Nevada Supreme Court Rejects Class Action Status, Reducing Homes from 1000 to 71
July 02, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Las Vegas Review-Journal reported that the “Nevada Supreme Court has rejected a request for class action status for claims of damaged stucco from faulty construction by Del Webb Communities involving nearly 1,000 Sun City Summerlin residents,” however, “the court upheld the award of damages to 71 homeowners following a jury trial in Clark County District Court in 2008.”
The case began in 2003, and the Las Vegas Review-Journal referred to it as “one of the largest construction-defect cases in Nevada history.” But District Judge Allan Earl denied class action lawsuit in 2006. “Attorneys were seeking $70 million for the homeowners.” In 2008, another court “determined that only 71 homeowners merited compensation totaling $4 million for the stucco issues.”
According to the Las Vegas Review-Journal, “[h]omeowners alleged that Del Webb failed to install metal screeds that would protect homes from water damage, and as a result, the homes suffered from cracked stucco, mold and weakened walls.”
Read the court decisionRead the full story...Reprinted courtesy of
Thank Your Founding Fathers for Mechanic’s Liens
August 04, 2015 —
Craig Martin – Construction Contract AdvisorYep, our founding fathers, Thomas Jefferson and James Madison specifically, Craig Martin, Construction Attorney Lamson Dugan & Murray LLPwere responsible for proposing the first mechanic’s lien laws in the United States. Mechanic’s liens were not a new concept when the first law was passed in the United States; France, Spain and other countries already had them. But, in England, where landownership was limited to the upper classes, the concept of giving a tradesman an interest in the land for his labors was a truly foreign concept.
The Early Years—Pre Mechanic Lien
In the 1700s, there was no right to a mechanic’s lien. The possession of land was never deemed to be changed by its improvement and the laborer or material supplier was held to have acquired no right of lien in the property. The only remedy the laborer or material supplier had was to bring an action against the land owner. If the laborer or material supplier obtained a judgment, he would acquire the lien of a judgment creditor. A Treatise on the law of Mechanics’ Liens on Real and Person Property, 1893.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
From Singapore to Rio Green Buildings Keep Tropical Tenants Cool
June 07, 2021 —
Andrew Janes & Shawna Kwan - BloombergOn a typically hot and humid afternoon in Singapore, a fresh breeze blows beneath the canopy of the South Beach development, keeping temperatures several degrees cooler than on the surrounding streets.
The rippling 280-meter (919 feet) wave of steel-and-aluminum runs the length of the Norman Foster-designed complex, funneling prevailing winds over outdoor patrons of restaurants and bars and saving on air conditioning for the mixed-use complex. The canopy is covered with solar panels and catches rainwater to irrigate the gardens.
Offices and apartment blocks designed to be green are springing up all over the world as architects reverse almost a century of trying to insulate workers from nature and instead try to adapt structures to their natural surroundings. The change is being driven by stricter building codes, a desire to cut energy costs and, in particular, demands from corporations and startups that need to show shareholders and customers they are meeting environmental standards.
Reprinted courtesy of
Andrew Janes, Bloomberg and
Shawna Kwan, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Appraisal Panel Can Determine Causation of Loss under Ohio Law
February 19, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court granted the insured's motion to compel an appraisal that would include a determination of causation of the loss. Eagle Highland Owners Association v. State Farm Fire and Casualty Co., 2023 U.S. Dist. LEXIS 220937 (S.D. Ohio Dec. 12, 2023).
Plaintiff argued its property suffered wind and hail damage from a storm on June 18, 2021. A claim was submitted to State Farm. State Farm's investigation determined the loss to be $0.00. Plaintiff's investigator determined the loss to be $586,647.08 in repair costs.
State Farm opposed appraisal because, in its view, the damage arose from a loss in 2019, not from the June 18, 2021 storm. Plaintiff submitted a loss claim in 2019 for damage that State Farm alleged was exactly the same as the damage alleged in the loss claim for the June 18, 2021 storm. Therefore, State Farm did not view the matter as a dispute over an amount of loss, but rather over whether a loss even occurred on June 18, 2021.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Construction Suit Ends with Just an Apology
February 10, 2012 —
CDJ STAFFAfter suing a contractor for failing to complete the remodeling of their home, an Orange County couple has settled for an apology. Douglas J. Pettibone represented the contractor, who had lost his business after a broken neck, multiple surgeries, and an addiction to pain medicine. Mr. Pettibone represented his client pro bone. The case was settled in arbitration by JAMS.
