Oregon Courthouse Reopening after Four Years Repairing Defects
April 01, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Courthouse Square in Marion County, Oregon is due to reopen after four years and nearly $23 million of repair costs to fix structural defects, according to the Statesman Journal. The square includes a courthouse building and bus mall, and is jointly owned by the county and transit district.
Two years after the Courthouse Square had been built, cracks were observed “in the building’s walls” and “paving stones on the bus mall shifted and settled.” A construction defect suit was filed in 2006.
However, the situation worsened in July of 2010 when “engineers determined that the entire complex was dangerous,” according to the Statesman Journal. “Building safety officials gave Courthouse Square’s occupants 60 days to move out, forcing county and transit district operations into temporary leased space.”
Now that the structural repairs have been completed, Dave Clark, project manager with Structural Preservation Systems LLC (the company awarded the repair contract), stated that the building’s structure is now stronger than most buildings. “If there’s an earthquake, come to this building,” Clark said.
Read the court decisionRead the full story...Reprinted courtesy of
When Subcontractors Sue Only the Surety on Payment Bond and Tips for General Contractors
August 13, 2019 —
Ira M. Schulman & Emily D. Anderson - ConsensusDocsPayment bonds have been a staple of public construction projects since 1874, when the U.S. Congress first passed the Heard Act, which required that contractors obtain payment bonds for public projects to ensure that subcontractors and material suppliers have a way to recover their damages if an upstream contractor fails to pay for work performed and materials furnished on the project. The 1874 Heard Act has since been replaced by the 1935 Miller Act, and the concept has been expanded to construction projects funded by the states through state statutes known as “Little Miller Acts.” But the structure remains the same: On most public projects where the project’s cost exceeds $100,000, the prime contractor (the bond principal) is required to obtain a payment bond from a surety equal to the contract price to guarantee to subcontractors and material suppliers (the bond obligees) that the surety will pay for labor and materials under certain statutory or contractual conditions should the contractor fail to make payment.
A surety is jointly and severally liable with the contractor to the subcontractor, which means that the subcontractor may seek recovery against either the contractor or the surety or both, and the contractor and surety will be liable for the damages together. Put another way, in most states and in federal court, an unpaid subcontractor has the right to sue only the surety on the payment bond without joining the contractor because a contract of suretyship is a direct liability of the surety to the subcontractor.1 When the contractor fails to perform, the surety becomes directly responsible at once — it is unnecessary for the subcontractor to establish that the contractor failed to carry out its contract before the obligation of the surety becomes absolute.
Reprinted courtesy of
Ira M. Schulman, Pepper Hamilton LLP and
Emily D. Anderson, Pepper Hamilton LLP
Mr. Schulman may be contacted at schulmani@pepperlaw.com
Ms. Anderson may be contacted at andersone@pepperlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
9th Circuit Plumbs Through the Federal and State False Claims Acts
January 16, 2024 —
Garret Murai - California Construction Law BlogYou may have heard of the False Claims Act and know that it penalizes companies and individuals in contract with the government who present false claims. The federal False Claims Act was signed into law by President Abraham Lincoln in 1863 to penalize profiteers during the Civil War who were selling the Union Army moth eaten blankets, boxes of sawdust instead of guns, and sometimes re-selling the Army calvary horses several times over. Since then, many states, including California, as well as municipalities, have enacted their own false claim statutes.
As currently written, the federal False Claims Act provides for statutory penalties against any person who:
- “[K]nowingly presents, or causes to be presented, a false or fraudulent claim for payment or approval”;
- “[K]nowingly makes, uses or causes to be made or used, a false record or statement material to a false or fraudulent claim”;
- “[H]as possession, custody, or control of property or money used, or to be used, by the Government an knowingly delivers, or causes to be delivered, less than all of that money or property”;
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
U.K. Developer Pledges Building Safety in Wake of Grenfell
April 19, 2022 —
Ryan Hesketh - BloombergCrest Nicholson Plc intends to sign the building safety pledge set up in the aftermath of the Grenfell fire in 2017 to improve standards that may cost the U.K. developer as much as 120 million pounds ($157 million).
The company’s best estimate of further liability as a result of the pledge would be 80 million pounds to 120 million pounds, according to a statement Tuesday. Since 2019, Crest Nicholson has recorded 47.8 million pounds of net charges from obligations imposed after the fire at Grenfell Tower in London in which flammable cladding materials contributed to the deaths of 72 people.
The Secretary of State for the Department for Levelling Up, Housing and Communities announced in January the government’s intention to increase the legal obligation on developers to fix potentially dangerous buildings. Since then, Crest Nicholson has engaged in “intensive dialogue” with the government about the new guidelines, resulting in the decision to sign the pledge, the firm said in the statement.
The new restrictions will be enacted in law through proposed amendments to the Building Safety Bill that is currently passing through parliament. Crest Nicholson is currently considering whether any further regulatory approvals are required in respect of the proposed laws, according to the statement.
