impact to the critical path by the other party. For example, a contractor cannot collect delay damages for delays caused by the owner if the contractor itself was causing independent impacts that would have pushed off the completion date anyway.
However, the concept of “pacing” provides a potential defense for a party who is not on pace with the as-planned schedule for noncritical activities, even where those activities are still ongoing after the planned completion date. “Pacing delays” are a type of concurrent delay that occur when one party makes a conscious decision to decelerate or slow down the pace of noncritical activities to keep pace with the critical delays of another party. A more formal definition would be “deceleration of the work of the project, by one of the parties to a contract, due to a delay caused by the other party, so as to maintain steady progress with the revised overall project schedule.” Zack, Pacing Delays–The Practical Effect, Construction Specifier 47, 48 (Jan. 2000). A party to the construction process may decide to slow down its performance of noncritical activities to keep pace with the delayed progress. For example, contractors may adjust the pace of their work in light of delays in owner-furnished equipment, delays by other multiple prime contractors, delays in permits, limited access, or differing site conditions. Owners may slow down their response time to requests for information or submittals, or postpone the delivery of owner-furnished equipment or the processing of change orders. Id. at 48.
Read the court decisionRead the full story...Reprinted courtesy of
Luke Mecklenburg, Snell & WilmerMr. Mecklenburg may be contacted at