Mr. Pettibone noted that his client gave “a heartfelt and very moving apology.” The remodeling was completed by another contractor, two years after Thorp Construction stopped work on the project. After the apology, the case was dismissed.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
New York Court Permits Asbestos Claimants to Proceed Against Insurers with Buyout Agreements
December 06, 2021 —
Patricia B. Santelle & Frank J. Perch, III - White and Williams LLPA recent New York federal district court decision addresses a number of issues in the context of asbestos coverage involving an insolvent insured, holding that policy buyout agreements between the insured and its insurers did not bar actions by certain tort judgment creditors against some of the settling insurers, and further finding that such agreements can constitute fraudulent conveyances, especially where the proceeds of the settlement are not reserved for payment of insured claims.
In the litigation pending in the Western District of New York (Mineweaser v. One Beacon Insurance Company, et al., No. 14-CV-0585A), certain asbestos plaintiffs sought recovery from excess insurers for judgments obtained against an insolvent asbestos supplier (Hedman Resources, formerly known as Hedman Mines), which ceased operations in 2007 due to insolvency. Hedman had at one time been a subsidiary of Gulf & Western. As of 2009-2011, the excess insurers of Gulf & Western were advised of exhaustion of primary insurance as well as Hedman’s insolvency.
Reprinted courtesy of
Patricia B. Santelle, White and Williams LLP and
Frank J. Perch, III, White and Williams LLP
Ms. Santelle may be contacted at santellep@whiteandwilliams.com
Mr. Perch may be contacted at perchf@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
U.K. Developer Pledges Building Safety in Wake of Grenfell
April 19, 2022 —
Ryan Hesketh - BloombergCrest Nicholson Plc intends to sign the building safety pledge set up in the aftermath of the Grenfell fire in 2017 to improve standards that may cost the U.K. developer as much as 120 million pounds ($157 million).
The company’s best estimate of further liability as a result of the pledge would be 80 million pounds to 120 million pounds, according to a statement Tuesday. Since 2019, Crest Nicholson has recorded 47.8 million pounds of net charges from obligations imposed after the fire at Grenfell Tower in London in which flammable cladding materials contributed to the deaths of 72 people.
The Secretary of State for the Department for Levelling Up, Housing and Communities announced in January the government’s intention to increase the legal obligation on developers to fix potentially dangerous buildings. Since then, Crest Nicholson has engaged in “intensive dialogue” with the government about the new guidelines, resulting in the decision to sign the pledge, the firm said in the statement.
The new restrictions will be enacted in law through proposed amendments to the Building Safety Bill that is currently passing through parliament. Crest Nicholson is currently considering whether any further regulatory approvals are required in respect of the proposed laws, according to the statement.
Read the court decisionRead the full story...Reprinted courtesy of
Ryan Hesketh, Bloomberg
Harmon Towers Duty to Defend Question Must Wait, Says Court
March 01, 2012 —
CDJ STAFFThe Harmon Towers project in Las Vegas was eventually halted short of the planned forty-seven stories after “it was determined that there was substantial defective construction, including defective installation of reinforcing steel throughout the Harmon.” The American Home Insurance Company and Lexington Insurance Company put forth a claim that they had no duty to defend Perini Construction, the builder of the defective Harmon Towers. Further, American Home seeks to recover the monies American reimbursed Perini. The United States District Court of Nevada ruled in the case of American Home Assurance Co. v. Perini Building on February 3, 2012.
The two insurance companies covered Perini and its subcontractors, Century Steel, Pacific Coast Steel, and Ceco Concrete Construction. Century Steel was the initial subcontractor for the reinforcing steel; they were later acquired by Pacific Coast Steel. In this current case, Perini Construction is the sole defendant.
Perini sought a dismissal of these claims, arguing that without the subcontractors joined to the case, “the Court cannot afford complete relief among existing parties.” The court rejected this claim, noting that the court can determine the duties of the insurance companies to Perini, which the court described as “separate and distinct from those of the subcontractors.” The subcontractors “have not claimed an interest in the subject matter of the action.” The court concluded that it could determine whether Perini was entitled or not to coverage without affecting the subcontractors. The court rejected Perini’s claim.
Perini also asked the court to abstain from the case, arguing that it was better heard in a state court. The court noted that several considerations cover whether a case is heard in state or federal courts. The court noted that if the case weighed heavily on state law, the state courts would be the obvious location. Further, if there were a parallel action in the state courts, “there is a presumption that the whole suit should be heard in state courts.” This is, however, no parallel state suit, although the court noted that Perini has “threatened” to do so.
However, the issue of who is to blame for the problems at Harmon Towers has not been resolved. The court concluded that until the “underlying action” was concluded, it was premature to consider the issues raised in this case while the earlier lawsuit was still in progress. The court denied Perini’s motion to dismiss the case. Given that the outcome of the earlier construction defect case may lead to further litigation in state court, the District Court granted Perini’s motion to abstain, but staying their judgment until the construction defect case is resolved.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of