Read the court decisionRead the full story...Reprinted courtesy of
Ryan Hesketh, Bloomberg
Court Orders House to be Demolished or Relocated
April 26, 2011 —
Beverley BevenFlorezCDJ STAFFDecision Affirmed in Central Arkansas Foundation Homes, LLC v. Rebecca Choate
The Arkansas Court of Appeals affirmed the decision by the trial court in Central Arkansas Foundation Homes, LLC v. Rebecca Choate. In the trial case, Central Arkansas Foundation Homes (CAFH) sought payment for a home built for Choate, while Choate alleged that the builders committed multiple construction defects including using the wrong foundation materials and positioning the house in the wrong direction.
After the house was built, CAFH contacted Choate regarding payment, however, Choate alleged that the finished product did not match the contract. “ After CAFH completed construction, it obtained permanent home financing for Choate and tried to contact her to close the transaction. Choate did not respond until October 2005, when she sent CAFH a list of alleged construction defects, including that the house was facing in the wrong direction; that it was not built on a slab; and that the fireplace, garbage disposal, driveway, and storage area were missing. CAFH replied to Choate in writing, telling her that she had until January 6, 2006, to close on the house or CAFH would sell it. The correspondence enclosed worksheets showing that the amount Choate would owe at closing exceeded $94,000, which included interest that had accrued on the as-yet unpaid construction loan.”
Initially, the court found in favor of CAFH. “On April 18, 2007, Choate’s attorney withdrew from representing her. Soon thereafter, CAFH’s attorney asked the court to set a final hearing on the case. The attorney purportedly sent Choate a letter by regular mail on May 15, 2007, advising her that the case was set for trial on July 9, 2007. Choate, however, did not appear. CAFH did appear, and its general manager, John Oldner, testified to events leading up to the case and the amount of damages claimed. According to Oldner, the interest on the construction loan had accrued to the point that CAFH now sought $104,965.88 from Choate. The court found in favor of CAFH and entered judgment for that amount, plus attorney fees, on July 18, 2007. The court ruled that CAFH could sell the house and either remit any excess to Choate or look to Choate for the deficiency if the sales price did not cover the judgment.”
However, Choate successfully argued that she did not receive notice of the trial. A new trial was ordered, and the outcome was quite different. “On June 6, 2008, the circuit court entered judgment for Choate, ruling that the house was not in substantial compliance with the parties’ contract and that the contract should be rescinded. The court found that the house suffered from numerous construction defects, that the contract contemplated a slab rather than a concrete-pier foundation, and that CAFH ignored Choate’s complaints that the house was facing the wrong way. The judgment directed CAFH to hold Choate harmless on the construction loan, to deed Choate’s two acres back to her, and to remove the house from Choate’s property.”
The Court of Appeals “found that Choate would be unjustly enriched by retaining the benefit of the septic systems and utility lines that CAFH installed on her land. The court therefore awarded $5340 to CAFH as a quantum-meruit recovery for the value of that work. CAFH contends that the award is not sufficient, but we see no clear error.” In the end, the Court of Appeals provided this reason for declining to reverse the trial court’s decision: “The court in this case apparently concluded that the house constructed by CAFH was so fundamentally at odds with Choate’s contractual expectations that she was not unjustly enriched and should simply be, as nearly as possible, returned to the status quo ante. Accordingly, the court ordered the house removed from her property and permitted CAFH to either relocate the house or salvage the house’s materials and unused appliances. We decline to reverse the court’s weighing of the equities in this manner.”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Mediation Scheduled for Singer's Construction Defect Claims
February 11, 2013 —
CDJ STAFFA judge has scheduled mediation and trial over the claims of Rihanna that her Beverley Hills home suffers from construction defects. The singer claims that the previous owners, Adriana and Heather Rudomin, did not disclose construction defects which lead to flooding from water leaks in January 2010.
The Rudomins did not appear at the February 7th hearing, and the judge fined them $500. They will be required to explain their absence on March 12. The mediation will begin on May 7. The trial has been scheduled for February 24, 2014, and is expected to last three weeks.
Read the court decisionRead the full story...Reprinted courtesy of
Builder Survey Focuses on Green Practices of Top 200 Builders
October 01, 2014 —
Beverley BevenFlorez-CDJ STAFFBuilder magazine reported that the 2013 Builder 100/Next 100 survey provided data on how many builders constructed homes using a certified third-party green rating system. They discovered that nearly half of the 200 top U.S. builders constructed 100% of its homes to a third-party standard, while 38.5% reported that some of the homes were constructed using a third-party standard, while 12.5% stated that none of their homes were built to a third-party standard.
“The decision to offer homes that are high-performance, energy-efficient, non-toxic, sustainable--whatever the preferred term--involves many considerations and builders must weigh expenses and impediments against potential benefits,” according to Builder magazine.
Read the court decisionRead the full story...Reprinted courtesy of
Park Avenue Is About to Get Something It Hasn’t Seen in 40 Years
February 05, 2015 —
David M. Levitt – BloombergSometime next week, a metal frame will go up around the blocky brick tower at Manhattan’s 425 Park Ave., designed to protect pedestrians from falling objects. It’s a prelude to the building’s demise.
In about three years, if all goes according to plan, the site will have a new Norman Foster-designed skyscraper more than twice the height of the existing one. The replacement would be the first new office building in almost four decades on what the developer, David Levinson, called New York’s “grand boulevard of commerce.”
Read the court decisionRead the full story...Reprinted courtesy of
David M. Levitt, Bloomberg