DoD Issues Guidance on Inflation Adjustments for Contractors
August 15, 2022 —
Jennifer Harris & Abby Salinas - ConsensusDocsThe Department of Defense (“DoD”) recently issued a memorandum to contracting officers (“COs”) guiding the use of economic price adjustment (“EPA”) clauses to address inflation-related cost increases. The memorandum, entitled Guidance on Inflation and Economic Price Adjustments, comes as the year-over-year inflation rate rose to 8.6% in May, and contractors with fixed-price contracts seek ways to recover their rising costs. EPA clauses allow the parties to mitigate cost risks that present themselves as a result of circumstances beyond the contractor’s control, e.g., inflation and supply chain price fluctuations. Generally, an EPA clause will dictate that the Government bear the cost risk up to a mutually agreed-upon ceiling. EPA clauses apply to the cost portion of a contract, but do not normally apply to the profit. DFARS PGI 216.203-4.
Memorandum: No CO Authority to Grant Contractual Relief Absent an EPA Clause
The memorandum states that absent an existing EPA clause, COs do not have the authority to provide contractual relief for unanticipated inflation under a firm-fixed-price contract.
Reprinted courtesy of
Jennifer Harris, Peckar & Abramson, P.C. (ConsensusDocs) and
Abby Salinas, Peckar & Abramson, P.C. (ConsensusDocs)
Ms. Harris may be contacted at jharris@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
The Godfather of Solar Predicts Its Future
October 02, 2023 —
Oscar Boyd, Akshat Rathi, & Christine Driscoll - BloombergSetting world records. Combing through warehouses of old electronics. Seeding the Chinese solar industry from afar. This is the life of Martin Green, a professor at the University of New South Wales in Sydney and the director of the Australian Centre for Advanced Photovoltaics.
Green’s work on solar panel design made the modern solar industry possible: 90% of solar panels made last year were based on his designs. He’s still going strong, too, regularly breaking new records in the pursuit of the perfect solar panel.
This week on
Zero, Akshat Rathi sits down with the man many call “the godfather of solar” to hear firsthand how it happened, the next record he wants to break and whether solar panels are destined for space.
Reprinted courtesy of
Oscar Boyd, Bloomberg,
Akshat Rathi, Bloomberg and
Christine Driscoll, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Homebuilders Call for Housing Tax Incentives
May 10, 2013 —
CDJ STAFFThe National Association of Home Builders has asked Congress to support tax incentives for home buyers and renters, including the Low Income Housing Tax Credit and the mortgage interest deduction. Robert Dietz, an economist at the NAHB, noted that in 2009, 35 million home owners were able to claim the mortgage deduction. Dietz responded to arguments that the deduction simply lead to people buying bigger homes by saying that “the need for a larger home created the higher loan deduction, not the other way around.”
The NAHB notes that one hundred new single-family homes creates more than 300 jobs and generates substantial tax revenues. “Housing provides the momentum behind an economic recovery because home building and associated businesses employ such a wide range of workers” said Dietz.
Read the court decisionRead the full story...Reprinted courtesy of
Wisconsin Federal Court Addresses Scope Of Appraisal Provision In Rental Dwelling Policy
September 05, 2022 —
James M. Eastham - Traub LiebermanIn Higgins v. State Farm Fire & Cas. Co., No. 22-C-198, 2022 U.S. Dist. LEXIS 117477 (E.D. Wis. July 5, 2022), the Court addressed the often disputed question of whether an appraisal provision in an insurance policy is limited to disputes over valuation or extends beyond valuation to causation and/or coverage. The underlying loss in the Higgins case involved a fire at a rental dwelling owned by the Plaintiff and insured by State Farm under a Rental Dwelling policy for, among other things, fire losses. Subsequent to being notified of the fire, State Farm investigated and provided the Plaintiff with its estimated cost of repair. Plaintiff disputed the estimate, including the repairs necessary, and also sought additional sums for debris removal and lost rent.
The insurance policy at issue in Higgins included an appraisal provision which provided: “If you and we fail to agree on the amount of loss, either one can demand that the amount of the loss be set by appraisal.” Pursuant to this provision, Plaintiff demanded that State Farm submit to an appraisal to resolve the parties' disagreements. State Farm responded by indicating that it would enter into appraisal over the areas where there were "pricing differences" but not areas where there were "scope differences." According to State Farm, there were a number of issues regarding the scope of repairs necessary to restore the dwelling to its pre-loss condition. Plaintiff disagreed with State Farm's position and did not seek to move forward with the appraisal process on only the items State Farm identified as appropriate for appraisal.
Read the court decisionRead the full story...Reprinted courtesy of
James M. Eastham, Traub LiebermanMr. Eastham may be contacted at
jeastham@tlsslaw.com
Presenting a “Total Time” Delay Claim Is Not Sufficient
September 12, 2022 —
David Adelstein - Florida Construction Legal UpdatesWhen presenting a delay-type of claim on a construction project, a claimant MUST be in a position to properly PROVE the claim. Trying to present a delay claim loosey-goosey is not a recipe for success. In fact, it can be a recipe for an easy loss. This is not what you want. To combat this, make sure you engage a delay expert that understands delay methodologies and how to calculate delay and do NOT present a total time claim. Presenting a delay claim using a total time approach, discussed below, makes it too easy to attack the flaws and credibility of the approach. Per the discussion of the case below, a total time claim with a contractor that used its project manager, versus a delay expert, to support its claim turned the contractor’s claim into a loss.
In French Construction, LLC v. Department of Veteran Affairs, 2022 WL 3134507, CBCA 6490 (CBCA 2022), a contractor submitted a delay claim to the government for almost $400,000. The contractor was hired to construct a two-story corridor to connect hospital buildings. The contractor was required to be complete within 365 days. It was not. The contractor was seeking 419 days of delay from the government. The contractor’s “delay expert” was its project manager who compared the contractor’s as-planned schedule to an as-built schedule he prepared for the claim.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Tennessee Looks to Define Improvements to Real Property
January 27, 2020 —
Lian Skaf - The Subrogation StrategistFor subrogation practitioners dealing with an installation-based statute of repose, knowing what is an improvement to real property is the first battle in what can, but does not have to be, a long fight. Like many other states, Tennessee’s statute of repose bars claims based on improvements to real property. Tennessee’s statute of repose runs four years after substantial completion of the improvement. See Tennessee Code Ann. § 28-3-202. In the case of Maddox v. Olshan Found. Repair & Waterproofing Co. of Nashville, L.P., E A, 2019 Tenn.App. LEXIS 464, 2019 WL 4464816, the Court of Appeals of Tennessee examined whether or not the work done by the defendant, Olshan Foundation Repair & Waterproofing Co. of Nashville, L.P., E.A. (Olshan) — which addressed bowing walls, cracks in the foundation and walls and water intrusion — qualified as improvements to real property for the purposes of the statute of repose. The court held that the work by Olshan essentially amounted to repairs, and did not qualify as improvements to real property.
In Maddox, the plaintiff, Rachel Maddox (Maddox), noticed cracking in her home in 2005 and hired Olshan to assess the issue and conduct necessary repairs. Olshan made several recommendations and the parties agreed on Olshan’s proposal for the price of $27,000. From their initial work in 2005 until late 2011, Olshan visited the property several times to address ongoing structural issues with the home. Eventually, eight months after Olshan told Maddox they could not fix the house and failed to return her phone calls, Maddox filed suit, alleging fraud against the company.
After a three-day bench trial, the trial court found in favor of the plaintiff for $187,000, plus $15,0000 in punitive damages. Among other holdings, the court rejected Olshan’s statute of repose defense. Olshan appealed, raising the statute of repose issue again.
Read the court decisionRead the full story...Reprinted courtesy of
Lian Skaf, White and Williams LLPMr. Skaf may be contacted at
skafl@whiteandwilliams.com
Resolve to Say “No” This Year
January 26, 2016 —
Christopher G. Hill – Construction Law MusingsWe hear all of the time how to “get to ‘yes'” and how doing so can lead to more business and of course more business leads to more profits. Purely logical, right? Without construction owners with work for general contractors to perform and general contractors hiring subcontractors to perform that work, construction grinds to a halt and clients and friends of mine in the construction industry don’t make money. For this to happen, “yes” has to happen more often than not. So, why the title of this post?
Chalk it up to spending much if not all of my time as a construction attorney either anticipating or dealing with the Murphy’s Law ruled nature of the construction world or to the “Monday morning quarterback” nature of my profession, but I see numerous instances where not taking the job or signing the bad contract would have led to a better outcome than performing the work. What do I mean by this? I mean that as a construction company (particularly one that is lower down the “payment chain” and therefore less in control of the flow of money), you need to carefully evaluate not only the contract presented, but whether you get a good feeling about the party with whom you are contracting.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Make Your Business Great Again: Steven Cvitanovic Authors Construction Today Article
April 20, 2017 —
Steven M. Cvitanovic - Haight Brown & Bonesteel LLPThere is a lot of uncertainty regarding how President Trump’s immigration and trade policies will affect the construction industry. In his Construction Today article, Partner Steven Cvitanovic discusses how businesses can remain competitive and profitable during this period of uncertainty, including updating contract documents, recruiting and retaining employees, and increasing cybersecurity efforts.
“If you do not know when your contract documents were last updated, it’s probably been too long,” writes Cvitanovic. “Unlike wine, contract documents only get worse with age.” Cvitanovic advises teams to sit down together and review contracts to see if they still meet the firm’s needs.
Read the court decisionRead the full story...Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLPMr. Cvitanovic may be contacted at
scvitanovic@hbblaw.com